Every data centre press release says "1GW". None says which substation will give you 50MW, when, and at what landed cost. That is the Layer. 62 rows, public sources, Conf 1–3, pilot.
Press release = headline. Layer = whether you can energize.
MW actually sanctioned at that substation — from DISCOM ARR / CTUIL/GNA. Not the campus headline.
OK / Constrained / Queue 12–18mo — can that substation take your next 50MW?
Policy says ₹X — has money left the treasury? G.O. ≠ bank credit.
Months to energize at that landed cost — the only date your construction schedule cares about.
ARR, tariff orders, GNA registers, SLDC, POSOCO
KIADB/RIICO/MIDC G.O.s, single-window, CEIG/EC
Operator newsrooms, ET, Savills/C&W (aggregates only)
Every row: exact URL + announcement date + verified_date + Conf 1–3. We do not warrant error-free data — verify before you rely. Disclaimer →
| Project | Sanctioned | Headroom | TTP |
|---|---|---|---|
| Sify Siruseri 45MW | 45 MW · Conf 3 | OK | 8 mo |
| AdaniConneX Taloja ph1 | 80 MW · Conf 3 | Constrained | 14 mo |
| Google Vizag (prop.) | — | Queue 18mo | 24+ mo · at own risk |
Sample 3 of 62. Full pilot = 62 with Layer fields. Free 8-row preview →
Dashboard/API is in development, not yet hosted. Pilot is analyst-led: