Project record · Enriched · Verified 22 Oct 2026

PDG MU1 Campus, Airoli — Navi MumbaiPrinceton Digital Group · five buildings, ~15 acres

Record PRJ-026Maharashtra — Navi MumbaiTier A — procurement-ready14 public sources cross-checked
50 MW live100 MW under constructionIndia's first OCP ReadyCampus aggregate
150MW
Campus IT design
50MW
Live · two buildings
100MW
Under construction
~15ac
Campus area
220kV
Dedicated GIS substation
35,600m²
Colocation area

PDG's MU1 campus at Airoli in Navi Mumbai is designed for 150 MW of IT capacity across five buildings on about 15 acres inside a 50-acre IT/ITES park. 50 MW is live in the first two buildings; the third, fourth and fifth add 100 MW and were under construction as of 2025, with the first phase of that expansion scheduled for delivery in 2026. It is India's first OCP Ready data centre, Mumbai's first IGBC Platinum facility, Uptime Tier III certified, and it sits beside the Kalwa substation with its own 220 kV GIS substation.

1At a glance

Record ID
PRJ-026 — Gridvik India Data Centre Registry
Project
PDG MU1 — Princeton Digital Group's flagship Indian campus
Operator
Princeton Digital Group, a Singapore-headquartered pan-Asian data-centre operator
Location
Airoli, Navi Mumbai, within a 50-acre IT/ITES park, Maharashtra
State
Maharashtra
Record type
campus_aggregate — the 150 MW contains the live 50 MW and the 100 MW expansion
Status
Live and expanding. Two buildings operational at 50 MW; three more under construction
Capacity
150 MW IT across five buildings. 50 MW live, 100 MW expansion in construction
Campus area
About 15 acres within the IT/ITES park · 35,600 m² of colocation area
Power
Dedicated 220 kV GIS substation, and the campus is located directly beside the Kalwa substation — the single most important fact about this site
Certifications
Uptime Institute Tier III (design and construction) · IGBC Platinum · OCP Ready · ISO 9001, 14001, 27001, 20000, 27017/27018, 45001, 22301
Financing
About US$160 million of green loans secured July 2025 from Axis Bank, Kotak Mahindra Bank and Canara Bank — part of PDG's US$1 billion India programme
Gridvik tier
A — procurement-ready. A live campus with 100 MW of funded construction in progress

2Campus build-out

Campus designfive buildings, ~15 acres150 MWBuildings 3–5expansion under construction100 MWBuildings 1–2live · Q4 2022 and 202550 MWTwo-thirds of the campus is still to be built. The existing 50 MW triples to 150 MW through three new buildings.
Figure 1PDG MU1 by building group. The first two buildings are live at 50 MW. Three new buildings add 100 MW — a tripling of the campus — with the first phase of that expansion scheduled for 2026.
What is live and what is being built
ElementCapacityStatusNote
Building 1Part of 50 MWLive Q4 2022Delivered in about 20 months during the pandemic
Building 2Part of 50 MWLive 2025Reported variously as taking the campus to 48 MW or 50 MW
Buildings 3–5100 MWUnder constructionFirst phase of the expansion scheduled for delivery in 2026
Campus total150 MWDesignFive buildings, about 15 acres
Gridvik read — two-thirds of this campus is still to be built

A 150 MW headline on a campus with 50 MW live is not a misrepresentation — it is a five-building design at 40% completion. But the distinction decides how a vendor plans: 100 MW of funded, permitted, in-construction capacity is the largest single live build opportunity in Navi Mumbai outside NTT and Sify.

The 48-versus-50 MW discrepancy on the live buildings appears in PDG's own materials across two dates. Gridvik uses 50 MW, consistent with the operator's current facility page, and notes the 48 MW figure.

The delivery record is worth knowing: the first building took about 20 months, through the pandemic, on a site that already had a substation next door. That is the fastest credible build time in the Mumbai market and it is not an accident.

3Power — the decisive advantage

Almost everything that makes this campus commercially strong comes down to one thing: it was sited next to a substation.

The location
MU1 sits directly beside the Kalwa substation. That is a circumstance of site selection, not engineering, and it is the hardest advantage in Indian data centres to replicate
Site substation
A dedicated 220 kV GIS substation on the campus. Gas-insulated switchgear at 220 kV is the top end of Indian data-centre power infrastructure — most facilities connect at 110 kV or 33 kV
Why 220 kV matters
Connecting at a higher voltage reduces losses, reduces the number of transformation stages, and — most importantly — increases the size of load the state transmission utility will sanction. A 150 MW campus needs that headroom; a 110 kV connection supports materially less
What it changes in the equipment list
GIS switchgear at 220 kV, power transformers, protection and control systems, and the associated civil works are a separate and much larger package than a 110 kV installation. This is the single largest electrical contract on the site
Comparison
NTT's Noida 2 publishes no substation rating. Sify's Rabale runs 110 kV for Towers 1–3 and 220 kV GIS for Towers 4–6. Microsoft publishes nothing. On substation disclosure and specification, PDG and Sify lead the Indian market
Renewables
The expanded campus is contracted to be powered 50% by renewable energy
Why this matters to a vendor
A 220 kV connection means the HV package is live, large and specialist. Vendors who only sell at LV/MV distribution level are not in that conversation

4Certifications and design

OCP Ready
India's first Open Compute Project Ready facility. OCP is a hyperscaler-driven open hardware standard for racks, power shelves and server designs. OCP Ready status means the facility can accept OCP-format equipment without modification — a meaningful qualification for hyperscale tenants that specify OCP hardware
IGBC Platinum
Mumbai's first IGBC Platinum-certified data centre
Uptime Tier III
Design and construction certification — concurrently maintainable, meaning any component of the power or cooling path can be taken offline for maintenance without dropping the IT load
Cooling
PDG describes the design as accommodating high rack density requirements and hybrid cooling needs. Hybrid cooling implies provision for both chilled water and liquid cooling in the same building — the current design answer to tenants who cannot yet say how much of their estate will be GPU-based
Renewable target
50% of campus power contracted as renewable on completion
Management systems
ISO 9001, 14001, 27001, 20000, 45001, 22301 and the 27017/27018 cloud-security extensions — the fullest published certification stack of any Indian campus in this registry
What is not published
Rack count, rack density, PUE, chiller architecture, UPS topology, generator configuration and fuel autonomy. The certifications are public; the engineering numbers are not

5The green financing

What a green loan actually requires

In July 2025 PDG secured about US$160 million in green loans for MU1, from Axis Bank, Kotak Mahindra Bank and Canara Bank — bringing PDG's cumulative green loan commitments across Asia to US$728 million.

A green loan is not a marketing label. It requires the borrower to commit to defined environmental performance criteria — typically certification, energy efficiency and renewable procurement — and to report against them. That has three consequences worth understanding.

Consequence 1 — the specification is constrained
Once a facility is financed against green criteria, equipment choices that worsen measured performance become difficult to justify. Expect the cooling and electrical plant to be selected partly on efficiency, not only on price. For a vendor, an efficiency claim is worth more here than a price reduction
Consequence 2 — the lenders are Indian
Axis, Kotak and Canara are domestic banks, not development finance. This is significant: it means Indian bank credit is now available at scale for data-centre build-out, which removes what was historically the binding constraint on Indian operators
Consequence 3 — the paper trail exists
Green-loan reporting creates a documented, filed record of facility performance. Over time this will be the best source of verified PUE and energy data for Indian data centres, better than anything the operators publish voluntarily
The programme it sits in
The US$160 million supports the US$1 billion India programme announced in late 2024, which covered the MU1 expansion to 150 MW and the 72 MW CH1 campus in Chennai
What is not disclosed
The loan margin, the specific green criteria, the reporting cadence, and whether the interest rate steps down if targets are met

6Timeline

  • The first MU1 building is delivered — in about 20 months, through the pandemic.
  • PDG announces a US$1 billion India programme: MU1 expands from two to five buildings, taking the campus to 150 MW across about 15 acres, and PDG enters Chennai with a 72 MW campus. First phase of the 100 MW expansion scheduled for 2026.
  • PDG acquires 500 MW of powered land across Mumbai, Chennai, Johor and Jakarta, occupying over 88 acres — the land bank behind the later 210 MW acquisition.
  • The second MU1 building goes live, taking the campus to about 50 MW.
  • About US$160 million of green loans secured for MU1 from Axis Bank, Kotak Mahindra Bank and Canara Bank, bringing PDG's cumulative green loan commitments to US$728 million.
  • PDG becomes the first in Asia-Pacific to reach OCP Ready v2 hyperscale status; MU1 is described as providing 150 MW of IT capacity across five buildings on a dedicated 220 kV GIS substation.
  • PDG announces a further 210 MW acquisition in Mumbai and Hyderabad, taking its India operating and planned capacity to about 1 GW — see PRJ-025.
  • First phase of the 100 MW MU1 expansion scheduled for delivery

7Procurement

Read this before the table

Two of five buildings are live. Three are funded, permitted and under construction. This is the most actionable large build in Mumbai. Everything below is a Gridvik estimate.

Procurement window and scope
Gridvik assessment · 22 Oct 2026
Order window
Now through 2027. The 100 MW expansion was scheduled to begin delivering in 2026, which means major equipment orders were placed in 2025–2026 and fit-out runs into 2027. The electrical package — driven by the 220 kV GIS substation — is the largest element.
Procurement heat
High. Green-loan-funded, part of a US$1 billion India programme, with a hyperscale tenant profile and a demonstrated fast-build capability.
Who buys
PDG centrally, with group engineering standards applied through the India team. PDG is a specialist hyperscale developer rather than an incumbent Indian operator, which in practice means a smaller and more accessible vendor panel
DG / gensets (indicative)
At 150 MW IT with N+1 redundancy, roughly 190–220 gensets of 2,000–2,250 kVA class across the campus. The 100 MW expansion alone implies about 130–150 units. Mumbai requires CPCB IV+ compliance
UPS (indicative)
Tier III concurrently maintainable implies at minimum N+1 on UPS; hyperscale single-tenant floors increasingly use distributed battery at the rack, which reduces centralised UPS content per MW
Cooling (indicative)
Hybrid by design. PDG publishes hybrid cooling capability, which means both chilled-water CRAH plant and liquid-cooling provision exist in the same buildings. For a vendor this is the ideal case: one order, two cooling categories, and a green-loan requirement that rewards efficiency over purchase price
Categories in scope
220 kV GIS switchgear · power transformers · protection and control · DG and gensets · UPS and rack-level battery · PDUs and busway · chillers, CRAH and dry coolers · CDUs and liquid cooling · high-density racks and containment · structured cabling and fibre · fire detection and suppression · BMS/DCIM · fuel storage · water treatment · renewable PPAs
Decision role
Public decision roles — in GridFeed
Stage-change history
Dated change log — in GridFeed
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

8Assumptions and method

What is sourced
Campus capacity and building split, live capacity and building dates, campus and colocation area, substation specification, certifications, green loan amount, date and lenders, renewable target, programme context
What is derived
Only the procurement section
Capacity figure used
150 MW campus design; 50 MW live. The 48 MW figure reported in 2024 coverage is noted, not adopted
Additivity rule
Non-additive as a campus aggregate. It contains the live buildings and the expansion. It is never summed with PDG's India portfolio record (PRJ-025) or the MU2 and HY1 campuses
Relationship to PRJ-025
MU1 is a separate campus from the 210 MW acquired in March 2026. It contributes to PDG's claimed ~1 GW India total but is not part of the 210 MW

9Limits and open questions

Live capacity
50 MW per the operator's current page; 48 MW in 2024 coverage. Small, unexplained
Expansion schedule
First phase scheduled for 2026. No confirmation that it was delivered on time, and no phase dates for buildings four and five
Design detail
No PUE, rack count, rack density, redundancy scheme, chiller architecture or generator configuration published
Tenants
None named. PDG describes the facility as serving hyperscalers, but no lease is disclosed
Green loan criteria
The specific environmental performance criteria and reporting obligations are not public
Substation capacity
220 kV GIS is confirmed. The MVA rating and the sanctioned load are not published
What we will not claim
No PUE, no tenants, no completion confirmation for 2026, and no equipment brands

10Sources

This record was compiled entirely from publicly available sources, cross-checked against one another.

Princeton Digital Group newsroom and India location pages·DatacenterDynamics·Datacentre Magazine·The Hindu BusinessLine·Economic Times·Times of India·w.media·Developing Telecoms·Energetica India·Digital Infra Network·Datacenter News Asia·Baxtel·CEO Insights Asia·ETCIO SEA

Gridvik does not publish source URLs on record pages; citations are retained in the internal source register and are available on request.

What this page is, and what it is not

This is a public-source record of a live campus with a large funded build. Capacity, certification, substation and financing facts are attributed to PDG and the outlets that reported them.

The procurement section is labelled as estimation. No tender insider information, no private contact data, no operator-paid placement. Corrections are free and published with a date.