Yotta Greater Noida Data Center ParkYotta Data Services (Hiranandani Group) · Knowledge Park V, Greater Noida · six buildings

Record PRJ-036Uttar Pradesh — Knowledge Park VTier A — procurement-relevant13 public sources cross-checked
Umbrella — not additiveCampus aggregateFour conflicting capacitiesOne of six buildings live
20ac
Site
6
Buildings planned
28.8MW
Delivered
250–350MW
Latest claims
₹7,000cr
Park cost
11.5%
Delivered against 250 MW

Yotta's Greater Noida park is the most-quoted campus in North India and the least settled. Its capacity has been published as 200 MW, then 160 MW, then 250 MW, and in September 2026 as 350 MW — over the same twenty acres, without a second building being completed. Four years after the first building opened, the campus has actually delivered 28.8 MW. That is 11.5% of the figure currently in circulation. This record exists so that nobody who needs a number has to guess which one to use.

1At a glance

Operator
Yotta Data Services, Hiranandani Group, through Nidar Infrastructure
Site
About 20 acres at Knowledge Park V, Greater Noida, Uttar Pradesh. Land allotted by the state in 2020; construction began January 2021
Plan
Six interconnected data centre buildings, described at announcement as 30,000 racks with four dedicated fibre paths
Capacity in circulation
200 MW, 160 MW, 250 MW and 350 MW — all published, none reconciled. See the conflict table below
Delivered
28.8 MW. One building, D1, live since 31 October 2022. D2 under construction, not live
Park cost
About ₹7,000 crore as announced for the six buildings. A separate figure of ₹9,134.9 crore appears in the state dashboard basis
Group commitment
₹39,000 crore over five to seven years under a memorandum with the Uttar Pradesh government, covering the park plus IT equipment
Additivity
Not additive. This is an umbrella record. It is never summed with D1, D2 or any other Yotta facility, nor into any national total
Status
Expanding. One of six buildings complete, four years in
Confidence
High on D1 and the site. Low on every aggregate figure, which is precisely why they are all listed

2One park, four capacities

Economic Timesannouncement, October 2020200 MWYotta launch release31 October 2022160 MWMoneycontrol and Yotta pagesOctober 2022 to 2026250 MWFounder, Global Fintech Fest23 September 2026350 MWSame twenty acres throughout. The number has more than doubled without a single new building being completed.
Figure 1Every figure here was published. None was retracted. Each reflects a different scope, date or rounding, and the movement is not all in one direction — the number fell from 200 to 160 MW before it rose.
The park capacity as published, by source and date
SourceDateCapacityContext
Economic TimesOct 2020200 MWInitial announcement of the six-building park
Yotta official launch release31 Oct 2022160 MWThe park as described on the day D1 opened: 30,000 racks, four fibre paths, 160 MW
Times of India, UP government releaseOct–Nov 2022160 MW, elsewhere 250 MWSame week, two figures
Moneycontrol31 Oct 2022250 MW"More than 250 MW of power" for 30,000 racks
Yotta colocation pages2025–2026more than 250 MWCurrent operator description of the park
Yotta release on the Blackwell deployment18 Feb 2026scalable to 250 MWSame week as the D2 announcement
Founder, Global Fintech Fest23 Sep 2026350 MWThe Greater Noida park described as expandable to 350 MW
Which one Gridvik uses

None of them. This record carries no capacity of its own and adds nothing to the national total. The individual building figures — D1 at 28.8 MW — are what count, and they are counted once, under their own records.

If a single number is needed to describe the site, use 28.8 MW delivered. That is the only figure on this page that describes something that exists.

3What the park was promised to be

The 2021–22 vision was specific and is worth restating plainly, because the current marketing has drifted away from it.

Scale
Six interconnected buildings on 20 acres, 30,000 racks, four dedicated fibre paths
Campus power
160 MW of IT power in the launch release; 250 MW in the same week's other coverage
Cadence
"We will put up one building every 18 months." Executive chairman, 31 October 2022
Per-building cost
"Each data centre will cost ₹6,500 crore" — including IT equipment, not construction alone
D2 and D3
Foundation stones laid on the same day as the D1 inauguration, with a stated 12–15 month delivery
IT equipment
₹5,000 crore of IT equipment per building once fully operational, a figure repeated for every building
Incentive
Memorandum with the Uttar Pradesh government for ₹39,000 crore across the state over five to seven years

Run the stated cadence forward from October 2022. One building every 18 months, five buildings remaining, puts the sixth at roughly mid-2030. Four years after the promise, one of the six is complete.

4What has actually been built

D1 — live and operatingcommissioned October 202228.8 MWD2 — under construction60 MW, targeted live August 202660 MW, not livePark claim in circulationsix buildings250 MWPark claim, September 2026founder, at a fintech conference350 MWAfter four years the campus has delivered 28.8 MW. Everything to the right of the first bar is a plan.
Figure 2The second bar is a building under construction and is not counted as live anywhere in Gridvik. The third and fourth bars are campus claims, not delivered capacity.
Building-by-building status on the Greater Noida campus
BuildingStated capacityStatusEvidence
D128.8 MWLive, since 31 Oct 2022Inaugurated by the chief minister. Operating
D260 MWUnder constructionFoundation stone Oct 2022. Targeted live Aug 2026; that date passed. Partner disclosures in Aug 2026 put overall progress at 33% against a 42% plan
D3Not publishedNot builtFoundation stone 2022. A November 2024 project survey recorded construction not started
D4, D5, D6Not publishedNot builtNo construction evidence in any source reviewed

On the evidence, the park has produced 28.8 MW in four years against a published claim of 250 MW. If the 160 MW figure from the launch release is used instead, it is 18%. Neither reading supports the language the site is marketed with.

The one thing this park has actually proved

Speed to first building. D1 went from construction start to inauguration in 20 months, which is genuinely fast, and it is the strongest fact in Yotta's favour.

The second building has now taken longer than the first did. That is the entire story of Indian data-centre delivery in one campus: the first building is a project, the fifth is an organisation.

5The rack-count problem

Here is an arithmetic problem that has not been publicly reconciled, and it matters to anyone sizing equipment.

Two published figures that no longer fit each other
FigureValueImplied average
Park racks30,000—
Park capacity250 MW8.3 kW per rack
D1 alone5,000 racks, 28.8 MW5.8 kW per rack
D2 alone60 MW, liquid-cooled GPU hallsnot consistent with 8.3 kW per rack at any plausible rack count

The 30,000-rack figure and the 250 MW figure were both published in 2022, for a park of general-purpose colocation halls. Since then the campus has pivoted to 60 MW buildings filled with liquid-cooled GPU racks. GPU halls run at tens of kilowatts per rack, not eight. If D2's 60 MW is delivered at high density, the park cannot hold 30,000 racks at 250 MW — the rack count has to fall, or the megawatt figure has to rise.

That is almost certainly why the park figure moved to 350 MW in September 2026. The rack count stayed in the marketing and the capacity was raised to make the arithmetic work again.

What a supplier should take from this

The rack count is a 2022 number and should not be used for anything. Rack count is the wrong unit for an AI campus — megawatts and kilowatts per rack are the units that determine what gets ordered.

A park that cannot fix its rack count cannot fix its cooling load, its busway length, its switchgear count or its generator schedule.

6Money, four ways

Four investment figures, four scopes
FigureValueScopePer MW of park capacity
Park construction, as announcedabout ₹7,000 croreSix buildings on 20 acres₹28 crore at 250 MW; ₹44 crore at 160 MW
State dashboard basis₹9,134.9 croreCarried in Gridvik's registry for this recordDifferent scope, not directly comparable
State memorandum₹39,000 crorePark plus IT equipment across UP, five to seven yearsnot a construction figure
Per building, with ITabout ₹6,500 croreCompany statement, per data centreabout ₹108 crore at 60 MW per building

The number that gets quoted, ₹39,000 crore, is not a data-centre construction figure. It bundles buildings with servers and GPUs over five to seven years. The number that matters for the buildings alone is about ₹7,000 crore.

For scale: at ₹7,000 crore for 250 MW the park is being built at roughly ₹28 crore per MW, or about $3.2 million. Against its 160 MW description it is ₹44 crore per MW. Against the 350 MW figure now in circulation it is ₹20 crore. The same ₹7,000 crore produces a per-MW cost that varies by more than a factor of two, entirely depending on which capacity claim is used as the denominator. That is not a rounding issue. It is the difference between the cheapest and the most expensive build in the country.

7Why the park pivoted to GPUs

In February 2026 Yotta announced that 20,736 liquid-cooled Nvidia Blackwell Ultra GPUs would be deployed at the 60 MW D2 building, backed by more than $2 billion — about ₹17,700 crore — with Nvidia taking roughly half the capacity under a four-year DGX Cloud arrangement reported at about $1 billion. A Nasdaq-listed partner is supplying and financing part of the hardware through project-level structures.

The pivot in one comparison
Park constructionOne GPU deployment
Capitalabout ₹7,000 croremore than ₹17,700 crore
What it buysSix buildings and their power and coolingAbout 20,700 GPUs plus networking and liquid cooling
Ratio1.0about 2.5 times

The consequence is structural and it has not been absorbed by most of the market commentary. Yotta is no longer valued as a landlord. It has raised $150 million at about $3.9 billion, is targeting a valuation of up to $6 billion, and plans to file draft listing papers. Its reported FY25 revenue from operations was ₹890.72 crore with a profit after tax of ₹11.05 crore — a business that doubled revenue and saw profit fall. That is the profile of a company converting from rent to compute, and the data-centre park is now the shop floor rather than the product.

What follows for a supplier

Building work on this campus will slow and equipment work will accelerate. A campus chasing GPU revenue does not need building six; it needs one hall of liquid-cooled capacity live sooner.

That is exactly what the September 2026 statement about single-storey, steel-framed, five-to-six-month buildings describes. It is also an admission that the six-building, multi-storey plan was the wrong shape for the demand that arrived.

8Timeline

  • Hiranandani Group announces a 20-acre, six-building park in Greater Noida, described as 200 MW.
  • Construction starts on D1.
  • D1 inaugurated. Park described in the official release as 160 MW; described elsewhere the same week as 250 MW. Foundation stones for D2 and D3. ₹39,000 crore state memorandum signed. Building cadence promised at one every 18 months.
  • D1 reported about 85% full. D2 racks said to be going live imminently.
  • Project survey records D2 at finishing stage and D3, D4 and D5 not started.
  • 20,736 Blackwell Ultra GPUs announced for the 60 MW D2 building. More than $2 billion. Live target August 2026.
  • Target missed. Partner disclosures show construction progress at 33% against a 42% plan; equipment deliveries begin in September.
  • Founder describes the Greater Noida park as expandable to 350 MW, and announces a shift to single-storey steel-framed buildings that can be built in five to six months.
  • One of six buildings complete. 28.8 MW live. 350 MW now in circulation as the park figure.

9Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
This record
A live campus with one operating building, one building in build and four unevidenced
The real order book
D2 at 60 MW with liquid cooling: coolant distribution units, high-density busway, in-row and rear-door heat exchangers, medium-voltage switchgear
What has already been ordered
20,736 GPUs, 800 Gbps InfiniBand fabric, more than 40 PB of parallel file-system storage
What is not yet ordered publicly
D3 to D6 electrical and mechanical plant. No tender, supplier or schedule has been published
Design shift to watch
Single-storey steel-framed buildings at five to six months each change the order profile from bespoke to repeatable — a different supplier list
Order window
D3 to D6: 2027 to 2030 on the originally stated cadence, earlier if the pivot accelerates
Procurement heat
High on cooling and power distribution for AI halls; low on shell and core
Decision role
Yotta infrastructure and delivery leadership; group procurement at Hiranandani
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

Rows with a lock are the paid layer.

10Assumptions and method

What is sourced
Site area, building count, rack count, all four capacity claims with dates and sources, D1 details, D2 capacity and GPU deployment, park cost, state memorandum value, per-building cost, cadence commitment and delivery status of each building
What is derived
The 11.5% and 18% delivery ratios, all per-MW cost figures, the 8.3 kW per rack average and the money comparison against the GPU deployment
Capacity figure used
None. The record carries no capacity. D1's 28.8 MW is counted once under PRJ-035
Additivity rule
Not additive. Explicitly excluded from national and state totals to prevent double counting with D1 and D2
Progress percentage
The 33% against 42% figures come from a listed partner's project documentation, not from Yotta. They are reported as a partner disclosure
Currency
₹88.40 to the US dollar, fixed quarterly

11Limits and open questions

The central gap
No reconciled capacity figure exists. Four numbers are in circulation and the operator has published all of them
D2 completion
The August 2026 target has passed. No revised date has been published
D3 to D6
No capacity, no design, no cost, no dates. Nothing beyond a foundation stone in 2022
Rack count
30,000 racks cannot be reconciled with 250 MW once D2 is a 60 MW GPU hall. The figure appears to be stale
350 MW
Stated once, verbally, at a conference. Not accompanied by a building count, cost or schedule
Growth of the claim
200 to 160 to 250 to 350 MW across six years, with one building delivered. Gridvik does not treat the trend as evidence of capacity
What we will not claim
No total park capacity, no completion date for D2, no D3 to D6 schedule, no equipment brands, and no suggestion that 250 MW or 350 MW exists or is funded

12Sources

This record was compiled entirely from publicly available sources, cross-checked against one another.

Yotta Data Services launch release·Yotta colocation pages·Yotta Blackwell deployment release·Yotta Navi Mumbai and portfolio pages·Economic Times·Moneycontrol·Times of India·Uttar Pradesh government release·Financial Express·DatacenterDynamics·Hiranandani Group·Data Center Hawk·Baxtel

Gridvik does not publish source URLs on record pages; citations are retained in the internal source register and are available on request.

What this page is, and what it is not

A campus record that deliberately holds four conflicting published figures side by side instead of choosing one and presenting it as fact.

Corrections are free and published with a date.