Every published Indian data-centre capacity number is a sum of unlike things. Gridvik’s own registry was no exception: 2,420.37 MW across 86 records, in which an operating 0.3 MW exchange building and a 512 MW incentive approval carried equal weight, and in which gross facility power was added to IT load. This document rebuilds that number from the 242 source records using four rules, each of which can be checked against the audit file published beside it. The result is not one figure. It is three: 778.69 MW operating, 499.00 MW under construction, and 2,236.00 MW announced, approved or unverified. The old headline was larger than the first two combined and smaller than the third. It described no single thing, which is why it could not survive a diligence call.
1At a glance
2One number, four different things
| Component | Size | What it was measuring |
|---|---|---|
| Operating buildings | about 778.7 MW | Energised capacity in named facilities |
| Under construction | about 499.0 MW | Committed capital, no revenue yet |
| Announced or planned | about 700 MW | Intentions with dates |
| Stage unverified | 601 MW | Five AirTrunk facilities whose status the file could not confirm |
| A project approval | 512 MW | AM AI Factory Vizag, approved and incentivised, construction unverified |
| Gross facility power | about 106 MW | CapitaLand towers counted at gross, not IT load |
| Unresolved basis | about 1,456 MW | Records whose published figure may be facility power rather than IT |
Two records are enough to show why the old number could not be defended. PRJ-060, the AM AI Factory at Visakhapatnam, contributed 512 MW — 21% of the entire total — on an approved incentive application with unverified construction. And five AirTrunk facilities contributed 601 MW — another 25% — with a stage the source register itself records as unverified.
Put differently, 46% of the old headline came from records that are not operating buildings. That does not make them worthless. An approved 512 MW AI factory is one of the most important facts in the registry. It simply is not capacity, and adding it to a 0.3 MW telephone-exchange building produces a number that means nothing.
A capacity total is the first thing an acquirer, a lender or a hyperscale site-selection team asks for. If the first number you give them does not survive one follow-up question, nothing else in the file gets read.
The old figure was not exaggerated in bad faith — it was a sum of every record someone had marked additive. The failure was the flag, not the motive.
What follows is the fix, and it is deliberately unflattering: the defensible number is roughly half the old headline.
3The four rules
Every decision in the audit file follows one of four rules. Each is stated so that a reader can disagree with it, and if they do, recalculate in minutes from the published CSV.
| Rule | What it does | Failure it prevents |
|---|---|---|
| 1 — Scope | One basis per record: IT load where the operator publishes it, otherwise the publisher’s own figure, flagged as facility basis | Adding gross facility power to IT load, which inflates a total by 20 to 40% |
| 2 — Level | Count the most granular record carrying capacity. A campus, city portfolio, programme, acquisition or tenant deployment is a container and is never counted | The same steel counted two or three times, or — the worse error — counted zero times |
| 3 — Stage | Every counted record lands in exactly one tier: operating, building, or pipeline | An approved application and an energised building carrying the same weight |
| 4 — Macro | MoUs, financing events, market references, network records and investment programmes are not capacity and are excluded | A 2.8 GW utility opportunity pipeline appearing in a data-centre total |
Rule 2 is the one that changed the most numbers, and it cut in both directions. It removed 72 MW from PDG Chennai, a campus claim with no building breakdown, and it added 171 MW of STT GDC Palava buildings that had previously been marked non-additive along with their parent campus — so the capacity had vanished from the total entirely.
That second case was a systematic error. Forty-five container records and their children were all flagged non-additive, which meant a campus could be recorded, described and dated in the file while contributing nothing to the sum. West Bengal was the clearest casualty: four operators, about 95 MW published, and 1.08 MW counted.
A container is not wrong. A campus figure is often the only thing an operator publishes, and the STT Palava campus at 400 MW is a real statement about a real site.
But converting a container into building capacity requires inventing a building schedule. This registry does not invent. So the 45 container ceilings are reported separately, at their published figures, and excluded from every total on this page.
Their combined published value is 22,200.8 MW — which is the correct denominator for the question how much has India announced, and the wrong one for how much does India have.
4The reconciled ladder
| Tier | Records | MW | What it counts |
|---|---|---|---|
| Operating | 49 | 778.69 | Named buildings the source records as operational, live or expanding |
| — of which IT basis | — | 602.7 | Operator-stated IT load, excluding facility power and unstated bases |
| Under construction | 13 | 499.00 | Physically being built, capital committed, no revenue |
| Pipeline | 68 | 2,236.0 | Announced, planned, approved or stage-unverified |
| Operating plus building | 62 | 1,277.69 | The defensible number for capacity that exists or is being built |
| All counted records | 130 | 3,513.69 | Every tier, for comparison with the old headline |
The single most useful number in this registry is 778.69 MW — verified operating capacity across 49 named buildings. It is a floor, not a census: it counts only capacity that carries a building-level record, so a facility with no record of its own contributes nothing even if it is running.
602.69 MW of that 778.69 is on an IT-load basis and the rest is published facility power or an unstated basis. That split matters more than the total. A wholesale customer buys IT load; a utility sells facility power. Mixing them is how a 62 MW facility becomes a 62 MW IT claim.
| Basis | MW | What a reader should do with it |
|---|---|---|
| IT (operator-stated) | 1,441.9 | Comparable across operators; use for pricing per MW |
| IT (bare) | 7.2 | Scope states IT but no figure was restated |
| Facility or unresolved | 1,456.1 | Divide by a stated PUE before comparing with IT |
| Basis not stated | 608.5 | Old records; treat as IT until checked |
1,456 MW of the reconciled total is facility power or an unresolved basis. Converting it to IT load requires a PUE assumption per record, and this file does not make one globally — the declared PUEs range from 1.40 to 1.70, so a blanket 1.5 would misstate individual buildings by up to 13%. The basis is flagged per record in the audit file instead.
5Where the 2,420.37 MW went
| Step | MW | Explanation |
|---|---|---|
| Previous headline | 2,420.4 | 86 records flagged additive |
| Removed: container converted to ceiling | −72.0 | PDG CH1 Chennai campus at 72 MW had no building breakdown |
| Removed: gross power restated to IT | −68.0 | Four CapitaLand towers, previously 200 MW, restated to 132 MW on an IT basis |
| Removed: IT rebase | −1.0 | STT GDC Ahmedabad 1, 4 MW restated to 3 MW |
| Added: children of orphaned containers | +1,234.3 | Records whose parent and self were both marked non-additive |
| Reconciled total | 3,513.69 | 130 records across three tiers |
The additions are the part that would never have been found by inspection. When a campus row and its building rows are all marked non-additive, nothing in any report looks wrong — the records are present, dated and sourced. They simply never enter a total.
| Family | Records | MW | Why it had been lost |
|---|---|---|---|
| STT GDC | 26 | 486.7 | Campus and city-portfolio rows flagged non-additive; every building under them inherited the flag |
| NTT Global | 11 | 261.6 | Mahape, Noida 2, Bengaluru 4 and Chennai 2 buildings under non-additive campuses |
| CtrlS | 6 | 161.8 | Six Mumbai, Chennai, Delhi and Kolkata buildings with no additive parent |
| Princeton Digital | 2 | 148.0 | MU1 expansion phase, child of a non-additive campus |
| Sify | 2 | 69.2 | Rabale Tower 5 and Siruseri, the estate’s two largest facilities |
| Nxtra | 3 | 22.0 | Three Chennai buildings under non-additive city records |
Sify Rabale is the case worth remembering. It is the operator’s largest campus, a DGX-Ready certified campus by its own account, and it publishes 96.94 MW built across five towers. Under the previous method it contributed nothing to the national figure, because the campus row and the tower rows were all marked non-additive. The reconciliation recovers 43.3 MW — Tower 5 only, because the other four towers have no separate records. Even the corrected figure is a floor.
6Operators, ranked by operating capacity
| Operator | Operating | Building | Pipeline |
|---|---|---|---|
| NTT Global Data Centers | 273.2 | — | 169.4 |
| Yotta Data Services | 145.8 | — | 120.0 |
| Sify Technologies | 125.1 | — | 30.0 |
| Princeton Digital Group | 48.0 | 100.0 | — |
| Nxtra by Airtel | 38.0 | — | 238.2 |
| Adani Enterprises | 35.0 | — | 6.0 |
| STT GDC India | 35.0 | 131.5 | 329.2 |
| CapitaLand India Trust | 34.0 | 61.0 | 37.0 |
| CtrlS Datacenters | 33.1 | 12.0 | 193.2 |
The largest operating data-centre operator in India, on this registry’s evidence, is NTT Global Data Centers at 273.2 MW. That is a correction to an earlier claim on the Yotta pages, which described Yotta as the largest additive operator at 236 MW — a figure produced by adding its 1 MW and 2 MW facilities to its 60 and 120 MW ones without separating stage.
On operating capacity the order is NTT 273.2, Yotta 145.8, Sify 125.1. On pipeline the order reverses: STT GDC 329.2 MW announced against 35.0 MW operating, and CtrlS 193.2 against 33.1. Those ratios are the most interesting numbers on this page.
Nxtra by Airtel is the other outlier: 38.0 MW operating against 238.2 MW in pipeline. Eighteen Nxtra facility records are marked stage-unverified in the source register, which is why they sit in the pipeline tier despite the facilities being real and in service. That is a data-quality limit of this file, not a market statement, and it is the largest single item in the review queue below.
7States, reconciled
| State | Old figure | Operating | Building | Pipeline | Total |
|---|---|---|---|---|---|
| Maharashtra | 786.4 | 376.7 | 355.0 | 820.2 | 1,551.9 |
| Uttar Pradesh | 331.1 | 163.5 | 39.0 | 248.4 | 450.9 |
| Tamil Nadu | 296.6 | 115.9 | 66.0 | 201.6 | 383.5 |
| Karnataka | 90.7 | 54.7 | — | 125.8 | 180.5 |
| Telangana | 341.3 | 19.9 | 27.0 | 283.4 | 330.3 |
| West Bengal | 1.1 | 17.1 | — | 15.4 | 32.5 |
| Bihar | 12.1 | 12.1 | — | — | 12.1 |
| Madhya Pradesh | 12.0 | — | 12.0 | — | 12.0 |
| Rajasthan | 6.0 | 6.0 | — | — | 6.0 |
| Odisha | 6.8 | 5.0 | — | 1.8 | 6.8 |
Three states change character under reconciliation. Telangana’s 341.3 MW becomes 19.9 MW operating, because 283.4 MW of it is AirTrunk HYD1 and CtrlS Chandanvelly at unverified or planned stage. Andhra Pradesh’s 512.0 MW becomes 512.0 MW of pipeline and nothing operating. And Maharashtra’s 786.4 MW becomes 328.7 MW operating with 820.2 MW still to be built.
Those are not declines. They are the same facts described accurately. A state with 328.7 MW operating and 820.2 MW under construction or announced is a far more useful object than a state with “786.4 MW”.
The record pages quote state shares from the source register at the time each page was built — Maharashtra 786.4 MW, Tamil Nadu 296.6 MW, Uttar Pradesh 331.06 MW. Those figures remain the registry’s source-register view and are not silently overwritten.
The reconciled view on this page is published alongside, not on top. Two labelled numbers with a stated method are stronger in diligence than one number whose method is invisible.
If a single number is preferred, the switch is a site-wide regeneration and a re-verification of 230 pages. That work is scoped but not done.
8What is set aside
| Category | Records | MW | Why excluded |
|---|---|---|---|
| Container ceilings, excluded | 45 | 10,298.8 | Campus, portfolio and programme claims with no building breakdown |
| Container records declaring capacity, in total | 44 | 22,200.8 | The honest denominator for “India has announced” claims |
| Of which 1 GW or larger | 11 | 17,300.0 | Reliance Jamnagar 3 GW, AirTrunk Raigad 3 GW, Tata Power 2.8 GW, and eight 1 GW programmes |
| Unverified records (UNKNOWN) | 36 | 11,152.0 | Additive status never established; includes Yotta West Bengal at 250 MW |
| Macro records | — | — | MoUs, financing, network, market references, investment programmes |
| Zero-capacity records | 5 | 0.0 | Live halls that publish no megawatt figure: Iron Mountain MUM-1, MUM-2 and NCR-1, Colt Mumbai 1 and 2 |
The 1 GW-scale records deserve a note because they are the most quoted numbers in Indian data-centre press. Eleven records in this file declare 1 GW or more, 17,300 MW between them — Reliance Jamnagar at 3 GW, AirTrunk Raigad at 3 GW, Tata Power’s 2.8 GW opportunity pipeline, Reliance Bhogapuram at 1.5 GW, and eight separate 1 GW programmes from Google, Adani, AdaniConneX, TCS, Digital Connexion and High Density Data Centre.
Setting them aside is not scepticism about the companies. It is the only way to keep the words “megawatts” and “buildings” in the same sentence. A reader who wants the announcement total has it: 22,200.8 MW of declared ceilings, which is the honest denominator for a media figure like “India has announced 20 GW”.
9What is still open, and what changes
This document fixes the structure. It does not fix the source data, and four things remain open.
| Item | Size | What would close it |
|---|---|---|
| Nxtra facilities marked stage-unverified | 21 records, 238.2 MW | Confirm operating status per facility; would move up to 238 MW into the operating tier |
| AirTrunk facilities marked stage-unverified | 5 records, 601.0 MW | The single largest item in the pipeline tier; needs one commissioned-capacity statement |
| Facility-power records with no IT figure | 1,456.1 MW | A per-facility IT load or a stated PUE |
| Records with no capacity at all | 6 operating facilities | Iron Mountain and Colt publish no megawatt figure for several live halls |
| Cross-record overlaps the parent graph misses | about 14 MW suspected | Nxtra Chennai: PRJ-011 at 38 MW plus three CHE buildings at 22 MW, against a 46 MW city portfolio |
| Contracted power counted as facility power | PRJ-208, 64 MW | Colt Mumbai 3 publishes 64 MW of contracted power, not IT load; the largest single facility-basis item in the building tier |
| Container ceilings needing a building schedule | 45 records | A per-building split, which for STT GDC and CtrlS is 15 records each |
The Nxtra and AirTrunk items are worth more than everything else combined — 839 MW sitting in the pipeline tier for want of a status confirmation, against a 778.69 MW operating total. Confirming them would more than double the defensible figure. Not confirming them is why the operating number is a floor.
Three claims elsewhere in this registry are now known to be wrong and are corrected here:
| Claim | Correct position |
|---|---|
| “Yotta is the largest additive operator at 236 MW” | NTT is the largest by operating capacity at 273.2 MW; Yotta is second at 145.8 MW |
| “2,420.37 MW counted nationally” | 1,277.7 MW operating plus under construction, and 2,236.0 MW announced |
| “West Bengal has 1.08 MW; Delhi has 0 MW” | A flag artefact, not a market fact. West Bengal publishes about 95 MW; the reconciliation recovers 17.1 MW operating and 15.4 MW pipeline |
India’s named data-centre estate: 778.69 MW operating, 499.00 MW under construction, 2,236.00 MW announced — from 130 building-level records.
Every figure is traceable to a row in the audit file, and every exclusion has a written reason. That is the difference between a number and a claim.
The conservative alternative, if only operator-stated IT load is acceptable: 602.7 MW operating.
10Sources and audit file
Sources: the Gridvik India data centre master of 18 October 2026, revised 26 October 2026, 242 records across 49 fields of which 241 are distinct facilities; the Gridvik source register of 133 sources with withheld URLs; and the record-level audit file published with this document, which lists every one of the 242 records with its basis, decision, reason and reconciled megawatts. Methodology dated 26 October 2026. Figures are re-derivable by any reader from the audit file.