Project record · Verified 22 Oct 2026

Adani Noida Data Centre Project 2, Sector 80Noida, Uttar Pradesh · AdaniConneX through Noida Data Centre Limited

Record PRJ-008Gautam Buddh Nagar, Uttar PradeshTier C — early stage, land constrained11 public sources cross-checked
Proposed — pre-constructionSub-lease permission reversedLand held since 2021Registry record
6MW
Registry proposal
50MW
Planned park
10ac
Plot area
₹70cr
Plot premium
Apr 2021
Allotted
2025
Sub-lease reversed

Adani holds ten acres at Sector 80 in Noida, allotted in April 2021 for ₹70 crore with a six-year build obligation, intended as a 50 MW hyperscale data-centre park developed through the AdaniConneX special purpose vehicle, Noida Data Centre Limited. The registry records a 6 MW current proposal. The reason that number is small is documented: in September 2024 Noida Authority approved sub-leasing the plot to the SPV after state-government intervention, and in June 2025 it reversed that decision.

1At a glance

Record ID
PRJ-008 — Gridvik India Data Centre Registry
Project name
Adani Noida DC Project 2 — Sector 80, Noida
Operator
AdaniConneX, through Noida Data Centre Limited — the joint-venture SPV with EdgeConneX
Location
Sector 80, Noida, Gautam Buddh Nagar district, Uttar Pradesh
State
Uttar Pradesh
Record type
Project proposal — land held, build not evidenced
Status
Planned / proposed. No construction evidenced. Sub-lease permission to the SPV was approved in September 2024 and reversed in June 2025
Capacity (registry)
6 MW current proposal. Basis — IT load versus gross — not specified in the state dashboard
Capacity (planned)
50 MW hyperscale data park, as described in Noida Authority and SPV reporting
Land
10 acres notified for allotment on 12 April 2021 at ₹70 crore, with a six-year build obligation. Regional reporting references a 20-acre allocation; the authority record refers to 10 acres
Investment
Not carried — see Limits. The state dashboard holds conflicting figures of ₹2,416 crore and ₹2,713 crore, neither reconciled
Gridvik tier
C — early stage. The land is real and the intent is documented, but the permission constraint means no build schedule can be inferred

2Capacity reconciliation

Two figures, and the difference between them is almost entirely a permissions question rather than an engineering one.

Plot allotted01Sub-lease moved02Approved03Reversed04Build05Navy = verified · Red = current stage · Grey = not yet evidenced
Figure 1Delivery stage. The plot is allotted and the sub-lease to the SPV was twice decided — approved in September 2024, then reversed in June 2025. Nothing beyond land and permissions has been evidenced.
What each figure measures
FigureDateMWScope and source
50 MWThe hyperscale data park intended at Sector 80, as described when the sub-lease to Noida Data Centre Limited was sought and approvedPlanned
6 MWThe current proposal recorded by this registry, reconciled against the Uttar Pradesh Data Centre Policy dashboard listingRegistry
50 MWDashboard figure, inherited from the original park plan and not updated to reflect the permission reversalState dashboard
20 acresAllocation referenced in regional reporting, against the 10 acres in the authority record. The discrepancy is not explained publiclyConflicting
Gridvik read

Treat 6 MW as the registry figure and 50 MW as the park intention. Neither is evidence of construction. The 50 MW number has been in circulation since 2021 and has survived the permission reversal unchanged, which is exactly why it should not be read as a build plan.

This record is a textbook case for why a two-and-a-half-year-old announcement should not be carried into a vendor pipeline without re-verification.

3Land and the sub-lease — the constraint that matters

The plot itself is unremarkable. What happened to it is the story, and it is publicly documented in unusual detail.

Plot
10 acres, Sector 80, Noida
Allotment
Notified 12 April 2021 to Adani Enterprises at ₹70 crore, with a condition to set up the data centre within six years
Intended structure
Development through Noida Data Centre Limited, the AdaniConneX SPV of which EdgeConneX is a part
Why sub-lease was needed
Adani Enterprises was the original allottee. To build through the joint-venture SPV, the plot had to be sub-leased to it
Initial position
A committee of the finance controller, chief legal adviser and an additional CEO recommended rejection, on the basis that the original allottee must complete the project and obtain an occupancy certificate first
September 2024
Approved. The Uttar Pradesh chief secretary, as chairman of Noida Authority, overturned the rejection and permitted sub-leasing, citing provisions in the amended Uttar Pradesh Data Centre Policy of 2022. The committee had itself noted that Adani Enterprises was previously allowed to sub-lease an institutional plot in Sector 62 for an IT/ITES project to an SPV — DC Development
June 2025
Reversed. Noida Authority ruled out sub-leasing the Sector 80 plot to Noida Data Centre Limited before the project is declared functional, stating it would not relax the original allotment conditions
Where that leaves it
The plot remains with Adani Enterprises. Building through the JV SPV appears blocked until the project is functional — a circular condition, since the project was to be built by that SPV

4Why this matters more than one plot of land

The commercial lesson

Adani's Sector 62 plot was permitted to be sub-leased to an SPV in 2021, and that SPV route is what allowed the flagship Noida facility to reach operation with Google as tenant. The Sector 80 plot was allotted two months earlier and has not moved, because the same permission was refused and then withdrawn.

This is what execution risk looks like in Indian data centres: not capital, not demand, not technology — a sub-lease clause in a land allotment.

For anyone tracking Noida capacity, the signal to watch is not an MW announcement. It is a Noida Authority order permitting sub-lease to Noida Data Centre Limited, or a declaration that the project is functional under the current structure.

5Timeline

  • Ten acres in Sector 80 notified for allotment to Adani Enterprises at ₹70 crore, with a six-year build condition.
  • The separate Sector 62 plot is allotted, and is later permitted to be sub-leased to DC Development Noida — the route that produced the operational facility recorded as PRJ-007.
  • Adani Enterprises applies to sub-lease the Sector 80 plot to Noida Data Centre Limited. A Noida Authority committee recommends rejection.
  • The Uttar Pradesh chief secretary approves sub-leasing after state-government intervention, citing the amended Uttar Pradesh Data Centre Policy of 2022.
  • Noida Authority reverses the position: no sub-lease before the project is declared functional, and no relaxation of the original allotment conditions.
  • Construction start, capacity build, tenant, commissioning. No public evidence of any of these as of 22 October 2026.

6What it means commercially

Straight answer for a vendor

There is nothing to sell into here. There is land, an intention for a 50 MW park, and a permission dispute. There is no building, no specification and no schedule.

What to monitor. A Noida Authority order permitting the sub-lease, a declaration that the project is functional, or an environmental clearance filing. Any of those converts this from Tier C to a trackable project, and it would move quickly if it did — the AdaniConneX delivery machine is already running in the same city at Sector 62.

Where Noida capacity actually is is Sector 62 (PRJ-007), which is operational with a Google lease and roughly 115 MW of site headroom left. That is the sellable record.

Is a procurement window estimable?
No. No credible window can be derived from a plot with a reversed sub-lease
Is it a lead?
No
Worth tracking?
Yes — the parent joint venture has capital, capability and a nearby operating site, so the project is dormant rather than dead
What would change the grade
A sub-lease order, a functionality declaration, or an environmental clearance. Any one of them
Deadline to watch
The allotment carried a six-year build condition from April 2021, implying 2027. Whether that condition has been extended is not public

7Assumptions and method

What is sourced
Plot allotment, premium, build condition, intended 50 MW park, sub-lease approval and reversal, SPV identity
What is derived
The assessment in the commercial section
Capacity figure used
6 MW as the current proposal, reconciled from the state dashboard listing. The 50 MW park intention is retained and labelled
Investment
Not carried. The dashboard holds ₹2,416 crore and ₹2,713 crore against the two Noida projects without reconciling which applies where
Additivity rule
Flagged additive as a distinct land holding, but it contributes effectively no built capacity to any total at present
Relationship to PRJ-007
Separate plot, separate allotment, separate SPV. The two are different sites and are not alternatives for the same capacity

8Limits, conflicts and open questions

The central constraint
Sub-lease to the joint-venture SPV was reversed in June 2025. The project structure is blocked on a permission, not on capital
Plot area
10 acres in the authority record against 20 acres in regional reporting. Unexplained
Capacity
6 MW proposal against a 50 MW park intention. Neither is evidence of construction
Build deadline
The six-year condition from April 2021 implies 2027. Whether it has been extended, and what penalty applies, is not public
Approvals
No environmental clearance, no construction permit and no tenant identified
Design
None published — no rack count, density, PUE or redundancy
What we will not claim
No construction status, no schedule, no tenant and no view on whether the 50 MW park will be built

9Sources

This record was compiled entirely from publicly available sources, cross-checked against one another.

Times of India, Noida Authority coverage (August 2024, June 2025)·Hindustan Times·DatacenterDynamics·Uttar Pradesh Data Centre Policy dashboard·AdaniConneX official location pages·Adani Enterprises annual digital report 2026·The Uttar Pradesh Index·Economic Times Datacenters·Blackridge / industry reporting on the Adani Noida plan·datacenters.com·Synergy Infracon

Gridvik does not publish source URLs on record pages; citations are retained in the internal source register and are available on request.

What this page is, and what it is not

This is a public-source record of a land holding and a permission dispute. It is not a record of a data centre, because no data centre has been built here.

No tender insider information, no private contact data, no operator-paid placement. Corrections are free and published with a date.