High Density Data Centre — Naraj, OdishaHigh Density Data Centre Ltd, an Adani Infra (India) company · Naraj, Odisha · 1 GW proposed

Record PRJ-049Odisha — NarajTier B — approved, not built14 public sources cross-checked
Approved, not builtCampus proposalSite district disputedNot AdaniConneX
1GW
Proposed
₹1,04,550cr
Proposed
250ac
Land earmarked
₹104.55cr
Per MW implied
2.4cr
Units a day at full load
1,000
Jobs claimed

On 23 September 2026 the Odisha high-level clearance authority, chaired by the chief minister, approved a 1 GW integrated data centre park proposed by High Density Data Centre Limited, a subsidiary of Adani Infra (India) Limited, at an investment of ₹1,04,550 crore on about 250 acres of land earmarked near Naraj. It was one of 27 projects worth ₹2.47 lakh crore cleared in a single meeting, and part of ₹1,42,941 crore of data centre and AI approvals that day. No power allocation, water allocation, environmental assessment or memorandum has been made public. That absence has become a public dispute in the state, and the arithmetic behind it is straightforward.

1At a glance

Proponent
High Density Data Centre Limited. Confirmed by the state government as a subsidiary of Adani Infra (India) Limited, which is separate from AdaniConneX
What was approved
An integrated data centre park with a proposed 1 gigawatt data centre
Investment
₹1,04,550 crore, about $11.8 billion at ₹88.40 to the dollar. Some coverage rounds this to ₹1.04 trillion
Land
About 250 acres earmarked by the state government
Location
Contested. Reported as Naraj, near Cuttack; the state clearance listings place the project in Khordha district
Approved by
The 46th meeting of the Odisha high-level clearance authority, chaired by chief minister Mohan Charan Majhi, on 23 September 2026
Jobs claimed
About 1,000
What is not public
The memorandum, the clearance minutes, the power source and allocation, the water allocation, and the environmental assessment
Status
Approved. No construction, energisation or operation. No date has been given
Additivity
Flagged unresolved in the registry. Contributes nothing to any total because nothing is built and the capacity basis is unstated

2What was actually approved

The distinction matters and it is routinely lost. A high-level clearance authority approval is a state government decision to permit a large investment. It is not a land grant, a power connection, an environmental consent, a building permit or a financing commitment.

What an HLCA approval does and does not do
It doesIt does not
Signals state backing and unlocks the single-window processTransfer or lease land — the 250 acres are described as earmarked, not allotted
Places the project in the state’s published investment pipelineAllocate electricity or water
Commits the state to facilitation for approvalsGrant environmental clearance, which is a separate central or state process
Creates a public record of the proposed investment and capacityOblige anyone to spend anything, or fix a schedule

None of that makes the approval meaningless. In Indian project development, state clearance is a real milestone and usually precedes land allotment by months. It is simply the beginning of a process rather than the end of one, and the ₹1.04 lakh crore figure does not change hands at this stage.

The comparison the coverage led with

This is described as the second-largest data centre proposal by an Indian conglomerate, behind Reliance Industries’ ₹1.08 lakh crore AI data centre and cable landing station in Andhra Pradesh.

Both are approvals or agreements. Neither is a building. Ranking projects by approval value places announcements above capacity, which is how a country ends up with a pipeline several times larger than anything it can build.

3Naraj or Khordha

The site is published two different ways, and this is the kind of discrepancy that matters to anyone who needs to know where the power and water will be drawn from.

Where the project is said to be
SourceLocation given
State clearance listings and several national reportsKhordha district
Economic Times and Odisha trade coverageNaraj, near Cuttack, on about 250 acres
Business Standard, quoting the industries additional chief secretaryThe proposal was approved; about 250 acres earmarked at Naraj

Naraj sits on the Mahanadi in Cuttack district, at the head of the Mahanadi delta and next to the barrage that supplies drinking water to Bhubaneswar and Cuttack. Khordha district contains Bhubaneswar and the state’s existing IT corridor. They are adjacent districts with very different water and power situations.

Gridvik records both and does not choose. The state government’s own additional chief secretary, quoted by name, said Naraj. That is the strongest single statement in the public record, and it is also the statement that makes the water question urgent, because Naraj is where the region’s drinking water is drawn.

4₹104.55 crore per megawatt

The approved investment against published Indian build costs
ProjectPer MWWhat ₹1,04,550 crore would buy at that rate
Uttar Pradesh committed pipelineabout ₹33 croreabout 3,170 MW
CtrlS Chennai campusabout ₹56 croreabout 1,870 MW
Yotta D1about ₹52 croreabout 2,010 MW
High Density Data Centreabout ₹104.55 crore1,000 MW as approved

At ₹104.55 crore per megawatt, this project costs roughly twice the standard Indian build rate for the capacity it declares. Two explanations fit and neither is disqualifying.

The money is not all data centre capital. An integrated park may include power generation, water treatment, a cable landing station, internal transmission, GPUs and a decade of phasing. Once GPUs are in the number, the per-megawatt comparison breaks down completely — Yotta is spending more than $2 billion on GPUs alone inside a single 60 MW building.

The 1 GW is a ceiling, not a first phase. If the park is built over fifteen years to 1 GW while the initial investment covers a fraction of it, the per-megawatt figure for what actually gets built first is much lower.

Either way, the announced number and the announced capacity do not describe the same thing, and both are published without a phasing schedule.

5Two and a half crore units a day

This is the part of the record that has become a public argument, and the arithmetic is checkable.

The calculation
1,000 MW running continuously for 24 hours is 24,000 megawatt hours a day, which is 2.4 crore units
The comparison made publicly
A former Union minister wrote to the chief minister stating that this is roughly the entire daily domestic electricity consumption of Odisha’s 4.5 crore people
The check
The arithmetic is right, and it is the correct order of magnitude. A 1 GW continuous load is a very large amount of power for one site, whatever the comparison
Water
The same letter asks how 30 million litres a day would be supplied, against a reported existing drinking water deficit of over 100 million litres a day in Bhubaneswar
The wider water problem
The Mahanadi is already stressed and subject to an unresolved inter-state dispute with Chhattisgarh
What the state has not published
Any power source, any allocation, any water allocation, any environmental impact assessment, the memorandum, or the clearance minutes
Why this is a commercial question, not only a political one

A 1 GW data centre needs either a dedicated generation source or a very large transmission allocation. Neither has been named. In Odisha, coal is the abundant option and the state has surplus generation — which is precisely why this project exists here.

For a supplier, the practical consequence is that the power question is the schedule. Nothing can be ordered until the connection is sanctioned, and no connection has been sanctioned. 30 million litres a day of water is likewise an engineering scope — treatment, storage, pipelines — that has not been defined and cannot be priced.

Gridvik publishes the arithmetic and not the conclusion. The environmental and drinking water questions are for the state’s regulators to answer, and the documents to answer them with have not been released.

6Two Adani Odisha deals, not one

The Adani group has two separate Odisha data centre commitments, announced within weeks of each other, through two different corporate structures and possibly for two different things.

The two commitments, kept apart
High Density Data CentreAdani and International Holding Company
AnnouncedApproved 23 September 2026Signed earlier in September 2026
Value₹1,04,550 crore₹50,000 crore
CounterpartyOdisha government, as approverInternational Holding Company of Abu Dhabi, as partner
EntityHigh Density Data Centre Ltd, under Adani Infra (India) LtdNot specified in the reporting reviewed
Capacity1 GW proposedNot specified in the reporting reviewed
Relationship between the twoNot disclosed by any partyNot disclosed by any party

Trade coverage describes them as separate and states that the ₹1.04 lakh crore project is a standalone venture distinct from the ₹50,000 crore agreement with International Holding Company. Gridvik records them as separate and does not add them together, because no party has stated whether they cover the same site, the same gigawatt or different phases of one programme.

There is a third entity in the picture as well. AdaniConneX is the group’s established data centre joint venture, with a unit operating in Chennai and projects in Mumbai, Pune and Hyderabad. It is the group’s data centre arm in most market descriptions, and it is not the entity proposing this project.

The registry rule Gridvik applies

Do not merge this 1 GW with AdaniConneX’s capacity, and do not add it to the ₹50,000 crore Abu Dhabi commitment.

Adani now has at least three data centre vehicles reporting into different parts of the group. Until the company publishes a portfolio statement reconciling them, no third party can total Adani’s data centre capacity with confidence — and any figure that does is a guess wearing a spreadsheet.

7The clearance meeting

High Density Data CentreAdani Infra subsidiary, 1 GW at Naraj₹1,04,550 crHCLTechAI data centre, 24 July 2026₹14,257 crTwo other AI and data centre projectscombined₹24,134 crTotal, four projectsone high-level clearance meeting₹1,42,941 crFour approvals in a single meeting, dominated by one proposal that is larger than the other three together several times over.
Figure 1The four data centre and AI approvals from the 23 September 2026 clearance meeting. The two unnamed projects are shown combined because their individual values were not separated in the reporting reviewed.
What else was cleared that day
Value
Total projects cleared at the 46th clearance authority meeting27 projects, about ₹2.47 lakh crore
Of which data centre and AI projects4 projects, about ₹1,42,941 crore
High Density Data Centre, Naraj₹1,04,550 crore
HCLTech AI data centre₹14,257 crore (see record PRJ-042)
Two further AI and data centre proposalsAbout ₹24,134 crore combined
Share of the day’s value that was data centresabout 58%

More than half the value of every project approved by Odisha on a single day was two data centre proposals and two AI projects, of which one accounted for three quarters. This is what an investment pipeline concentrated in one sector looks like when measured by announcement value.

Odisha is a serious power state with surplus generation and low industrial tariffs, which is a genuine advantage in this industry. It is also a state that had no operating hyperscale data centre of significance before 2026, and now carries approvals for more data centre investment than most countries.

8Timeline

  • The Adani group signs a ₹50,000 crore agreement with Abu Dhabi’s International Holding Company for a hyperscale AI data centre in Odisha.
  • The 46th Odisha high-level clearance authority meeting, chaired by the chief minister, clears 27 projects worth about ₹2.47 lakh crore. Among them, High Density Data Centre Ltd — an Adani Infra (India) subsidiary — is approved for a ₹1,04,550 crore integrated data centre park with a 1 GW data centre on about 250 acres.
  • National coverage describes the project as the second-largest data centre proposal by an Indian conglomerate, after Reliance’s ₹1.08 lakh crore Andhra Pradesh project. Trade coverage reports the project is separate from the ₹50,000 crore Abu Dhabi agreement.
  • A former Union minister writes to the chief minister seeking clarity on power, water, environmental impact and the public availability of the memorandum and clearance minutes. He states the project would consume about 2.4 crore units of electricity and 30 million litres of water a day.
  • No memorandum, clearance minutes, power allocation, water allocation, environmental assessment, land allotment order, construction start or schedule is in the public domain.
  • No phase, commissioning or construction date has been published by any party

9Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
This record
A state-cleared 1 GW proposal with no land allotment order, no power sanction, no water allocation and no design
What a 1 GW campus would need
Substantially more electrical and mechanical plant than any building in this registry, plus dedicated transmission, water treatment and probably on-site generation
The power question is the gate
Nothing can be ordered until a connection is sanctioned. The state’s surplus generation makes this the most likely source, but nothing has been allocated
Water is an engineering scope
About 30 million litres a day at full load, which means treatment, storage and pipeline works that have not been defined
Phasing is unknown
1 GW over an unstated number of years. The first orderable phase is unknown
Why it is still worth tracking
Adani Infra builds at scale and on schedule more reliably than most Indian developers, and a 250-acre site with state backing is a real asset
Order window
Cannot be stated. The trigger to watch is the land allotment order, then the power sanction
Procurement heat
Cold. This is a 2029 to 2035 opportunity, not a 2026 one
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

Rows with a lock are the paid layer.

10Assumptions and method

What is sourced
The clearance date, the authority and its chair, the proponent and its parent, the investment value, the 1 GW capacity, the 250 acres, the site descriptions, the jobs figure, the composition of the clearance meeting, the separate Abu Dhabi agreement, and the contents of the public letter
What is derived
The ₹104.55 crore per megawatt figure, the equivalent capacities at other build rates, the 2.4 crore unit daily consumption, the share of the clearance day, and the assessment of what the investment must include
Capacity figure used
None. The 1 GW is a proposed ceiling with an unstated basis and is not added to any total
Additivity rule
Flagged unresolved. Must not be merged with AdaniConneX capacity (PRJ-009) or with the ₹50,000 crore Abu Dhabi commitment
The 2.4 crore units
Arithmetic on a 1 GW continuous load. It assumes full utilisation, which no data centre achieves; a realistic average utilisation would reduce the figure
Currency
₹88.40 to the US dollar, fixed quarterly

11Limits and open questions

The central gap
No document other than the approval itself. No memorandum, minutes, power allocation, water allocation or environmental assessment is public
Site
Naraj in Cuttack district and Khordha district are both reported, by sources that include the state government’s own officials
Capacity basis
Whether the 1 GW is IT load, gross facility load or a park-wide connection capacity is not stated
Power
No source, allocation or connection is named. This is the binding constraint on every gigawatt-scale proposal in India
Water
30 million litres a day at full load, with no allocation published, in a region reporting an existing drinking water deficit
Environmental clearance
A separate statutory process. No application or clearance is in the public record
Relationship to the Abu Dhabi agreement
Not disclosed by any party
Schedule
None. No phase, construction or commissioning date
What we will not claim
No built capacity, no schedule, no power source, no water source, no land ownership, and no total for the Adani group

12Sources

This record was compiled entirely from publicly available sources, cross-checked against one another.

Economic Times Datacenters·Business Standard·Odisha state clearance listings·Odisha TV·Times of India·Moneycontrol·BW Businessworld·Voice & Data·Entrepreneur India·Pragativadi·Orissa POST·Odisha Bytes·New Projects Tracker·Tele.net

Gridvik does not publish source URLs on record pages; citations are retained in the internal source register and are available on request.

What this page is, and what it is not

A record of a state approval for the largest data centre proposal in India, with the arithmetic that the approval does not answer.