CtrlS — NTPC Green Energy Renewable Power MoUCtrlS Datacenters Limited and NTPC Green Energy Limited · pan-India · 2,000 MW+

Record PRJ-034National — no siteTier B — context record9 public sources cross-checked
Power procurementCarries no MWNon-additiveFramework, not a PPA
2GW+
Announced RE capacity
~600MW
Average output, derived
Zero
Data-centre MW
2yr
MoU term
31 Oct 2025
Signed
0
Tariff disclosed

On 31 October 2025 in New Delhi, NTPC Green Energy Limited and CtrlS Datacenters signed a memorandum to explore renewable energy projects of 2 GW or more, supplying round-the-clock power on a pan-India basis for CtrlS's captive consumption. The MoU runs for two years. It contains no tariff, no site, no land, no transmission arrangement and no data-centre capacity. Gridvik records it because it is the clearest public signal of how India's largest Rated-4 operator intends to keep its racks powered — and because the number in the headline is roughly three times what it will actually deliver at the meter.

1At a glance

Record type
Energy procurement memorandum. Not a data-centre facility and not a capacity record
Signed
31 October 2025, New Delhi
Signatories
Sarit Maheshwari, chief executive of NTPC Green Energy and NTPC Renewable Energy; Sridhar Pinnapureddy, founder and chairman of CtrlS
Scope
Renewable energy projects of 2 GW or more, developed greenfield or acquired, supplying round-the-clock power to CtrlS data centres across India on captive consumption
Term
Two years, extendable. On current terms the framework lapses on 31 October 2027
Commercial terms
None published. No tariff, no power purchase agreement, no site, no land, no evacuation or transmission arrangement
Data-centre capacity
Zero. This record adds no MW to any Gridvik total, and the registry sets its additivity flag to not applicable
Confidence
High on what was signed and by whom. Low on what will be built

2What the memorandum says

The language is careful and worth reading literally. The two firms will explore business opportunities of mutual interest towards developing renewable projects of 2 GW or more, for the supply of round-the-clock renewable power to CtrlS data centres on a pan-India basis for captive consumption. Development may be greenfield or through acquisitions — an important detail, because an acquisition path means the 2 GW could be bought rather than built, and could arrive years earlier than a greenfield schedule implies.

Both firms commit to working together to plan and implement the capacity. That is the entire substance of it. No financial or timeline detail was released at signing, and none has been released since.

The three things an MoU of this kind does not have

A price. No tariff, no escalation formula, no term for supply.

A place. No site, no state, no land, no grid connection point. CtrlS's load centres are in nine markets; the generation could be anywhere that can evacuate.

A delivery obligation. A memorandum to explore is not an order to build. Under Indian practice these documents are routinely extended or allowed to lapse, and a two-year term is short for a project of this size.

There is a second, less-noticed number in the same week. The Union cabinet committee on economic affairs raised NTPC's permitted investment in NTPC Green Energy and its subsidiaries from an earlier ceiling of ₹7,500 crore to ₹20,000 crore, to support capacity addition against NTPC Green's 60 GW by 2032 target. That is the money behind the mandate — and it is not earmarked for CtrlS.

3Two gigawatts of what

Announced RE capacityMoU headline, 31 Oct 20252,000 MWAverage output at about 30% CUFderived from a solar-wind blend~600 MWCtrlS live IT loadcompany statement, June 2026370 MWCtrlS announced project pipelinecompany statement, June 20264.4 GW2,000 MW of panels and turbines is not 2,000 MW of power at the rack. The gap is the whole story.
Figure 1Announced renewable capacity against average delivered output and the buyer's actual load. The average-output estimate applies a blended 30% capacity utilisation factor to a solar-wind mix without storage accounting; a storage-backed round-the-clock contract would raise the deliverable figure somewhat and raise the cost materially.

This is the number that matters and almost nobody runs it. A gigawatt of solar in India produces at a capacity utilisation factor of roughly 22–25%. Wind runs 28–35%. A blended round-the-clock package without storage therefore delivers something close to 30% of nameplate as average output, and nothing at all for the eight hours after sunset.

So 2,000 MW of announced renewable capacity is roughly 600 MW of average power — before any storage is added, and before transmission losses. Round-the-clock supply is a stronger promise than plain renewable supply: it obliges the seller to firm the output, which in practice means batteries or pumped storage, which is not mentioned in the announcement. If storage is added, less than 2,000 MW of generation fits in the same envelope.

Where 2 GW of renewable capacity lands against CtrlS's own disclosed numbers
MeasureFigureBasis
Announced renewable capacity2,000 MW+Headline, 31 October 2025
Average output at a 30% blended factorabout 600 MWDerived by Gridvik, no storage
CtrlS live IT load370 MW+Company statement, June 2026
Approximate gross facility load at that IT loadabout 480–520 MWDerived at a 1.3–1.4 PUE
CtrlS announced project pipeline4.4 GWCompany statement, June 2026
Capacity the MoU can firm at a 370 MW loadyes, with storageJudgement
Capacity the MoU can firm at a 4.4 GW pipelinenoJudgement — would need several times more nameplate
The honest reading

Two gigawatts of renewable capacity is sized to roughly the company CtrlS is today, not the company it says it will be by 2031. Against 370 MW of live load, 2 GW of nameplate plus storage is a plausible green-power strategy. Against a 4.4 GW pipeline it is a first instalment.

That is not a criticism of the deal. It is a warning against quoting 2 GW alongside 4.4 GW as though they belong to the same sentence.

4Two power tracks, one operator

CtrlS is assembling its electricity from two directions at once, and the order matters.

CtrlS's two power tracks
TrackDateCounterpartyWhat it actually provides
Green generation31 Oct 2025NTPC Green EnergyA two-year framework to explore 2 GW+ of renewable capacity. No tariff, no site
Capital for build-out17 Jun 2026Canada Pension Plan Investment Board₹7,000 crore: ₹4,000 crore for an 8.2% stake and ₹3,000 crore into a 48:52 joint venture
Grid capacityJul 2026State Bank of India and Central Bank of India₹5,500 crore of debt for the 3.5 GW Hyderabad campus

Read together, the sequence is coherent. First a green-power framework, then a sovereign-scale equity partner, then grid-side debt for the largest single campus. None of the three is a power purchase agreement. All three are commitments to try, and the equipment that gets ordered sits downstream of whichever one converts first.

The tractable signal for a supplier is not the 2 GW. It is that CtrlS has now committed publicly to a captive, round-the-clock, renewable-heavy power model at national scale. That model needs storage, switchgear, high-voltage substations and transmission interconnection at every campus — none of which are announced, all of which have to exist before a single additional megawatt of IT load can be energised.

5Timeline

  • NTPC Green Energy and CtrlS sign the memorandum in New Delhi for 2 GW or more of round-the-clock renewable capacity, captive, pan-India, greenfield or acquired. Two-year term.
  • NTPC Green Energy, CtrlS and NTPC’s own disclosure to the exchanges carry the same facts. No tariff, no site, no schedule in any of them.
  • The Union cabinet committee on economic affairs raises NTPC’s permitted investment in its green subsidiaries from ₹7,500 crore to ₹20,000 crore.
  • CtrlS closes the ₹7,000 crore Canada Pension Plan transaction. The power framework is not mentioned in it.
  • No power purchase agreement, no site, no land, no storage contract and no transmission arrangement has been published in the eleven months since signing.
  • The memorandum lapses on its current terms unless extended. That is twelve months from this record.

6What this changes for a vendor

Procurement window and scope
Gridvik assessment · 22 Oct 2026
This record
An energy procurement framework. It is procurement-relevant for power equipment, not for IT or cooling
Who it affects
Transformers, high-voltage switchgear, substation EPC, battery storage integrators, transmission interconnection contractors
Not affected
UPS, cooling, racks, DG sets and cabling, which follow data-centre construction, not generation
What the framework does not settle
Who builds the storage, at which site, on what schedule
The unlisted opportunity
A round-the-clock renewable obligation at this scale implies battery energy storage that has not been announced anywhere
Order window
Estimate — 2027 to 2029 if the 2 GW converts
Procurement heat
Low today. The framework binds nobody and nothing has been ordered
Who to call
CtrlS power and infrastructure leadership; NTPC Green Energy business development
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

Gridvik does not publish private contact data. The rows above with a lock are the paid layer.

7Assumptions and method

What is sourced
The signing date and place, the signatories, the 2 GW+ figure, round-the-clock and captive-consumption language, the two-year term, NTPC Green's operating and pipeline capacity, and the investment-ceiling increase
What is derived
The about-600 MW average-output figure, the gross facility load implied by 370 MW of IT load, and the assessment of whether the framework is sized to live load or pipeline
Capacity figure used
None as data-centre capacity. The 2,000 MW is generation nameplate and is never added to any national total
Additivity rule
Flagged not applicable. This record cannot be summed with a facility record under any circumstance
Currency
Indian rupees as reported. US dollar conversions use ₹88.40 to the dollar, fixed quarterly
Status
Signed and in force. Nothing built, ordered or contracted publicly

8Limits and open questions

The central gap
No power purchase agreement. Everything in the announcement sits one legal step above a press release
Site
Not stated. Neither the state, the district nor the grid substation is named
Storage
Not mentioned. A round-the-clock obligation cannot be met from solar and wind alone
Cost
Not disclosed at any point. This is the number that decides whether CtrlS's green power is cheaper or more expensive than grid supply
Greenfield versus acquisition
Both are permitted. The split is not stated, and the two paths have completely different timelines
Land and evacuation
No land identified, no transmission capacity identified
Whether it is exclusive
CtrlS is free to buy renewable power elsewhere, and almost certainly will
What we will not claim
No commissioning date, no equipment brands, no capacity addition to Gridvik's national total, and no suggestion that 2 GW of data-centre load is being powered

9Sources

This record was compiled entirely from publicly available sources, cross-checked against one another.

NTPC Green Energy disclosure·CtrlS Datacenters press release·Economic Times (PTI)·The Hindu BusinessLine·Business Standard·DatacenterDynamics·Renewable Watch·Tech Observer·Indian Infrastructure

Gridvik does not publish source URLs on record pages; citations are retained in the internal source register and are available on request.

What this page is, and what it is not

This is a record of a power-procurement framework, published short because the public record is short. It carries no data-centre capacity and is not counted anywhere in Gridvik's totals.

Corrections are free and published with a date.