On 31 October 2025 in New Delhi, NTPC Green Energy Limited and CtrlS Datacenters signed a memorandum to explore renewable energy projects of 2 GW or more, supplying round-the-clock power on a pan-India basis for CtrlS's captive consumption. The MoU runs for two years. It contains no tariff, no site, no land, no transmission arrangement and no data-centre capacity. Gridvik records it because it is the clearest public signal of how India's largest Rated-4 operator intends to keep its racks powered — and because the number in the headline is roughly three times what it will actually deliver at the meter.
1At a glance
2What the memorandum says
The language is careful and worth reading literally. The two firms will explore business opportunities of mutual interest towards developing renewable projects of 2 GW or more, for the supply of round-the-clock renewable power to CtrlS data centres on a pan-India basis for captive consumption. Development may be greenfield or through acquisitions — an important detail, because an acquisition path means the 2 GW could be bought rather than built, and could arrive years earlier than a greenfield schedule implies.
Both firms commit to working together to plan and implement the capacity. That is the entire substance of it. No financial or timeline detail was released at signing, and none has been released since.
A price. No tariff, no escalation formula, no term for supply.
A place. No site, no state, no land, no grid connection point. CtrlS's load centres are in nine markets; the generation could be anywhere that can evacuate.
A delivery obligation. A memorandum to explore is not an order to build. Under Indian practice these documents are routinely extended or allowed to lapse, and a two-year term is short for a project of this size.
There is a second, less-noticed number in the same week. The Union cabinet committee on economic affairs raised NTPC's permitted investment in NTPC Green Energy and its subsidiaries from an earlier ceiling of ₹7,500 crore to ₹20,000 crore, to support capacity addition against NTPC Green's 60 GW by 2032 target. That is the money behind the mandate — and it is not earmarked for CtrlS.
3Two gigawatts of what
This is the number that matters and almost nobody runs it. A gigawatt of solar in India produces at a capacity utilisation factor of roughly 22–25%. Wind runs 28–35%. A blended round-the-clock package without storage therefore delivers something close to 30% of nameplate as average output, and nothing at all for the eight hours after sunset.
So 2,000 MW of announced renewable capacity is roughly 600 MW of average power — before any storage is added, and before transmission losses. Round-the-clock supply is a stronger promise than plain renewable supply: it obliges the seller to firm the output, which in practice means batteries or pumped storage, which is not mentioned in the announcement. If storage is added, less than 2,000 MW of generation fits in the same envelope.
| Measure | Figure | Basis |
|---|---|---|
| Announced renewable capacity | 2,000 MW+ | Headline, 31 October 2025 |
| Average output at a 30% blended factor | about 600 MW | Derived by Gridvik, no storage |
| CtrlS live IT load | 370 MW+ | Company statement, June 2026 |
| Approximate gross facility load at that IT load | about 480–520 MW | Derived at a 1.3–1.4 PUE |
| CtrlS announced project pipeline | 4.4 GW | Company statement, June 2026 |
| Capacity the MoU can firm at a 370 MW load | yes, with storage | Judgement |
| Capacity the MoU can firm at a 4.4 GW pipeline | no | Judgement — would need several times more nameplate |
Two gigawatts of renewable capacity is sized to roughly the company CtrlS is today, not the company it says it will be by 2031. Against 370 MW of live load, 2 GW of nameplate plus storage is a plausible green-power strategy. Against a 4.4 GW pipeline it is a first instalment.
That is not a criticism of the deal. It is a warning against quoting 2 GW alongside 4.4 GW as though they belong to the same sentence.
4Two power tracks, one operator
CtrlS is assembling its electricity from two directions at once, and the order matters.
| Track | Date | Counterparty | What it actually provides |
|---|---|---|---|
| Green generation | 31 Oct 2025 | NTPC Green Energy | A two-year framework to explore 2 GW+ of renewable capacity. No tariff, no site |
| Capital for build-out | 17 Jun 2026 | Canada Pension Plan Investment Board | ₹7,000 crore: ₹4,000 crore for an 8.2% stake and ₹3,000 crore into a 48:52 joint venture |
| Grid capacity | Jul 2026 | State Bank of India and Central Bank of India | ₹5,500 crore of debt for the 3.5 GW Hyderabad campus |
Read together, the sequence is coherent. First a green-power framework, then a sovereign-scale equity partner, then grid-side debt for the largest single campus. None of the three is a power purchase agreement. All three are commitments to try, and the equipment that gets ordered sits downstream of whichever one converts first.
The tractable signal for a supplier is not the 2 GW. It is that CtrlS has now committed publicly to a captive, round-the-clock, renewable-heavy power model at national scale. That model needs storage, switchgear, high-voltage substations and transmission interconnection at every campus — none of which are announced, all of which have to exist before a single additional megawatt of IT load can be energised.
5Timeline
- NTPC Green Energy and CtrlS sign the memorandum in New Delhi for 2 GW or more of round-the-clock renewable capacity, captive, pan-India, greenfield or acquired. Two-year term.
- NTPC Green Energy, CtrlS and NTPC’s own disclosure to the exchanges carry the same facts. No tariff, no site, no schedule in any of them.
- The Union cabinet committee on economic affairs raises NTPC’s permitted investment in its green subsidiaries from ₹7,500 crore to ₹20,000 crore.
- CtrlS closes the ₹7,000 crore Canada Pension Plan transaction. The power framework is not mentioned in it.
- No power purchase agreement, no site, no land, no storage contract and no transmission arrangement has been published in the eleven months since signing.
- The memorandum lapses on its current terms unless extended. That is twelve months from this record.
6What this changes for a vendor
Gridvik does not publish private contact data. The rows above with a lock are the paid layer.
7Assumptions and method
8Limits and open questions
9Sources
This record was compiled entirely from publicly available sources, cross-checked against one another.
NTPC Green Energy disclosure·CtrlS Datacenters press release·Economic Times (PTI)·The Hindu BusinessLine·Business Standard·DatacenterDynamics·Renewable Watch·Tech Observer·Indian Infrastructure
Gridvik does not publish source URLs on record pages; citations are retained in the internal source register and are available on request.
This is a record of a power-procurement framework, published short because the public record is short. It carries no data-centre capacity and is not counted anywhere in Gridvik's totals.
Corrections are free and published with a date.