L&T is the largest engineering contractor in India and it is now an operator. Its data centre business, renamed Larsen & Toubro Vyoma, has a campus at Kancheepuram that has been published at 90 MW, then 30 MW, then 24 MW, then 18 MW, then 12 MW — and separately described as a 250 MW Phase 1 on 150 MVA of live power. In August 2026 it took a ₹10,000 to ₹15,000 crore order from the American AI cloud company Together AI to host 10,000 Nvidia B300 GPUs. Five weeks earlier, the Tamil Nadu government announced a ₹15,000 crore data centre expansion by L&T at the same campus. Both were reported as news. They are almost certainly one number.
1At a glance
2Seven capacities for one campus
| Figure | Date | What it is | Is it capacity? |
|---|---|---|---|
| 250 MW | Aug 2026 | Phase 1 design of the Chennai campus, described as gigawatt-scale overall | No — design |
| 150 MVA | Aug 2026 | Power infrastructure actually available at the site | No — connection size |
| 90 MW | Nov 2021 | Memorandum target, in phases over five years | No — a target |
| 30 MW | May 2026 | Capacity claimed as available on the platform | Partly, and it does not reconcile |
| 24 MW | Aug 2026 | Capacity being converted from colocation to AI workloads | No — a plan for existing capacity |
| 18 MW | May 2026 | 12 MW commissioned plus 6 MW in commissioning | Yes — this is the built figure |
| 12 MW | 2024–2026 | Commissioned at Sriperumbudur | Yes — the first building |
18 MW. That is the only figure on this page that describes equipment which has been installed. Everything else is a design, a target, a connection size or an unreconciled claim.
The 250 MW Phase 1 deserves particular scepticism. One hundred and fifty megavolt-amperes is the power that exists at this site. A 250 MW data centre cannot run on 150 MVA, so the Phase 1 figure is conditional on a grid upgrade that has not been announced.
3The 12 plus 6 does not equal 30
In May 2026 the company reported that its data centre business had commissioned 12 MW at Kanchipuram, that a further 6 MW was at an advanced stage of commissioning, and that this brought total capacity available to 30 MW. Twelve plus six is eighteen.
Three explanations are consistent with the public record and Gridvik cannot choose between them:
| Explanation | Fits the evidence? | Consequence |
|---|---|---|
| The claim was rounded up or a target was reported as delivered | Common in this sector | 18 MW is the built figure |
| Another site's capacity was included in a platform total | Plausible; the group has other facilities | The 30 MW is a group number, not a campus number |
| Further capacity was energised between the reporting and the claim | Possible, but no announcement supports it | Would need a source, and none exists |
Gridvik uses 18 MW and states the conflict rather than resolving it. A vendor planning against 30 MW at this site should confirm energisation directly.
4Two ₹15,000 crore stories
This is the most consequential thing on the page, and it is a reporting observation rather than an accusation. Two announcements, five weeks apart, both carrying the number ₹15,000 crore, both about the same campus.
| 4 June 2026 | 13 August 2026 | |
|---|---|---|
| What was announced | A Tamil Nadu government memorandum with L&T covering three projects worth ₹18,600 crore | A mega order won by LTN Compute from Together AI |
| Data centre element | ₹15,000 crore for a hyperscale and edge AI data centre expansion in Kancheepuram district | ₹10,000 to ₹15,000 crore, L&T's mega-order classification. Reuters reported up to ₹15,000 crore |
| Direction of money | Money L&T said it would invest | Money L&T said it had won |
| Who else was involved | Chief minister C. Joseph Vijay; L&T chairman S. N. Subrahmanyan | Together AI, a US AI cloud provider |
| Jobs cited | 500 | Not stated |
| Rest of the package | ₹2,500 crore electronics in Coimbatore, ₹1,100 crore offshore wind at Kattupalli | Not applicable |
It is unlikely to be a coincidence. The most economical reading is that the Together AI order is the anchor contract that funds the ₹15,000 crore expansion the state announced in June, and that the two were reported as separate pieces of news because they were announced by different parties in different cities.
Why this matters commercially: if both numbers are real and they are the same money, the Indian AI infrastructure order book is being overcounted by ₹15,000 crore (about $1.7 billion) in most summaries of it. If they are genuinely two separate commitments, that is a materially larger and much more interesting fact. No public document reconciles them, and Gridvik will not assert which it is.
The order itself is real and disclosed to the exchanges: 10,000 Nvidia B300 GPUs, a single integrated cluster, for Together AI, at Vyoma's Chennai campus, described as the largest single-cluster AI deployment in India.
It also makes L&T the only Indian engineering contractor that builds data centres for others and now operates one, with a named international anchor tenant.
5What 10,000 B300 GPUs need
This can be checked arithmetically, and it validates the reported numbers in a way that most capacity claims in this market cannot.
| Step | Figure | Note |
|---|---|---|
| GPUs | 10,000 | Nvidia B300, Blackwell Ultra |
| Eight-GPU systems | 1,250 | Standard DGX B300 configuration |
| Power per system | about 14.5 kW | Published figure for DGX B300 including networking |
| IT load implied | about 18.1 MW | Derived |
| Published capacity of the AI factory | about 23 MW | Reported in trade coverage |
| Implied networking and storage overhead | about 27% | Comfortable and consistent |
| Colocation capacity retained on site | about 6 MW | Reported |
| Total campus capacity accounted for | about 29 MW | Against the 30 MW claimed |
The arithmetic closes. 23 MW of AI factory plus 6 MW of colocation is 29 MW, which is the 30 MW L&T claims, and 10,000 B300s at DGX densities need about 18 MW of IT load, which leaves about a quarter for networking and storage. Every number here is internally consistent, and that is unusual enough in this market to be worth saying out loud.
It also explains the "12 plus 6 equals 30" puzzle. The 30 MW is a campus capacity figure covering both the AI conversion and the residual colocation, not the sum of two commissioned phases.
6The contractor becomes the operator
L&T builds data centres. It has been the engineering, procurement and construction contractor on hyperscale projects for years. In 2026 it turned the same capability inward, and did it in three moves inside eight months.
| Date | Move | Significance |
|---|---|---|
| May 2026 | Data centre business rebranded Larsen & Toubro Vyoma; 12 MW commissioned at Kanchipuram | The platform is named and capitalised |
| 4 June 2026 | ₹18,600 crore Tamil Nadu memorandum including a ₹15,000 crore data centre expansion | The state commits land and power; L&T commits scope |
| August 2026 | L&T's data centre and cloud services business transferred to Vyoma.AI for ₹1,400 crore | A listed contractor puts the business into a separate vehicle |
| 13 August 2026 | Mega order from Together AI for 10,000 B300 GPUs at the Chennai campus | A named international anchor tenant, and the order book to justify the expansion |
| Q4 FY27 target | No date published for the AI factory going live; trade coverage suggests November 2026 | The cliff edge for everything above |
The incentive to watch is competitive as well as commercial. L&T is a contractor to operators including some of the companies in this registry. Every move it makes as an operator is a move its clients will notice — and its pricing as a contractor now competes with its own hosting business.
Unlike most projects here, the anchor tenant is named, the counterparty is a known US company, the GPU model is specified, the power is quantified as MVA, and the arithmetic closes.
It is still an order and a design. Nothing is live. But this is what a verifiable announcement looks like, and it should be the standard applied to everything else.
7Cost per megawatt does not fit
One number on this page does not agree with the rest of the market, and it is worth flagging because it changes equipment budgets.
| Project | Cost | Capacity | Per MW |
|---|---|---|---|
| Yotta D1, Greater Noida | ₹1,500 crore | 28.8 MW | about ₹52 crore |
| CtrlS Chennai park | ₹4,000 crore | 72 MW | about ₹56 crore |
| L&T Sriperumbudur | about ₹2,000 crore | 12 MW | about ₹167 crore |
Two explanations fit. Either the ₹2,000 crore figure covers more than the first 12 MW — a campus, land, a substation sized for far more, or later phases bundled into one number — or L&T built a genuinely more expensive specification, which is plausible for an AI-ready campus with high floor loading.
Gridvik records the discrepancy rather than picking one. The practical consequence is real either way: anyone using ₹167 crore per MW as a benchmark for Indian build costs will over-budget by a factor of three.
8Timeline
- L&T signs a memorandum with the Tamil Nadu government to build a data centre at Kanchipuram, described as up to 90 MW in phases over five years.
- A ₹2,000 crore, 12 MW facility at Sriperumbudur nears completion. Testing under way. Plan stated as 30 MW in the near term and 90 MW over five years.
- Data centre business rebranded Larsen & Toubro Vyoma. 12 MW commissioned, 6 MW at an advanced stage of commissioning, total capacity claimed at 30 MW.
- Tamil Nadu signs a ₹18,600 crore three-project memorandum with L&T, including a ₹15,000 crore hyperscale and edge AI data centre expansion in Kancheepuram. The first large industrial memorandum of the new state government.
- L&T agrees to transfer its data centre and cloud services business to Vyoma.AI for ₹1,400 crore.
- LTN Compute wins a mega order from Together AI: 10,000 Nvidia B300 GPUs in a single cluster at the Chennai campus, classified at ₹10,000 to ₹15,000 crore. Phase 1 design of 250 MW with 150 MVA of power ready is disclosed for the first time.
- 18 MW commissioned or in commissioning. Around 24 MW being converted to AI workloads. The AI factory is not live
9Procurement
Rows with a lock are the paid layer.
10Assumptions and method
11Limits and open questions
12Sources
This record was compiled entirely from publicly available sources, cross-checked against one another.
Larsen & Toubro press release, August 2026·Larsen & Toubro press release, November 2021·The Hindu·The Hindu BusinessLine·Economic Times·Economic Times Manufacturing·Moneycontrol·Business Standard·BusinessToday·Fortune India·Reuters·DatacenterDynamics·Manufacturing Today·Voice & Data
Gridvik does not publish source URLs on record pages; citations are retained in the internal source register and are available on request.
A campus record built around the only figures that can be verified against each other. Where the numbers do not reconcile, the page says so and shows the arithmetic.
Corrections are free and published with a date.