CtrlS — Five Metro Optical Networks with CienaCtrlS Datacenters Limited and Ciena · Chennai, Hyderabad, Kolkata, New Delhi, Noida · up to 100 Tb/s

Record PRJ-052National — five metrosTier B — connectivity recordCarries no data-centre MW11 public sources cross-checked
Network infrastructureCarries no MWNon-additiveHyperscaler unnamed
100Tb/s
Aggregate capacity
5
Metro networks
9
Existing data centres
800Gb/s
Per wavelength
~125
Wavelengths, derived
0
New MW

On 28 September 2026 Ciena announced that CtrlS is building five metropolitan optical networks connecting nine of its existing data centres across Chennai, Hyderabad, Kolkata, New Delhi and Noida, delivering up to 100 terabits per second. It is part of a larger managed optical fibre network deployment for a hyperscale customer that neither company has named. This record carries no data-centre capacity. It is here because it marks the point where India’s largest Rated-4 operator stopped selling floor space and started selling light.

1At a glance

Operator
CtrlS Datacenters Limited, which operates 19 data centres across nine Indian markets with over 370 MW of live capacity and a stated 4.4 GW of projects at various stages of execution
Technology partner
Ciena Corporation, a Nasdaq-listed optical networking company
What is being built
Five metropolitan optical networks connecting nine existing data centres
Cities
Chennai, Hyderabad, Kolkata, New Delhi and Noida. Delhi and Noida are counted separately, though they are adjacent clusters
Capacity
Up to 100 Tb/s of aggregate network throughput
Equipment
Ciena’s WaveLogic 5 Extreme-powered Waveserver platform and 6500 Reconfigurable Line System, with the Navigator Network Control Suite for automation
Services
Ciena’s services organisation is providing end-to-end project management
The larger programme
Part of a managed optical fibre network deployment for a hyperscale customer. Neither company has named the customer
Not disclosed
Contract value, deployment schedule, whether all five networks go live together, and the identity of the hyperscaler
Data-centre capacity
Zero. This record adds no megawatt to any total and the registry sets its additivity flag to not applicable

2What was deployed

The technical stack, and what each part does
ComponentRole
WaveLogic 5 ExtremeCiena’s coherent optical engine, capable of carrying up to 800 Gb/s on a single wavelength of light
Waveserver platformCompact optical transport purpose-built for data centre interconnection — the box at each end of a link
6500 Reconfigurable Line SystemThe optical transport layer in the middle, giving a programmable photonic path that can be provisioned and re-routed without physical changes
Navigator Network Control SuiteSoftware that automates network operations and speeds up provisioning of new services
Ciena ServicesEnd-to-end project management for the deployment

The reconfigurable line system is the part that matters commercially. It means CtrlS can provision a new wavelength path between two of its buildings in software rather than sending engineers to patch fibre. For a customer buying connectivity as a service, that is the difference between a delivery timeline measured in weeks and one measured in hours.

3100 Tb/s, translated

Per wavelengthCiena WaveLogic 5 Extreme800 Gb/sWavelengths needed for 100 Tb/sderivedabout 125Per metro networkfive metros20 Tb/sPer data centrenine facilities11.1 Tb/sTwo different units on one chart. The first bar is the unit of capacity; the other three are totals divided.
Figure 1The first bar is the capacity of one wavelength. The other three are 100 Tb/s divided, and are shown to give a sense of scale rather than as published figures.

One hundred terabits per second is a number most people cannot place. Four ways to make it concrete:

Putting 100 Tb/s in context
MeasureFigureNote
At 800 Gb/s per wavelengthabout 125 wavelengthsDerived. The physical light paths the system provisions
Across five metros20 Tb/s eachDerived. Average, not a published per-city figure
Across nine data centresabout 11.1 Tb/s eachDerived. Average
Per secondabout 12.5 terabytesDerived from 100 Tb/s at 8 bits to a byte
A 50 GB model filetransferred in about 4 millisecondsIdealised, at full line rate across the whole network

The useful comparison is not speed but shape. This is not a link between two buildings; it is a ring around five Indian cities with 125 wavelengths of capacity that can be re-pointed at will. It exists because AI workloads move enormous volumes of data between facilities — training data, checkpoints, model replicas — and that traffic runs east to west between data centres rather than out to users.

The unit trap this page exists to prevent

100 Tb/s is not 100 MW, and it is not 100 of anything a data centre buyer orders. Network throughput and electrical capacity are unrelated units that appear together in press releases constantly.

Gridvik’s registry carries this record with zero capacity. Anyone adding a network figure to a capacity total is producing a number that means nothing.

4Nine existing buildings, not nine new ones

The single most misread element of this announcement is the phrase "nine data centres". These are buildings CtrlS already operates. The project adds fibre and optical equipment between them, not concrete.

What is and is not new here
NewNot new
Optical transport equipment in nine existing buildingsThe nine data centres themselves
About 125 wavelengths of coherent capacityAny data-centre capacity, rack or megawatt
Metro fibre routes between the buildingsThe operator’s 370 MW of live capacity
A managed network service layerThe 4.4 GW of projects at various stages of execution

The cities are also worth noting as a set. Chennai, Hyderabad, Kolkata, New Delhi and Noida — but not Mumbai, which is India’s largest data centre market and where CtrlS operates several facilities. The release does not explain the omission, and Gridvik does not assume the reason.

Two possible readings. Either Mumbai connectivity was already in place and this programme extends the model to the other metros, or this is a first phase and Mumbai follows. Both are consistent with what was announced.

5Why a managed network is a different business

This is the part worth paying attention to, because it changes what CtrlS is.

The old model
Sell colocation space and power by the rack or by the megawatt. The revenue is a function of floor area and electricity
The managed network model
Sell connectivity as a service over dedicated fibre built to a specific customer’s requirements. The revenue is a function of ports, wavelengths and service levels
Who builds it
CtrlS builds and operates the optical layer. The hyperscaler does not have to own, build or run its own metro network in India
Why it matters to the hyperscaler
Regulatory requirements and speed. A local operator with existing rights of way and buildings can deliver a metro network faster than a foreign cloud company can arrange one
Why it matters to CtrlS
A second, higher-margin revenue line attached to buildings it already owns, with a customer locked into its infrastructure rather than merely renting racks in it
The strategic reduction
CtrlS stops competing for the hyperscaler’s data centre business and starts being paid to connect it

Ciena’s own numbers show why this model is spreading. In its fiscal third quarter of 2026, direct cloud-provider revenue rose 82% year on year and represented 53% of company revenue, with revenue from the Reconfigurable Line System and Waveserver both up more than 55%. Hyperscalers are buying optical transport in volume, and increasingly they are buying it through regional operators rather than directly.

For an Indian data centre operator, that is the most attractive business in the market right now: it uses assets you already own, sells to a customer with almost unlimited bandwidth appetite, and raises switching costs without requiring another megawatt of power.

6The customer nobody will name

Every party in this announcement is named except the one paying for it. Neither CtrlS nor Ciena identifies the hyperscaler, the contract value, the deployment schedule, or whether all five networks go live together.

That is normal. Managed optical fibre network agreements are usually confidential, because the hyperscaler does not want its Indian network topology in the public domain.

What that absence costs an analyst
QuestionPublic answer
Who is the customer?A leading hyperscaler. Not named
How much is the contract worth?Not disclosed
When does it complete?No date given
Do all five metros go live together?Not specified
Is this a multi-year service agreement or a one-off build?Not specified
Which CtrlS buildings are the nine?Not individually identified

The reasonable inference — and it is an inference, clearly labelled — is that a single hyperscaler wanting low-latency links between five Indian metros, buying through CtrlS rather than building itself, is most likely one of the three or four global cloud platforms with an established Indian presence. Gridvik does not guess which one.

What a supplier should take from this

The relevant opportunity is not the data centres. It is the fibre. Five metro networks require ducts, cable, optical equipment, regeneration sites, and power and cooling in small roadside or in-building enclosures across five cities.

That last category is systematically ignored by the data centre supply chain and it is a real, repeating order.

7Timeline

  • Ciena announces that CtrlS is building five metro optical networks connecting nine existing data centres across Chennai, Hyderabad, Kolkata, New Delhi and Noida, for up to 100 Tb/s, as part of a managed optical fibre network deployment for an unnamed hyperscaler.
  • Indian and international trade coverage repeats the figures. No coverage adds a contract value, a schedule or a customer name
  • No completion date, contract value, customer identity or per-metro capacity has been published. The nine buildings are not individually identified

8Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
This record
Optical transport and metro fibre across nine existing buildings. No new building, no new megawatt
Already decided
Ciena supplies the optical platform and the line system, and project-manages the deployment. That part of the scope is closed
What remains open
Ducts, fibre cable, civil works for routes and regeneration points, in-building enclosures, small power and cooling systems at each node
The deliberately unglamorous opportunity
Metro fibre means street furniture: cabinets, enclosures, small UPS systems, cooling for roadside nodes. It is ordered continuously and rarely appears in data centre market reports
Who buys
CtrlS, or its fibre contractor. Ciena’s services arm is project-managing
Not a data centre sale
No chillers, no busway, no generators for a hall. The scale is entirely different
Order window
During the deployment, which has no published end date
Procurement heat
Active but small-ticket, and it is a fibre supply chain rather than a facilities one
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

Rows with a lock are the paid layer.

9Assumptions and method

What is sourced
The network count, the nine data centres, the five cities, the 100 Tb/s capacity, the equipment, the services scope, the hyperscaler’s existence and anonymity, the absence of a value and schedule, CtrlS’s operating metrics, and Ciena’s quarterly revenue composition
What is derived
The wavelength count, the per-metro and per-building averages, the byte conversion, and the assessment of the business model
Capacity figure used
None. Throughput is not converted to capacity and this record is non-additive
Additivity rule
Not applicable. Cannot be summed with any facility record under any circumstance
The nine data centres
Existing buildings. Gridvik does not create nine new facility records from this announcement
Currency
₹88.40 to the US dollar, fixed quarterly. No rupee figure is disclosed in this record

10Limits and open questions

The central gap
The customer is unnamed and the value is undisclosed. Both make the commercial significance impossible to size
Schedule
No completion date and no statement about whether the five networks are concurrent
The nine buildings
Not individually identified. Which CtrlS facilities carry the optical equipment is not published
Mumbai
India’s largest data centre market is absent from the five cities. The reason is not given and Gridvik does not assume one
Whether this is new fibre or existing fibre
The release describes "managed optical fiber networks" without stating how much of the route is newly laid
Multi-year service or one-off build
Not specified, and the two have very different revenue profiles
What we will not claim
No customer name, no contract value, no completion date, no megawatt, and no assertion that this creates new data centre capacity

11Sources

This record was compiled entirely from publicly available sources, cross-checked against one another.

Ciena press release·Economic Times·Economic Times Datacenters·The Hindu BusinessLine·CXO Digitalpulse·Converge Digest·Telecom TV·Construction World·Yahoo Finance·CIO and Leader·The420

Gridvik does not publish source URLs on record pages; citations are retained in the internal source register and are available on request.

What this page is, and what it is not

A connectivity record. It carries no data centre capacity, by design and by rule.

Corrections are free and published with a date.