Facility record · Registry correction · Verified 22 Oct 2026

Sify Noida 02 — filed under SKVR SoftwareSify Infinit Spaces · Plot B-11, 12, 13, Sector 132, Noida · 26 MW built

Record PRJ-038Uttar Pradesh — Sector 132, NoidaTier A — procurement-relevantOperator field corrected12 public sources cross-checked
LiveFacility recordOperator correctedAdditive at 26 MW
120MW
Grid load filed
78MW
Campus design
26MW
Built
16MW
Commercialised
₹2,692cr
Sify investment
3
Towers planned

This record began as a data error and ends as a reconciliation. Gridvik's master listed a Noida project under an operator called SKVR Software, at 120 MW for ₹2,692 crore. SKVR Software Solution is not a data centre operator. It is the land and building company for Sify's Noida 02 campus, 100% acquired by the Sify group in September 2023. The 120 MW is the grid load Sify requisitioned for the campus. The campus is designed for 78 MW across three towers of 26 MW. One tower is built and the state records 16 MW as commercialised. The highest and lowest figures differ by 7.5 times.

1At a glance

Corrected operator
Sify Infinit Spaces Limited, the data centre subsidiary of Sify Technologies. Not SKVR Software
What SKVR is
SKVR Software Solution Private Limited, a special purpose company that holds the land and the building shell. All the remaining data centre infrastructure sits with Sify Infinit Spaces
How the ownership arose
Share purchase agreement dated 1 September 2023 between the Sify group and SKVR's shareholders for 100% of the equity. Sify Infinit Spaces took 49% and Sify Technologies 51%
Site
Plot B-11, 12 and 13, Sector 132, Gautam Budh Nagar, Noida, on the Greater Noida Expressway opposite Jaypee Hospital. About 19,305 square metres of land, roughly 4.8 acres, allotted by the Noida authority
Campus plan
Three towers of 26 MW each = 78 MW of design IT power, more than 13,000 racks, 6,300 mm floor to floor, 2,100 kg per square metre floor loading
Built
One tower at 26 MW. Construction largely complete as of November 2024; operational from Q4 FY25
Commercialised
16 MW, per the Uttar Pradesh government's own policy dashboard
Investment
₹2,692 crore, the figure the state carries for this project
Grid load requisitioned
120 MW, filed with the state transmission utility for the Sector 132 campus
Additivity
Additive at 26 MW only, the built tower. The campus figures are not summed with the tower

2Who SKVR actually is

The correction matters more than it looks. A record that names the wrong company produces the wrong sales call, the wrong procurement assumption and the wrong competitive reading.

The three entities, and what each actually holds
EntityRoleWhat it holdsOwnership
SKVR Software Solution Private LimitedLand and building companyThe land lease from the Noida authority and the building shell100% Sify group: 49% Sify Infinit Spaces, 51% Sify Technologies
Sify Infinit Spaces LimitedData centre operatorAll the balance data centre infrastructure: power, cooling, networking, fit-outData centre subsidiary of Sify Technologies
Sify Technologies LimitedListed parentControls and consolidates bothListed on Nasdaq

The structure is ordinary Indian project finance and it is used again and again: the costly, long-lived, immovable asset sits in a company that can borrow against it, while the operating business sits in another. The consequence for anyone reading the state dashboard is not ordinary at all. The dashboard lists SKVR Software as one of the major operators building data centre capacity in Uttar Pradesh, alongside NTT, Adani, Sify and Hiranandani. It is not one of them. It is Sify.

The specific error in Gridvik's own master file

The master row carried operator: SKVR Software and a 120 MW capacity at the state dashboard confidence level. Both have been corrected in this record.

The company that buys power, hires staff, signs tenants and issues purchase orders for this site is Sify Infinit Spaces. Every commercial approach should go there.

3One building, four numbers

State dashboard and grid filingUP policy listing and power requisition120 MWCampus design IT loadthree towers of 26 MW78 MWTower A, as builtthe only completed building26 MWCommercialisedstate government, September 202616 MWEvery step down is a real definition, not an error. The gap between the first bar and the last is 7.5 times.
Figure 1Four figures, all published, all correct within their own definition. The 120 MW is a grid filing for the campus, not a capacity claim for a building.
What each number means, and which one to use
NumberWhat it measuresSourceUse it for
120 MWGrid load requisitioned from the state transmission utility for the Sector 132 sitePower utility and state coverage, January 2023Power availability and interconnection, not built capacity
78 MWDesign IT power of the campus: three towers of 26 MWSify factsheet and annual reportThe ceiling of the site
26 MWDesign IT power of the completed towerOperator factsheet; care rating reportThe building that exists. This is Gridvik's additive figure
16 MWCapacity the state government records as commercialisedUttar Pradesh data centre policy dashboardWhat is actually energised and earning
Land01Towers 2 and 302Tower A fit-out03Tower A live04Towers B, C0578 MW06Navy = verified · Red = current stage · Grey = not yet evidenced
Figure 2Delivery stages. Towers B and C remain unbuilt, which is why the campus figure of 78 MW is not counted anywhere in Gridvik.

4Why the 120 MW exists

The 120 MW figure is the one that circulates and it is the one that is most often read as capacity. It is not capacity. It is a request to the grid.

In January 2023, as the state was planning substations to serve the Noida data centre corridor, officials disclosed that Sify needed 120 MW of load for its Sector 132 campus. The arithmetic then works: 78 MW of IT power at a plant efficiency of roughly 1.5 draws about 117 MW at the meter. That is the 120 MW. It is the campus gross load, filed as a power connection request, because in India the power connection is the binding constraint and you file for it years before you need it.

The reconciliation Gridvik applies

120 MW of grid load is not 120 MW of data centre. It is about 78 MW of IT load after electrical and cooling losses, of which 26 MW is built and 16 MW is recorded as earning.

A supplier who sized a pipeline against the 120 MW would be building for a campus three times larger than the one that exists.

5What the registry got wrong

Before and after
FieldAs carriedCorrectedWhy
OperatorSKVR SoftwareSify Infinit SpacesSKVR is the land and building company, acquired by Sify in 2023. It does not operate
Capacity120 MW26 MW additive; 78 MW campus ceiling120 MW is a grid requisition. Only 26 MW of tower is built
Capacity basisUnstatedIT load, design, per towerOperator factsheet states design IT power
Investment₹2,692 crore₹2,692 crore, retainedThe state figure is not contradicted by any Sify disclosure
Record typeProject proposalFacility, liveThe tower is built and energised. It is not a proposal

Gridvik publishes its own corrections with the same prominence as the original figure. Four fields on this record were wrong in the master file. They are listed above rather than quietly overwritten, because a data business that hides its corrections is not a data business.

6Timeline

  • The Noida authority allots the Sector 132 land parcel to SKVR Software Solution on a long lease. Company disclosures describe the term as 90 years from 2006 in one filing and 99 years in another.
  • Sify's first Noida building, Noida 01, opens nearby with 10.8 MW of IT power. It is the anchor that makes the second campus viable.
  • Sify group signs a share purchase agreement for 100% of SKVR Software Solution. Sify Infinit Spaces takes 49% and Sify Technologies 51%.
  • State officials disclose Sify needs 120 MW of load for the Sector 132 data centre, as three new substations are planned for the Noida corridor.
  • A rating agency records that construction of the 26 MW tower is largely complete and expects it to be operational from Q4 FY25, while noting delayed completion of the capex programme.
  • Tower A operational. The campus is described as AI-ready hyperscale, with the remaining towers to follow in the coming years.
  • The state records 16 MW commercialised from this company against its 120 MW listing. Towers B and C remain unbuilt.
  • 26 MW built, 16 MW commercialised, 78 MW still the ceiling of the site.

7Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
This record
A live 26 MW tower with two more towers of the same size planned and unbuilt
Who buys
Sify Infinit Spaces, not SKVR. All balance infrastructure procurement sits with the operator
Already built
Tower A electrical and mechanical plant, air-cooled with N+2 and N+2C configurations
The live opportunity
Towers B and C: 52 MW of design IT power, roughly 8,700 further racks, with the same specification as Tower A
Site constraints that matter
6,300 mm floor to floor and 2,100 kg per square metre floor loading — a high-density specification, not a generic shell
Fuel
30 hours of on-site fuel storage with two geographically diverse re-supply contracts
Order window
Towers B and C: 2027 onward. No tender published
Procurement heat
Moderate. The operator has a funded, permitted site and is building in sequence
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

Rows with a lock are the paid layer.

8Assumptions and method

What is sourced
The corporate structure and the September 2023 acquisition, the land area and lease, the tower count and per-tower capacity, the factsheet specifications, the 120 MW requisition, the 16 MW commercialised figure, the ₹2,692 crore investment, and construction status
What is derived
The 78 MW campus total from three towers of 26 MW, the gross load implied by 78 MW at a 1.5 plant efficiency, and the 7.5 times spread between the highest and lowest figure
Capacity figure used
26 MW, design IT load, additive. One tower. Contributes to Gridvik's live bucket
Additivity rule
Only the built tower is additive. The 78 MW campus figure is a ceiling and is never added to any total
Plant efficiency
A 1.5 factor is used to relate IT load to grid load. It is an assumption for reconciliation only, not an operator disclosure
Correction policy
Four fields were corrected against the master file and are published above rather than silently changed

9Limits and open questions

Commercialised capacity
16 MW is a government figure, not an operator figure. Sify has not published a Noida 02 energised-capacity number in the form Gridvik can verify
Towers B and C
No dates, no cost, no tenant pipeline published
The 120 MW
Filed as a power requisition. Whether the connection is fully energised or staged is not public
Lease terms
Company filings describe the land lease as both 90 years from 2006 and 99 years. The term is stated inconsistently and has not been reconciled here
Tenants
None named for this campus
Land area
About 19,305 square metres, or roughly 4.8 acres, for a 78 MW campus. That is a high-density use of a small site and is worth checking for any later land addition
What we will not claim
No tenant names, no energised capacity beyond the state figure, no dates for the remaining towers, and no equipment brands

10Sources

This record was compiled entirely from publicly available sources, cross-checked against one another.

Care Ratings press release·Sify Infinit Spaces annual report·Sify Technologies filings·Sify data centre factsheets·Sify corporate site·Uttar Pradesh data centre policy dashboard·Hindustan Times·Economic Times Government·DatacenterDynamics·ArusGrid·Sify investor presentation

Gridvik does not publish source URLs on record pages; citations are retained in the internal source register and are available on request.

What this page is, and what it is not

A facility record that also corrects Gridvik's own master file. The correction is published as prominently as the original error.

Corrections are free and published with a date.