Approved record · Verified 22 Oct 2026

SentraForge AI — Puri, OdishaSentraForge AI Limited with GVPR Engineers · Puri, Odisha · 120 MW proposed

Record PRJ-050Odisha — Puri districtTier B — approved, not built12 public sources cross-checkedFinancial close not achieved
Approved, not builtCampus proposalMost figures are first-partyJV structure unconfirmed
120MW
Proposed
₹22,634cr
Proposed investment
₹188.6cr
Per MW implied
₹7,089cr
Equity claimed
2,320
Jobs claimed
Dec 2027
Company target

On 23 September 2026 Odisha’s high-level clearance authority approved a 120 MW sovereign AI campus and global capability centre proposed by SentraForge AI, at ₹22,634 crore. It was one of four data centre approvals in that single meeting, and the second-largest by value. The company says it has ₹7,089 crore of equity committed and that it is in execution with a December 2027 facility target. What the state confirmed is the approval, the value and the jobs. Everything about the capacity, the equity and the schedule comes from the company’s own materials. That distinction decides what this record is worth.

1At a glance

Proponent
SentraForge AI Limited. National coverage describes it as a joint venture between Megha Engineering and Infrastructures Limited and GVPR Engineers Limited; the company’s own materials name GVPR as core equity backer, infrastructure co-promoter and foundational partner and do not confirm the MEIL interest
What was approved
An AI data centre and global capability centre
Declared capacity
120 MW. Stated by the company. The basis — IT load, gross facility load or connection capacity — is not given, and the state has not published a capacity figure
Investment
₹22,634 crore, about $2.56 billion at ₹88.40 to the dollar
Equity claimed
₹7,089 crore of equity capital committed, which is about 31% of the programme value. First-party claim, not independently verified
Financial close
Underway, not achieved. The company’s own wording
Location
Puri, Odisha in state clearance listings. A separate report places the land hub for this and the HCLTech project at Tangiapada near Info Valley, near Bhubaneswar
Jobs claimed
2,320, per the state clearance
Company targets
Initial campus-integrated services mid-2027; facility readiness December 2027. Neither is independently verified
Additivity
Flagged unresolved. Contributes nothing to any total, because nothing is built and the capacity basis is unstated

2Who SentraForge is

This is the first question a supplier asks about any 120 MW campus, and the public record does not answer it cleanly.

How the ownership is described
SourceDescription
State clearance reporting and national business pressA joint venture between Megha Engineering and Infrastructures Limited (MEIL) and GVPR Engineers Limited
Company materials and company-supplied releasesGVPR Engineers as core equity backer, infrastructure co-promoter and foundational partner. MEIL is not named
Company websiteSentraForge AI as the project company, in what it describes as the execution phase for a 120 MW sovereign AI campus

Both GVPR and MEIL are large Indian infrastructure contractors. GVPR is based in Hyderabad with a substantial civil works and power transmission business. That matters commercially: a data centre backed by a civil contractor is a construction-led project, which usually means the building gets built on schedule and the technology partnerships are arranged around it.

Gridvik records GVPR as confirmed because the company names it. MEIL is recorded as reported by the business press and not confirmed in the materials Gridvik reviewed. The distinction is left visible rather than resolved.

Why the ambiguity is worth publishing

If this is an MEIL and GVPR vehicle, it is one of the largest engineering groups in India entering sovereign AI compute, and the balance sheet behind a 120 MW build is not in doubt.

If it is GVPR alone, the project is being carried by a smaller company and the ₹15,545 crore of implied debt becomes the central question. That is a material difference and it should not be smoothed over.

3What the state confirmed, and what it did not

Sourcing, line by line
ItemWho says so
Approval by the high-level clearance authority on 23 September 2026State government
Investment of ₹22,634 croreState government
2,320 jobsState government
Located in PuriState government
120 MW of capacityCompany only
₹7,089 crore of committed equityCompany only
Financial close underwayCompany only
Execution phaseCompany only
Mid-2027 services and December 2027 facility readinessCompany only
Site of about 140 acres shared with HCLTech at TangiapadaTrade press, attributed to the state

The pattern is worth naming because it recurs in this market. States approve rupees. Companies announce megawatts. The rupee figure is in a government order and therefore reliable. The capacity figure is a website claim. Gridvik records both and marks which is which.

For this record that means the 120 MW is a company claim with no published basis. It is not a state-approved capacity, it has not been converted into racks, and no design document behind it has been released.

4₹188.6 crore per megawatt

This project₹22,634 crore for 120 MW₹188.6 crL&T Sriperumbudurthe previous outlier₹167 crCtrlS Chennai campusa built 72 MW park₹56 crYotta D1a built 28.8 MW tower₹52 crCost per megawatt of declared capacity. Only the bottom two bars describe buildings that exist.
Figure 1Cost per megawatt of declared capacity against every other benchmark in the registry. The top bar is a company claim about a site that does not exist yet; the bottom two are built buildings.

₹22,634 crore for 120 MW works out at ₹188.6 crore per megawatt, or about $21.3 million. That is the highest figure in this registry by a wide margin, and roughly three and a half times the standard Indian build cost of ₹52 to ₹56 crore per megawatt.

Three explanations fit, and they are not exclusive.

What the money could be
ExplanationEffect on the per-MW figure
GPUs are inside the numberEnormous. Yotta is spending over $2 billion on GPUs alone inside one 60 MW building, which is more than twice the entire cost of its six-building park
The global capability centre is inside the numberModerate. A large office and services operation with 2,320 jobs attached is a real capital cost that is not a data centre
120 MW is a ceiling reached over a decadeLarge. If the first phase is 30 MW and the 120 MW arrives in 2035, the early phases carry the whole figure in this ratio
Land, substation, water and internal transmission are inside the numberModerate. A campus needs infrastructure that a single building does not

What cannot be concluded is that the project is overpriced. What can be concluded is that ₹22,634 crore and 120 MW do not describe the same object, and any supplier who treats one as a proxy for the other will be wrong by a factor of three.

5The site, described three ways

Three descriptions of where this project is, from sources that include the state government. They may all be true; nobody has published a parcel number.

Where the project is said to be
SourceLocation given
State clearance listingsPuri district
Company websiteOdisha, with no district given
Trade press, quoting the stateA 140-acre land parcel near Bhubaneswar at Tangiapada near Info Valley, to serve both the HCLTech and SentraForge projects

This matters more than a place name usually would. Puri district and the Bhubaneswar periphery are different propositions for power, water and connectivity, and the 140-acre parcel described in trade coverage is a shared hub for two separate approved projects.

If HCLTech and SentraForge both sit inside 140 acres at Tangiapada, the implications are concrete: shared or adjacent grid infrastructure, a shared or at least sequenced water supply, and two separate operators competing for the same local utilities and the same construction labour market at the same time. Gridvik does not assume a shared campus and does not sum the acreage. It records the question.

A note on HCLTech’s own record

HCLTech’s announcement describes its site as the Odisha Sovereign AI Park. SentraForge is described as being in Puri. Trade coverage puts both on Tangiapada near Info Valley. Whether these are three names for one place, or two places and one park, is unresolved across two records in this registry.

That is exactly the kind of gap that produces double counting in a market database. See record PRJ-042 for HCLTech’s side of it.

6₹7,089 crore of equity and a closure that is not closed

Equity claimed
₹7,089 crore committed
Share of programme value
About 31%. The remaining ₹15,545 crore would be debt
What the company says about debt
That "full financial closure is underway"
What that means precisely
Money has not been closed. A project in financial closure has lenders in due diligence, term sheets or negotiation, not commitments
Why the distinction matters
Until closure, nothing can be ordered at scale. Equipment contracts follow financial close in every project of this kind, because nobody buys switchgear against an intention
The implied debt burden
About ₹15,545 crore on a 120 MW campus. For scale, that is more than the entire announced cost of Yotta’s six-building Greater Noida park
Who would lend
Not named. No bank, fund, non-banking lender or export credit agency has been identified
The state’s position
Odisha approved the project. It has not been reported as committing any capital, unlike the HCLTech project where financial assistance is explicitly part of the figure

There is nothing unusual in a project of this size being at financial close at the approval stage. Approval is what you need in order to raise the money. What is unusual is announcing the megawatts, the schedule and the execution phase before the money is closed, and that is a pattern worth recognising rather than a criticism of one company.

7Timeline

  • The 46th Odisha high-level clearance authority meeting, chaired by the chief minister, approves SentraForge AI’s ₹22,634 crore AI data centre and global capability centre, with 2,320 jobs claimed. It is one of four data centre and AI approvals worth ₹1,42,941 crore that day.
  • National coverage describes the project as a joint venture of Megha Engineering and Infrastructures and GVPR Engineers, with a 120 MW capacity and a site in Puri.
  • A company-supplied update is published naming GVPR as core equity backer and infrastructure co-promoter, and describing the project as next-generation sovereign AI compute infrastructure.
  • Company-backed coverage describes the project as one of India’s five largest AI facilities and states the capacity can scale as AI requirements grow.
  • The company describes itself as in execution with ₹7,089 crore of equity committed and financial closure underway. No land allotment order, power allocation, water allocation, design, contractor award or construction is in the public record
  • Company-stated targets for initial services and facility readiness. Not independently verified and not supported by any published construction schedule

8Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
This record
A state-approved 120 MW proposal at financial close, with no land allotment order, no power sanction and no design
Why it is still worth tracking
It is one of the largest declared AI capacities in the registry with a sponsor that has civil and power transmission engineering capability in-house
The structural advantage for sellers
A contractor-led sponsor builds through its own supply chain for civil and transmission, and buys the data centre technology — cooling, power distribution, networking — from outside
What has to happen first
Financial close, then land allotment, then a power sanction. The company’s own sequence puts facility readiness at December 2027, which leaves very little room for all three
The density question
A sovereign AI campus implies high-density, liquid-cooled halls. No density, rack count or cooling architecture has been published, so nothing can be sized
Order window
2027 at the earliest, and only after financial close is announced
Procurement heat
Cold. One announcement does not create a bill of materials
Decision role
SentraForge project leadership; GVPR infrastructure and procurement
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

Rows with a lock are the paid layer.

9Assumptions and method

What is sourced
The approval date, authority and value, the jobs figure, the four-project clearance total, the ownership descriptions from each source, the company’s equity, closure status and targets, and the site descriptions
What is derived
The per-megawatt cost, the equity share, the implied debt, and the comparison with other build costs in the registry
Capacity figure used
None. The 120 MW is a company claim with no stated basis and is not added to any total
Additivity rule
Flagged unresolved. Not summed with the HCLTech project, the High Density project, or any state total
On the MEIL interest
Reported by national business press, not confirmed in company materials. Recorded as reported and left visible
Currency
₹88.40 to the US dollar, fixed quarterly

10Limits and open questions

The central gap
Every figure that matters except the rupees is first-party. Capacity, equity, closure status, schedule and execution phase all come from the company
Capacity basis
IT load, gross load or connection capacity — not stated. The difference is a factor of up to 1.5
Ownership
The MEIL interest is reported by the press and absent from company materials
Site
Puri district, or Tangiapada near Info Valley near Bhubaneswar, or a shared 140-acre hub. No parcel number has been published
Financial close
Underway. No lender, no term sheet, no amount
Power and water
Nothing published. A 120 MW campus is a very large utility commitment and neither has been allocated publicly
Design
No building count, floor area, density, redundancy standard, cooling architecture or PUE
What we will not claim
No built capacity, no financial close, no construction, no schedule, no power source, and no confirmation of the MEIL interest

11Sources

This record was compiled entirely from publicly available sources, cross-checked against one another.

SentraForge AI official release·SentraForge AI project pages·Government of Odisha clearance·Business Standard·Economic Times Datacenters·BusinessToday·Odisha TV·Mid-Day·The Tribune·Times of India·Pragativadi·Indian Startup News·Vainetra·The News Insight

Gridvik does not publish source URLs on record pages; citations are retained in the internal source register and are available on request.

What this page is, and what it is not

A record that separates what a state government confirmed from what a company announced about the same project, because in this market they are rarely the same list.