Under construction · Verified 26 Oct 2026

STT GDC — Palava, Mumbai Metropolitan RegionSTT GDC India · Lodha Industrial Park, Palava · 50 MW first phase, ~400 MW design

Record PRJ-061Maharashtra — Palava, between Thane and Navi MumbaiTier A — under construction13 public sources cross-checkedAdditive: no
Under construction50 MW of 400 MWCampus aggregateSite area disputed
50MW
First phase, building
400MW
Campus design IT load
46ac
Site, per March 2026
₹12.5cr
Per MW if ₹5,000 cr were Palava
Mar 2026
Ground broken
—
Ready-for-service date

On 16 March 2026 STT GDC India broke ground on the first data centre at its Palava campus inside Lodha Industrial Park, between Thane and Navi Mumbai: a 50 MW first phase within a campus designed to scale to about 400 MW of IT load on 46 acres. It is the third STT campus in the Mumbai region and the first that was designed for AI and high-density computing from the outset. The number most often attached to it — a ₹5,000 crore investment — is not the campus cost. Divide it by 400 MW and you get ₹12.5 crore a megawatt, roughly a fifth of what Indian data centre capacity actually costs to build. The commitment covers STT’s Mumbai and Pune expansion too, and no Palava-specific capital figure has been published.

1At a glance

Operator
STT GDC India, part of ST Telemedia Global Data Centres. The India business reports more than 400 MW of critical IT load in operation and development across 30 facilities in 10 cities
Site
Palava City, between Thane and Navi Mumbai, inside Lodha Industrial Park. Lodha is the master developer, not a joint-venture partner in the campus
Phase 1
50 MW of IT load, ground broken 16 March 2026. Under construction
Campus design
About 400 MW of IT load at full build. The 50 MW phase is nested inside the 400 MW, not additional to it
Site area
46 acres per March 2026 coverage, against 27 acres in the October 2025 MoU coverage. The difference is unreconciled
Density
400 MW on 46 acres is about 8.7 MW an acre, which implies multi-storey halls rather than a single-storey layout
Investment
A ₹5,000 crore commitment under a Maharashtra MoU signed in October 2025, covering STT’s Mumbai and Pune expansion as well as Palava. No Palava-specific figure exists
Per megawatt
₹12.5 crore if the ₹5,000 crore were all Palava’s — which it cannot be. At observed build rates the campus needs ₹20,800 to ₹28,000 crore
Schedule
No ready-for-service date has been disclosed for the first phase
Ownership change
In September 2026 a KKR-led consortium with Singtel completed the acquisition of an 82% stake in STT GDC for $5.2 billion
Additivity
No. Retained as a non-additive record: the 400 MW and the ₹5,000 crore are not summed with the STT multi-state MoU umbrella

2The ₹5,000 crore that is not Palava’s

This is the single most misread number in the Mumbai market, and the arithmetic shows why in one line.

₹5,000 crore against 400 MW
TestResultReading
₹5,000 crore ÷ 400 MW₹12.5 crorea fifth of the cheapest rate at which capacity in this registry was built
What 400 MW costs at ₹52 crore a megawatt₹20,800 crorethe low end of observed build cost
What 400 MW costs at ₹70 crore a megawatt₹28,000 crorethe top end
What ₹5,000 crore buys at ₹52 to ₹70 crore a megawatt71 to 96 MWroughly the first phase plus land and infrastructure
Conclusionthe ₹5,000 crore covers the first phase and the state-wide expansion, not the campusno Palava-only capital figure has been published

There are two more reasons the rupee figure cannot be the campus. First, the MoU is explicitly for up to ₹5,000 crore to expand the existing Mumbai and Pune parks as well as build Palava. Second, in the same period the underlying land was bought separately: reports put an initial parcel at around $56 million, and Lodha has been selling plots inside its park to multiple operators.

None of this is a criticism of STT. It is a criticism of how the number is being repeated — including in investment notes and in at least one industry ranking. A ₹12.5 crore a megawatt data centre is not cheap capacity; it is a phase-one commitment being compared against whole-campus numbers.

Hold this number loosely

Every Indian campus announcement in this registry has the same defect: the money is for phase one and the capacity is for the campus. Palava is the cleanest example because the arithmetic fails by a factor of four.

When comparing projects, compare who has broken ground and how many megawatts are actually funded. On that basis Palava has 50 MW of committed capacity and 400 MW of design.

350 MW now, 400 MW designed

The distinction between design and phase is the whole difference between a campus that will exist and one that might.

What is real and what is a design ceiling
ItemStatus
50 MW first phaseGround broken 16 March 2026. Under construction
400 MW campusDesign intent. Requires seven further phases of roughly 50 MW, each needing its own capital, approval and tenant
46 acresSite area as reported in March 2026. Sufficient for 400 MW only at multi-storey densities
Purpose-built for AIThe October 2025 MoU describes the campus as purpose-built for AI and high-density computing. No rack density, cooling design or GPU tenant has been published
Ready-for-serviceNot disclosed
TenantsNone named
PowerNo connection agreement, sanction or capacity charge disclosed

The pacing detail is worth noting. STT has more than 400 MW of critical IT load across 30 facilities in operation and development nationwide. A single 400 MW campus in Palava would therefore be roughly equal to the entire rest of the Indian portfolio, which tells you the 400 MW is a decade-long ceiling rather than a near-term pipeline.

Palava’s practical significance in the near term is the 50 MW. That is a real building, on real land, with a real groundbreaking, and it is more than most of the records in this registry will deliver before 2029.

4Palava is becoming a cluster

The campus matters less than its address. Palava, and the Ambernath–Palava corridor more broadly, is assembling into the densest concentration of announced data centre capacity in India, and that has consequences no single record shows.

STT GDC Palavaground broken March 2026400 MWDigital Edge Palavaland bought, project unconfirmed270 MWAmazon Ambernathnearby, separate project473 MWLodha power shellsbuild-to-suit on about 100 acres1,000 MWThese may not add. Lodha’s 1 GW of power shells is built for others to occupy and may contain the STT and Digital Edge capacity. The safe range for the corridor is 1,000 to 2,143 MW.
Figure 1Four announcements in the same corridor. They may not add: Lodha’s power shells are built for other operators to occupy and could contain the STT and Digital Edge capacity. The defensible range is 1,000 to 2,143 MW.
The corridor, project by project
ProjectCapacityStatus
STT GDC Palava400 MW design, 50 MW buildingground broken March 2026
Digital Edge Palava270 MW reportedabout 30 acres bought from Lodha; Lodha confirmed the transaction, not the project
Amazon Ambernath473 MW reportedseparate project in the same corridor
Lodha power shells1,000 MW build-to-suit on about 100 acresLodha’s own programme inside its 400-acre park, with 3 GW of power claimed
Lodha park land bank400 acres, 2.5 to 3 GW of power claimedthe master plan that everything above sits inside

That concentration is good for the corridor and bad for everything else in Maharashtra. Power, water and skilled labour are finite in a corridor. A 3 GW claim on an area between Thane and Navi Mumbai is a claim on transmission capacity that ultimately comes from the same state grid that every other campus in the registry is also drawing from.

For suppliers the message is useful and unambiguous: this is where to be. A single service engineer based in the corridor can cover 2 GW of installed capacity within an hour’s drive. That economics does not exist in Chennai, Hyderabad or Noida, where capacity is spread across a wider area.

5New owner: KKR and Singtel

The ownership of the counterparty changed four months after ground was broken, which matters for anyone with a purchase order in the pipeline.

The transaction
ItemDetail
Announced and completedSeptember 2026
BuyerA KKR-led consortium with Singtel
AssetAn 82% stake in STT GDC
Value$5.2 billion
SplitKKR about 75%, Singtel about 25% of the acquiring consortium
What it means for PalavaA well-capitalised owner with a stated infrastructure thesis. Financial sponsors of this kind fund build-outs on schedule when the returns are contracted
What it means for procurementExpect standardisation across the portfolio. A new sponsor typically reviews capital programmes, vendor panels and specification standards, and often consolidates both
What is unchangedThe 400 MW design, the 50 MW phase, the site and the absence of a ready-for-service date

The strategic read is that a $5.2 billion valuation for 82% of STT GDC implies roughly a $6.3 billion enterprise-level equity value for a business with 400-plus megawatts in operation and development across ten Indian cities. That is the clearest price the market has put on Indian data centre capacity in this cycle, and it is a useful benchmark for every other record in this registry that claims to be worth something.

Singtel retaining a quarter of the acquiring vehicle also tells you something about the seller’s view: this is not an exit, it is a capital injection into a business the sponsor expects to grow.

6Timeline

  • STT GDC India signs a Maharashtra MoU for up to ₹5,000 crore of additional investment across its Mumbai and Pune parks, including a new large-scale campus at Palava described as spanning over 27 acres and purpose-built for AI and high-density computing
  • Ground broken on the first data centre at the Palava campus: 50 MW of IT load within a campus designed to scale to about 400 MW, now described as spread across 46 acres inside Lodha Industrial Park
  • DCD, W.Media and The Tech Capital report the groundbreaking. No ready-for-service date is disclosed
  • Digital Edge is reported to have bought about 30 acres in Palava from Lodha for a 270 MW project. Lodha confirms the land transaction only
  • A KKR-led consortium with Singtel completes the acquisition of an 82% stake in STT GDC for $5.2 billion
  • Construction status last publicly confirmed in March 2026. No phase completion, tenant, power sanction or ready-for-service date has been published

7Procurement

Procurement window and scope
Gridvik assessment · 26 Oct 2026
What is being bought
For a 50 MW AI-ready first phase: HV and MV distribution, transformers, chillers with a high-density heat rejection strategy, CDUs and liquid cooling provision, BMS and EPMS, fire suppression, plus 46 acres of campus infrastructure built for seven further phases
Why the AI framing matters
The campus is described as purpose-built for AI and high-density computing. That implies provision for liquid cooling and higher rack power, which changes the electrical and cooling specification from a conventional Indian colo build
Repeatability
A 400 MW design delivered in roughly 50 MW phases is a repeatable equipment package. Vendors who can supply the same skid several times over several years have a structural advantage
Likely window
First phase under construction since March 2026. Equipment for a 50 MW phase is largely ordered already. The phase two window is the live opportunity, and no date for it has been published
Decision stage
Building. Phase one under construction
Who to approach
STT GDC India, now majority-owned by a KKR-led consortium. Expect a professional, centrally specified procurement process and a sponsor with strong governance on capital spend
Quality of evidence
High on the milestone and the site, from the operator’s own post. Low on capital, tenants, power and schedule
Our confidence
High on 50 MW under construction and 400 MW design. Nil on the ready-for-service date
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

8Assumptions and method

Every figure and where it comes from
FigureBasisConfidence
50 MW first phaseSTT GDC India announcement of 16 March 2026, repeated by DCD, W.Media and The Tech CapitalHigh
400 MW campus designSame announcement. A design ceiling, not a funded programmeHigh as design
46 acresMarch 2026 coverage and the operator’s own post. October 2025 coverage said 27 acresHigh, with a noted conflict
₹5,000 croreMaharashtra MoU of October 2025, covering Mumbai and Pune expansion as well as PalavaHigh as a commitment, not as Palava capex
₹12.5 crore per MWGridvik arithmetic: ₹5,000 crore ÷ 400 MW. Shown to demonstrate that the figure is not Palava’s capexArithmetic, and explicitly rejected as a cost
₹20,800 to ₹28,000 croreGridvik arithmetic at ₹52 and ₹70 crore per MW for 400 MWArithmetic
8.7 MW an acreGridvik arithmetic: 400 MW ÷ 46 acresArithmetic
$5.2 billion, 82%Reported KKR and Singtel transaction, September 2026Medium — from trade coverage, not a filing
270 MW Digital EdgeReported. The project has not been confirmed by the developerLow
Not additiveThe 400 MW sits inside the STT multi-state umbrella recordRecorded as a rule

9Limits and open questions

What Gridvik will not do
We will not use ₹12.5 crore a megawatt as a cost, name a tenant, publish a ready-for-service date, or add the 400 MW to any total alongside the STT umbrella record
First question
When does the 50 MW phase energise? No date has been published, and it is the only figure in this record that is actually being built
Second question
Who is the tenant? An AI-focused 50 MW phase with liquid cooling provision needs an anchor customer. None has been named in fourteen months
Third question
Where does 400 MW of power come from in the Palava corridor? Lodha claims 3 GW of park capacity and multiple operators are buying into the same area. The connection reality has not been published by anyone
Fourth question
Is the campus 27 acres or 46? The site doubled between October 2025 and March 2026 and nobody explained it
Why this record matters
It is one of the few large campuses in the registry actually under construction, it sits in the corridor that is becoming India’s densest data centre cluster, and it is now owned by a sponsor that publishes nothing except results
What changes the tier
A ready-for-service date, a named tenant, a phase-two award, or a Palava-specific capital figure

10Sources

Sources: STT GDC India announcement and LinkedIn post of 16 March 2026, Data Center Dynamics, W.Media, The Tech Capital, Baxtel, Lodha Group, Business Standard, Moneycontrol, Blackridge Research, Financial Express, Digital Edge reporting via W.Media, KKR and Singtel transaction coverage.