Tenant deployment record · Verified 26 Oct 2026

CoreWeave at AdaniConneX Taloja — Navi MumbaiAdaniConneX host campus · CoreWeave sole tenant · 240 MW across three 80 MW buildings

Record PRJ-056Maharashtra — Taloja, Navi Mumbai regionTier B — tenant signed, not built12 public sources cross-checkedAdditive: no
Named tenantNot builtTenant deploymentNo capital figure
240MW
Sole-tenant reservation
3 × 80MW
Buildings
480MW
With option — not signed
Mid-2028
First phase target
5.7%
Of CoreWeave contracted power
—
Capital disclosed

On 6 October 2026 CoreWeave entered India as the sole tenant of three 80 MW buildings at AdaniConneX’s Taloja campus near Navi Mumbai: 240 MW, an option to double to 480 MW, NVIDIA Vera Rubin on the CoreWeave platform, direct liquid cooling in the GPU halls, a non-evaporative chilled-water system, and a first phase expected in mid-2028. It is the most concrete AI commitment in this registry — a named tenant, a named host, a named silicon platform and a date. It is also the record most likely to be double-counted, because 240 MW here is capacity already inside AdaniConneX’s 1 GW platform, newly occupied, not newly built.

1At a glance

Host
AdaniConneX, a 50:50 joint venture between Adani Enterprises and EdgeConneX. The Taloja campus is in the Navi Mumbai region
Tenant
CoreWeave, Inc. (Nasdaq: CRWV), sole tenant across all three buildings. Not a partial lease, not a joint venture
Declared capacity
240 MW across three 80 MW buildings. The basis — IT load or gross facility load — is not stated
Expansion option
Up to a further 240 MW at the same campus, taking a potential 480 MW. An option, not a signed phase, and not in any registry total
Capital
Not disclosed. Bloomberg describes the investment as several billion dollars over the life of the project. No rupee or dollar commitment has been published by either party
Compute
NVIDIA Vera Rubin platform deployed on the CoreWeave AI cloud, for training, inference, reasoning and agentic workloads
Cooling
Direct liquid cooling in the GPU halls and a non-evaporative chilled-water system designed for high-density AI workloads
Schedule
First phase mid-2028, with additional capacity phased thereafter. No building-by-building activation schedule and no capacity stated for the first phase
Announcement date
Release dated 6 October 2026. Business Wire syndication and most coverage is stamped 7 October
Additivity
No. This is tenant deployment inside AdaniConneX capacity that is already counted. Adding 240 MW to AdaniConneX’s platform would double-count it

2The tenant, not the campus

This registry holds AdaniConneX’s 1 GW India platform, its 1 GW Maharashtra MoU and the Prestige Taloja campus as separate records. This is a fourth, different kind of record: a customer.

CoreWeave base reservationthree 80 MW buildings240 MWWith the expansion optionnot signed, not scheduled480 MWAdaniConneX India platformthe ceiling this sits inside1,000 MWThe base 240 MW does not add to the platform total. It is a named tenant inside capacity already counted.
Figure 1The 240 MW reservation against the platform it sits inside. The middle bar is an option, not a signed commitment — 480 MW is arithmetic on a sentence, not a phase.

The distinction matters for two reasons that a supplier will feel directly.

First, it changes who specifies. When a campus is being built on spec, the developer chooses the cooling architecture and the vendor list. When a single tenant takes three whole buildings and runs a GPU cloud, the tenant’s reference design wins — and CoreWeave’s reference design is direct liquid cooling with high-density racks, not the conventional air-cooled halls that make up most Indian capacity.

Second, it changes the procurement language. The three buildings are being designed for high-density AI from the start. That means coolant distribution units, manifolds, rear-door or cold-plate systems, high-amperage busway, and substantially more power per square metre than the campus buildings that were commissioned in 2023 and 2024. A vendor with Indian references for air-cooled colo is not automatically an acceptable bidder here.

What this record actually is

It is a named, creditworthy tenant committing to a specific megawatt figure at a specific campus with a specific silicon platform and a stated target year — the rarest thing in this registry.

It is not new capacity. Nothing is built. And the money behind it has not been published by any party.

3Three buildings of exactly 80 MW

Three buildings at 80 MW each is a clean, round, satisfying structure, and that is the first reason to look at it closely. Indian data-centre buildings are commonly sized at 20, 30, 40 or occasionally 60 MW per building. Eighty megawatts in a single building is at the upper end of what has been built anywhere in the country, and doing it three times at once, on one campus, for one tenant, is a materially harder engineering problem than three separate developers would face.

What an 80 MW building implies
ParameterAt 80 MW a buildingWhy it matters
Typical AI rack density100 to 160 kW per rack7 to 15 times a conventional Indian colo rack at 5 to 10 kW
Rack count at that densityabout 500 to 800 per buildingsmaller halls, heavier floor loading, much denser cabling
Coolingliquid, not airair cannot move 130 kW out of a cabinet reliably at Indian ambient conditions
Power deliveryMV distribution inside the hallbusway and PDUs at a scale that changes the switchgear specification
Waternon-evaporative designno evaporative loss, so the heat rejection is dry or closed-loop — larger plant, more electrical load
Connection80 to 96 MVA a building240 to 288 MVA for the campus: a transmission-level connection, not a distribution one

The two engineering details in the release are the most informative sentences in the whole announcement, and they are easy to read past: direct liquid cooling and a non-evaporative chilled-water system. That combination says the developer has accepted a higher electrical overhead for heat rejection in exchange for zero evaporative water loss — a choice that is expensive and near-certainly driven by the water situation in the Taloja corridor.

It also tells you what will not be bought. No large evaporative cooling towers. No air-cooled CRAC fleet at scale. The bill of materials for these three buildings is not the bill of materials of the last ten Indian campuses.

4What 240 MW is in racks

Neither company has published a rack count, a GPU count or a per-rack power figure. Megawatts alone do not let a vendor size a package, so the arithmetic below is offered as a range with its assumption stated — not as a specification.

Rack count implied at three densities
Rack densityRacks at 240 MWComment
100 kW per rack2,400 racksconservative for a Vera Rubin generation hall
130 kW per rackabout 1,846 racksthe middle of the range used above
160 kW per rack1,500 rackshigh density, liquid cooled throughout

Even the bottom of that range is a hall count that would place this deployment among the densest AI facilities in Asia. It is 4 to 10 times the rack count of a conventional 240 MW colocation campus, which is the entire point of an AI cloud and the entire reason the cooling specification had to change.

Gridvik does not publish a GPU count. The platform has been named, the workloads have been described, and the number of accelerators that fit in 240 MW has not been stated by anyone. Any figure circulating with a GPU count attached has been invented by whoever circulated it.

5The number that is missing

Every other large record in this registry has a rupee figure and no megawatt, and we say so. This one is the reverse: 240 MW and no capital figure. Neither CoreWeave nor AdaniConneX has published one. Bloomberg’s "several billion dollars over the project’s lifetime" is the closest thing to a number and it is journalism, not a commitment.

What the capital would plausibly be, and why Gridvik will not record it
BasisImplied capital for 240 MWPosition
$8 million per MW — shell, power and basic fit-outabout $1.9 billionthe floor for a building of this class
$12 million per MW — AI-ready with liquid cooling and dense powerabout $2.9 billionmore consistent with the specification described
Including the compute inside itnot estimable from public dataVera Rubin pricing and CoreWeave’s purchase terms are not disclosed

The floor is useful and the ceiling is not, because the difference between a building and a building with GPUs inside it is a multiple, not a percentage. Note also who is paying for what. AdaniConneX builds and owns the campus; CoreWeave occupies it and pays rent over a long lease. The capital figures above are the developer’s problem, and the tenant’s commitment is a lease obligation whose value has not been published either.

The double-count this record invites

240 MW at Taloja, added to AdaniConneX’s 1 GW platform, plus the 1 GW Maharashtra MoU, plus Prestige’s Taloja campus, quickly becomes a number larger than Maharashtra can physically energise.

Gridvik records this as a tenant reservation and adds nothing. The megawatts are already inside a counted platform.

6CoreWeave’s position at signature

Whether a 2028 target is credible depends mostly on the tenant’s balance sheet, and that part of the record is public because CoreWeave is listed.

CoreWeave against its own announcement
MeasureValueReading
Active power at Q2 2026about 1.5 GWthe base the business actually runs on
Contracted power at 11 August 2026about 4.2 GWsigned capacity not yet active
240 MW as a share of contracted power5.7%India is a material but not dominant commitment
480 MW, with the option exercised11.4%the option is the part that would make India core
First India phasemid-2028roughly 20 months after signing
Platform namedNVIDIA Vera Rubina generation beyond what is installed in most Indian capacity today

Two readings follow, and both are true.

The bullish one: a company with 4.2 GW of contracted power, a listed currency for raising capital and a single-tenant model that fills whole buildings is exactly the customer a host developer wants, and India gets 5.7% of its pipeline as a first entry. That is a serious commitment from a serious counterparty.

The cautious one: mid-2028 is twenty months away, the first phase capacity is unstated, and the buildings do not exist. Between signing and energising, a company that has grown this fast has to do a great deal of financing and construction in several countries at once. The option for a further 240 MW is not a phase; it is a right that expires or converts on terms nobody has published.

Also worth stating plainly, because the release does: CoreWeave will open an India office and hire locally, and the collaboration references the government’s IndiaAI Mission with no subsidy figure attached. Any incentive this project eventually receives has not been disclosed.

7Timeline

  • CoreWeave releases its India entry: 240 MW at AdaniConneX’s Taloja campus, three 80 MW buildings, sole tenant, NVIDIA Vera Rubin, direct liquid cooling, first phase mid-2028, option for a further 240 MW. No capital figure
  • Business Wire syndication and international coverage, including Bloomberg and DCD, repeat the deployment and describe the investment as several billion dollars over the project life
  • Trade coverage adds the engineering detail: direct liquid cooling in the GPU halls and a non-evaporative chilled-water system. Inc42 and others describe a potential 480 MW footprint
  • No construction start, building schedule, capital figure or first-phase capacity has been published. No land, power or environmental approval for the three buildings is in the public domain

8Procurement

Procurement window and scope
Gridvik assessment · 26 Oct 2026
What will be bought
Coolant distribution units and manifolds, cold plates or rear-door heat exchangers, high-ampacity busway, medium-voltage switchgear, dry coolers or closed-loop heat rejection, high-density PDUs, leak detection, BMS and DCIM, fire suppression for lithium-bearing halls
What will not be bought
Large evaporative cooling towers and a conventional air-cooled CRAC fleet. The non-evaporative design is stated, which removes the default Indian cooling package from the bill
Who decides
CoreWeave’s reference design governs the halls; AdaniConneX governs the campus shell, power and heat rejection. Two different buyer conversations with two different reference lists
Likely window
Equipment orders for a mid-2028 first phase would logically fall in 2027. Nothing has been published, and no phase capacity is stated, so this is derived, not reported
Decision stage
Design. Buildings specified, not started
Quality of evidence
High on the commercial structure — a listed company’s own release with a named counterparty, a platform and a date. Low on engineering and capital
Our confidence
High on 240 MW, tenant and mid-2028. Nil on capital, rack density, GPU count and first-phase capacity
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

9Assumptions and method

Every figure and where it comes from
FigureBasisConfidence
240 MWCoreWeave release, 6 October 2026. Sole tenant across three 80 MW buildings. IT versus facility basis not statedHigh as a claim
480 MWThe stated option to expand by up to a further 240 MW. Not a signed phaseHigh as an option, zero as a commitment
Mid-2028Company target for the first phase. First-phase capacity is not statedStatement only
5.7% and 11.4%Gridvik arithmetic against CoreWeave’s roughly 4.2 GW of contracted power at 11 August 2026Arithmetic
1,500 to 2,400 racksGridvik arithmetic at 100, 130 and 160 kW per rackArithmetic with stated assumptions
80 to 96 MVA a buildingGridvik arithmetic at 1.0 to 1.2 times IT loadEstimate
$1.9 to $2.9 billionGridvik arithmetic at $8 to $12 million per MW, excluding computeEstimate, not recorded
Additivity: noThe 240 MW sits inside AdaniConneX capacity already in the registryRecorded as a rule

10Limits and open questions

What Gridvik will not do
We will not add 240 MW to AdaniConneX’s platform or to any state total, and we will not publish a GPU count. The option is excluded from every figure
First question
What does the first phase deliver in megawatts? A mid-2028 date with no phase size is a start, not a schedule
Second question
What is the capital, and who funds it? A campus of this specification is a multi-billion-dollar asset and no figure has been published by either party
Third question
What is the lease term and value? CoreWeave’s obligation is the security behind the whole development, and it is undisclosed
Fourth question
Water. A non-evaporative design is the right answer for the corridor and it costs more power and more plant. Whether the connection can carry that overhead is unstated
Why this record matters
It is the clearest signal yet that Indian capacity is being built to AI specifications rather than upgraded to them. That changes the equipment list for every supplier in the chain
What changes the tier
A construction start, a named EPC contractor, a first-phase capacity, or a capital figure. Any of those moves this to Tier A

11Sources

Sources: CoreWeave investor release, CoreWeave newsroom, Business Wire, Bloomberg, Data Center Dynamics, ETDatacenters, Inc42, Data Centre Magazine, Converge Digest, The Next Web, TradingView, FourWeekMBA, FinanceFeeds.