Facility record · Status corrected · Verified 22 Oct 2026

Avisirah Technologies — Navi MumbaiAvisirah Technologies Private Limited · Navi Mumbai, Maharashtra · 5.5 MW planned

Record PRJ-045Maharashtra — Navi MumbaiTier B — procurement-relevantStatus corrected11 public sources cross-checked
Funding stageFacility recordLand not acquiredAdditive when built
5.5MW
IT load planned
1,100
Racks
5kW
Per rack, design average
₹125cr
Debt drawn
₹250cr
Programme ceiling
2
Phases

Avisirah Technologies is building a 5.5 MW colocation data centre in Navi Mumbai in two phases — 2.5 MW then 3.0 MW — across about 1,100 racks at a 5 kW average design density, on a shared land parcel with a shared power and cooling backbone. It is the smallest project Gridvik has recorded so far and, unusually, one of the most precisely specified. It has drawn ₹125 crore of debt from Syndicate Finance and contemplates up to ₹250 crore. The proceeds are partly for acquiring the land — which means the site had not been bought when the financing closed. The registry carried this as under construction. It is not.

1At a glance

Operator
Avisirah Technologies Private Limited. Suresh Gurav is named as a director
Lender
Syndicate Finance. A ₹50 crore secured facility in May 2025, extended by a further ₹75 crore facility announced on 11 September 2026
Location
Navi Mumbai. The specific plot is not published and, on the company’s own use-of-proceeds statement, had not been acquired
Facility type
Greenfield colocation, described by the company as Uptime Tier III-equivalent
Capacity
5.5 MW of IT load at completion. Phase I about 2.5 MW, Phase II about 3.0 MW
Racks and density
About 1,100 racks at a 5 kW average design density. The arithmetic is exact: 1,100 racks at 5 kW is 5.5 MW
Site arrangement
A single shared land parcel with a shared power and cooling backbone across both phases
Debt to date
₹125 crore drawn. A further programme of up to ₹125 crore during 2027 and 2028, subject to milestones, documentation and credit approval, taking the potential total to ₹250 crore
Cost per megawatt
About ₹45 crore per MW on the ₹250 crore ceiling, or ₹50 crore per MW on Phase I alone. Both are consistent with Indian market rates
Status
Funding stage. Land not acquired, no construction evidenced. Corrected from "under construction"

2The building

The specification, as published
ParameterValueNote
Total IT load5.5 MWCompany statement
Phase Iabout 2.5 MWCompany statement
Phase IIabout 3.0 MWCompany statement
Racksabout 1,100Company statement
Average design density5 kW per rackStated as a design average, not a ceiling
Redundancy standardUptime Tier III-equivalentEquivalence claimed, not a certification. No certificate, body or date published
LandShared parcel across both phasesNot yet acquired
Power and coolingShared backbone across both phasesCapacity of the connection not disclosed
Phase cost₹125 crore eachTwo phases, ₹250 crore total programme

Five point five megawatts is a small facility. For scale, one Sify tower in Noida is 26 MW and Yotta’s D2 is 60 MW. But the specification is the most complete Gridvik has found on any project of this size, and that has commercial value: a supplier can size a bill of materials from it.

At 5 kW a rack and 1,100 racks, the electrical and mechanical plant is conventional: air-cooled chillers or a water-cooled system, room-level precision cooling, N+1 or 2N uninterruptible power supply, and diesel generation for backup. Nothing exotic is required, which is why the cost per megawatt lands in the normal ₹45 to ₹50 crore range.

3The money

Secured facilityMay 2025₹50 crSecond facilitySeptember 2026₹75 crExtended to dateaggregate₹125 crProgramme ceiling2027 to 2028, subject to approvalsup to ₹250 crDebt raised against a site that had not yet been acquired. The last bar is a condition, not a commitment.
Figure 1Debt drawn over eighteen months against the contemplated programme. The final bar is conditional and the company says so explicitly.

The financing structure is worth reading carefully because it shows how a small Indian data centre actually gets built.

May 2025
A ₹50 crore secured facility from Syndicate Finance. This is the capital that funds the early development work
September 2026
A further ₹75 crore facility, taking the aggregate to ₹125 crore
2027 to 2028
A contemplated programme of up to ₹125 crore more, expressly subject to project milestones, definitive documentation, credit approvals and customary conditions
Total possible
Up to ₹250 crore across the programme
Use of proceeds
Land acquisition in Navi Mumbai, facility development, civil, electrical, power, cooling and connectivity works, procurement and installation of computing and data centre equipment, and working capital
What the lender said
Syndicate Finance declined to comment, citing a policy of not discussing individual clients or lending relationships
What this structure tells you
Two phases and staged debt against milestones is exactly the right structure for a first-time developer at this scale. It is also why the land had not been bought: the money buys the land, rather than the land securing the money

45 kW a rack is not AI density

The announcement calls this an AI data centre. The specification says 5 kW a rack on average. Those two statements describe different buildings.

Rack density by workload
WorkloadTypical rack densityWhat it needs
General colocation, as specified here5 kWAir cooling, conventional power distribution
Cloud and enterprise compute8 to 15 kWAir cooling with containment, higher busway capacity
AI inference20 to 60 kWLiquid cooling, often direct to chip
AI training, current generation60 to 130 kW and aboveDirect liquid cooling, high-voltage distribution on the floor

At 5 kW a rack, this is a conventional colocation building. That is not a criticism — 5 kW is where a great deal of Indian demand actually sits, and it is a sensible thing to build. But it will not host an Nvidia training cluster, and a buyer should not approach it expecting to.

The gap has a second consequence. A building specified at 5 kW a rack that later wants to take AI workloads needs more than new cooling: it needs more power per cabinet, a different electrical topology, and possibly a different floor loading. That retrofit is expensive and it is decided now, at design, not later.

The number to hold on to

5 kW a rack. Gridvik has now recorded Yotta D1 at 5.76 kW and this facility at 5.0 kW. Both are labelled hyperscale or AI-ready in their own marketing. Both are conventional colocation buildings.

In this market, the density figure tells you what a building is. The label tells you what the developer hopes it will be called.

5The status correction

Before and after
FieldAs carriedCorrectedWhy
StatusUnder constructionFunding stageThe September 2026 announcement lists acquisition of land in Navi Mumbai as a use of the new facility. You cannot be under construction on land you have not bought
Capacity basisUnstatedIT load, design, stated by the companyThe company states 5.5 MW of IT load explicitly
Investment₹125 crore financed₹125 crore drawn; up to ₹250 crore contemplatedThe higher figure is conditional on milestones and credit approvals
TimelineTwo phases2.5 MW + 3.0 MW, dates not publishedPhase sizes are published. Dates are not

This is a small correction with a large practical consequence. A project under construction has a procurement schedule. A project that has raised debt against land it is about to buy has an option.

Gridvik publishes these corrections in full because a registry that quietly upgrades announced projects into construction sites is worse than no registry.

6Specifications that do not exist

This section exists because it is the clearest illustration of why Gridvik is worth paying for, and it involves no one in this deal.

Within days of the September 2026 financing announcement, at least one aggregator published a detailed technical write-up of this facility. The company has never published any of the following:

Claims circulating that are not in the company’s own release
ClaimWhat the company actually said
12 MW of total IT load5.5 MW of IT load
Phase 1 of 4 MW ready in Q3 2027Phase I of about 2.5 MW, no date given
Up to 80 kW per rack, liquid-cooling ready5 kW average design density
Designed PUE of 1.28 or belowNo PUE has ever been published
A dedicated 33/11 kV on-site substation with LFP battery storageNo substation, voltage or battery specification has been published
Credit-grade institutional infrastructure financiersSyndicate Finance, which declined to comment
Why this is the product

Every line above is plausible. That is the problem. A supplier who scopes a liquid-cooled, 80 kW-per-rack, 12 MW facility against a 5 kW colocation building has wasted a quarter and damaged its credibility with the buyer.

Gridvik exists because this material is now generated faster than it can be checked. The specification above is the company's own, and the company is the only party that has published it.

7Timeline

  • Syndicate Finance extends a ₹50 crore secured facility to Avisirah Technologies.
  • Avisirah announces a further ₹75 crore facility from Syndicate Finance, taking the aggregate to ₹125 crore, and discloses the facility specification publicly for the first time: 5.5 MW of IT load, about 1,100 racks at 5 kW average design density, two phases of 2.5 and 3.0 MW on a shared parcel with a shared power and cooling backbone.
  • The company states a contemplated further programme of up to ₹125 crore during 2027 and 2028, subject to milestones and credit approvals, for a total of up to ₹250 crore.
  • Land acquisition remains a stated use of proceeds. No purchase, allotment, power sanction, design, contractor or construction is on the public record.
  • The contemplated further financing window. No construction or commissioning date has been published

8Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
This record
A 5.5 MW colocation facility at funding stage, with a published specification and no site yet
What is orderable now
Ups and diesel generation for about 5.5 MW of IT load, precision cooling for 1,100 racks at 5 kW, low-voltage distribution, and a shared backbone across two phases
What is not orderable
Anything site-dependent: transformers, substation works, civil works and the incoming supply, all of which need the land first
The phase structure
Two phases of ₹125 crore each. The first phase is the entire addressable order for 2026 and 2027
Why the density matters to a seller
5 kW a rack means air cooling and conventional power distribution. No coolant distribution units, no rear-door heat exchangers, no liquid loop
The key risk
The land is not bought. Everything downstream of it is contingent
Order window
2027 onward, conditional on land acquisition and first drawdown
Procurement heat
Low now. The single most watchable trigger in this record is a land registration
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

Rows with a lock are the paid layer.

9Assumptions and method

What is sourced
The facility size, phase split, rack count, density, redundancy description, site arrangement, both loan facilities, the aggregate and contemplated totals, the conditions attached to the further programme, the use of proceeds, and the lender’s no-comment position
What is derived
Cost per megawatt on two different bases, the per-rack density arithmetic, and the comparison with other facilities in the registry
Capacity figure used
5.5 MW, IT load, additive when built. Not counted as live or building because nothing is built
Additivity rule
Additive as a distinct facility, but it contributes zero to any current total
Status correction
Changed from under construction to funding stage, with the reason published above
Currency
₹88.40 to the US dollar, fixed quarterly

10Limits and open questions

The central gap
No land and no site. Everything else about this project is unusually well specified
Land
Acquisition in Navi Mumbai is a stated use of the September 2026 proceeds. No purchase or allotment has been recorded
Power
The connection capacity behind a shared backbone is not disclosed. 5.5 MW of IT load needs roughly 7 to 8 MW of supply
Phase dates
Not published. Neither phase start nor commissioning has a date
Certification
Described as Uptime Tier III-equivalent. No certificate, issuing body or date has been published. Treated as a claim, not a certificate
Tenants
None named. A speculative colocation building at this scale depends entirely on local demand
The further ₹125 crore
Conditional on milestones, documentation and credit approval. It should not be read as committed capital
What we will not claim
No construction status, no commissioning date, no site, no tenants, no PUE and no certification

11Sources

This record was compiled entirely from publicly available sources, cross-checked against one another.

Avisirah Technologies announcement·Syndicate Finance statement·Press Trust of India·The Wire·The Tribune·Hindustan Times·LiveMint·Business Standard·Economic Times·Times of India·Prop News Time

Gridvik does not publish source URLs on record pages; citations are retained in the internal source register and are available on request.

What this page is, and what it is not

A facility record with a published specification, a corrected status and a section on the specifications that circulate but were never published.

Corrections are free and published with a date.