Under construction · Verified 26 Oct 2026

PDG MU2 — Navi Mumbai, MaharashtraPrinceton Digital Group · Navi Mumbai, Airoli–Ghansoli corridor · 120 MW under construction

Record PRJ-062Maharashtra — Navi MumbaiTier A — under construction12 public sources cross-checkedAdditive: no
Under constructionNo delivery dateCampusChild of a 210 MW acquisition
120MW
Critical IT capacity
18,880m²
Colocation area
6.4kW/m²
Density — 4–6× normal
10ac
Site
5
Storeys
Apr 2026
Construction start

Princeton Digital Group began construction on MU2 in Navi Mumbai in April 2026: a single five-storey building on 10 acres carrying 120 MW of critical IT capacity across 18,880 square metres of colocation space. That last pair of numbers is the most useful thing on this page. One hundred and twenty megawatts in 18,880 square metres is 6.4 kilowatts per square metre, four to six times what conventional Indian colocation delivers — and it is a measurable definition of what the industry means when it says AI-ready. No delivery date has been published. The 120 MW is part of PDG’s 210 MW March 2026 Mumbai and Hyderabad acquisition and is not additive to it.

1At a glance

Operator
Princeton Digital Group, Singapore-headquartered, founded 2017, operating across Singapore, Japan, India, Indonesia, China, Malaysia and South Korea. Backers include Warburg Pincus as largest shareholder, Ontario Teachers’, Mubadala and Stonepeak
Site
Navi Mumbai, in the Airoli–Ghansoli corridor. 10 acres. The exact parcel is not public
Capacity
120 MW of critical IT capacity, stated as IT load. A single five-storey building
Colocation area
18,880 square metres, about 203,220 square feet
Density
6.4 kW per square metre. Gridvik arithmetic from the two figures above, and the highest in this registry for a multi-tenant building
Land
Acquired March 2026, one of two sites in a multi-site acquisition that added 210 MW across Mumbai and Hyderabad
Construction
Commenced April 2026, following a groundbreaking ceremony whose exact date was not disclosed
Delivery
Not published. Third-party trackers place the site in 2027 with later expansions, which is not a company statement
Investment
No project-level capex disclosed. The site sits inside PDG’s India commitment of about $2.5 billion
Parent relationship
Part of a 210 MW acquisition. A reasonable reconciliation is MU2 at 120 MW plus Hyderabad HY1 at 90 MW, but the acquisition release does not allocate it
Additivity
No. Do not add 120 MW to the 210 MW parent, or to PDG’s 1 GW India portfolio claim

26.4 kilowatts a square metre

Every operator in this registry says its new capacity is AI-ready. Very few publish the two numbers that let you check: megawatts and square metres. PDG has published both.

The density test, and what it implies
MeasureValueBasis
Critical IT capacity120 MWcompany and trade coverage
Colocation area18,880 m²company site
Power per square metre6.4 kW/m²120,000 kW ÷ 18,880 m²
Power per square footabout 590 Wfor readers who work in feet
Conventional Indian colocation1.0 to 1.5 kW/m²5 to 10 kW racks at standard aisle widths
This building against that4 to 6 timesthe entire difference between air-cooled colo and an AI hall
Implied rack density at 5 m² a rackabout 30 kWa conservative mid-point for liquid-cooled halls
Implied rack density at 2.5 m² a rackabout 16 kWdense layout, air-assisted

That gives suppliers something the press release does not. A 6.4 kW/m² building cannot be cooled with conventional perimeter CRAC units and cannot be powered through a conventional floor grid. It needs in-row or rear-door cooling at minimum and liquid distribution if the racks go above roughly 30 kW. The floor loading, the cable containment and the fire suppression are all different.

It also explains the building form. Five storeys on 10 acres is the only way to fit 120 MW in that footprint: 24 MW a floor, about 3,776 square metres a floor, which is a big floorplate by Indian standards but not unusual for a hyperscale shell. A single-storey 120 MW building would need several times the land.

The number worth stealing

When an Indian operator says AI-ready, ask for megawatts and square metres. Divide one by the other. Under 2 kW a square metre is conventional colocation with better marketing; above 5 is a genuinely different building.

PDG MU2 is the only record in this registry that lets you run that test.

3MU2 inside a 1 GW platform

The 120 MW is a site. It is also a line inside two larger numbers, and neither is additive to it.

MU1 Navi Mumbailive 50 MW, expanding to 150150 MWMU2 Navi Mumbai120 MW, under construction120 MWHY1 Hyderabadplanned, three buildings90 MWCH1 Chennaiplanned, three buildings72 MWUnnamed balanceto reach the stated 1 GW568 MWNamed sites sum to 432 MW. The company describes its Indian operating and planned portfolio as about 1 GW, and has not said where the remaining 568 MW sits.
Figure 1The named sites and the gap to the company’s stated 1 GW Indian portfolio. The balance of 568 MW has not been located, named or allocated anywhere in the public record.
The three numbers around MU2
NumberWhat it isRelationship to MU2
120 MWMU2 as a sitethe record
210 MWMarch 2026 acquisition across Mumbai and HyderabadMU2 is 120 of it. Do not add
about 1 GWPDG’s India operating and planned portfolio after the acquisitionMU2 is 12% of it. Do not add

The arithmetic inside the 1 GW claim is worth keeping visible. MU1 at Navi Mumbai is 150 MW once its expansion completes, MU2 is 120, Hyderabad HY1 is 90 and Chennai CH1 is 72. That is 432 MW of named capacity. The remaining 568 MW is not attached to any announced site, which is normal for a platform that intends to buy more land and equally a reason not to treat 1 GW as a pipeline.

For a supplier, the useful reading is that PDG has a genuinely repeatable design. MU1 is a 50-acre park in Airoli with a five-building plan. MU2 is a single five-storey building on 10 acres. Chennai CH1 is three buildings, Hyderabad HY1 is three buildings. Four sites, all multi-building, all in the same corridor logic, all with the same operator and the same specifiers.

4What is missing: a date

This is the one important gap. Construction started in April 2026 and no ready-for-service date has been published by the company.

Land01Groundbreaking02Construction03Fit-out04Tenant05Live06Navy = verified · Red = current stage · Grey = not yet evidenced

Three stages are evidenced. The three that decide revenue are not. Third-party trackers list the site as planned for 2027 with expansions through 2029, and that is their inference rather than a company commitment.

What can be said with confidence is the shape of the programme: a five-storey shell in a live data centre corridor, on land acquired and approved before construction, with power reportedly secured. Those are the two constraints that usually delay Indian data centres, and both appear to have been dealt with. That makes a 2027 energisation plausible without being promised.

The tenant question is open in a different way. PDG is carrier-neutral and builds for hyperscalers; the 120 MW MU2 building has not been pre-let to anyone publicly. A single 120 MW building is the size of one hyperscaler’s regional footprint, and it is unlikely to be built without a named anchor. Nobody has named one.

5Power, and the time-matched green claim

This record contains something almost no other Indian data centre does: a time-matched clean energy arrangement rather than an annual certificate purchase.

What PDG has said about power
ItemPosition
Power statusThe March 2026 acquisition release states power is secured and key land approvals are in place
Renewable arrangementA 25-year power consumption agreement with Tata Power Renewable Energy for solar generated in Nanded district, Maharashtra
Matching basisA partnership with Flexidao to implement time-matched carbon-free energy at the Mumbai campus
Why time-matching mattersAnnual matching can be satisfied by buying certificates generated at noon for a load that runs at midnight. Hourly matching means the electrons line up with the load. It is materially harder and materially more expensive
What is not disclosedVolume, tariff, capacity of the solar project, storage, open-access approval, and how much of MU2’s 120 MW the arrangement covers

In this registry, "51% green" appears in at least four separate announcements with no generation, no PPA and no matching basis attached. PDG has named a generator, a district and a matching methodology. That still is not a contract for 120 MW — no volume has been published — but it is a different class of claim.

The honest caution is that a 25-year power consumption agreement with a solar generator cannot cover 120 MW around the clock without storage or a balancing arrangement. Time-matched supply for a flat data centre load needs either storage, a portfolio of technologies, or grid supply that is clean at the hour it is consumed. None of those details are public.

6Timeline

  • PDG raises more than $1.2 billion in financing, including $800 million of project financing for AI-ready campuses in Mumbai and two other geographies
  • PDG announces a multi-site India acquisition adding 210 MW across Mumbai and Hyderabad, taking its Indian operating and planned capacity to about 1 GW and its total India commitment to about $2.5 billion. Land for MU2 acquired
  • Groundbreaking ceremony for MU2. Exact date not disclosed
  • Construction confirmed as commenced. DCD reports 120 MW, 10 acres, five storeys and 18,880 sqm of colocation space
  • W.Media and other trade coverage describes MU2 as part of PDG’s expansion toward a 1 GW India portfolio
  • No ready-for-service date, no tenant, no project capex and no power volume published. Construction status last confirmed in April 2026

7Procurement

Procurement window and scope
Gridvik assessment · 26 Oct 2026
What is being bought
A five-storey hyperscale shell with 120 MW of IT capacity: HV and MV distribution, transformers, chillers, in-row or liquid cooling provision for 6.4 kW/m² halls, busway, BMS and EPMS, fire suppression, and a campus-wide security and monitoring layer
The specification signal
18,880 sqm for 120 MW rules out conventional air cooling. Expect liquid-cooling-ready halls and a cooling plant sized for dense heat rejection
Repeatability
PDG is building the same product in Navi Mumbai, Hyderabad and Chennai. A vendor that wins one specification can plausibly supply four sites
Likely window
Construction began in April 2026. Structural and shell works would dominate 2026 and 2027, with electrical and cooling packages in 2027 for a plausible 2027–28 energisation. Nothing has been published
Decision stage
Building. Shell under construction
Who to approach
PDG India, a professional Singapore-headquartered developer with a central engineering function and institutional shareholders. Vendor panels will be set at group level
Quality of evidence
Good. A company site with specifications, trade coverage of the construction start, and a parent acquisition release. Weak on dates, cost and tenants
Our confidence
High on 120 MW, 10 acres, five storeys and 18,880 sqm. Nil on delivery date and tenant
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

8Assumptions and method

Every figure and where it comes from
FigureBasisConfidence
120 MW IT capacityPDG India locations page and its LinkedIn announcement, repeated by DCD, W.Media, Baxtel and DataCenterMapHigh
18,880 m² colocationPDG India locations pageHigh
10 acres, five storeysPDG page and DCDHigh
6.4 kW per m²Gridvik arithmetic: 120,000 kW ÷ 18,880 m²Arithmetic
About 590 W per square footSame arithmetic in imperial unitsArithmetic
210 MW acquisitionPDG release of 24 March 2026High, but the allocation to MU2 is not stated
432 MW of named sitesGridvik addition of MU1 150, MU2 120, HY1 90 and CH1 72Arithmetic
568 MW unnamed balanceGridvik arithmetic: 1,000 less 432Arithmetic
April 2026 construction startCompany announcement and trade coverage. Groundbreaking date itself not publishedHigh
2027 deliveryThird-party tracker inference, not a company statementLow, and not recorded
Time-matched CFEPDG partnership announcement with Flexidao and Tata Power RenewablesMedium — no volume or contract disclosed

9Limits and open questions

What Gridvik will not do
We will not add 120 MW to the 210 MW acquisition or to the 1 GW portfolio, publish a delivery date, or name a tenant
First question
Who is the anchor tenant? A single 120 MW building with no pre-let is unusual in any market, and no customer has been named
Second question
What does MU2 cost? No project capex is public. At observed build rates 120 MW is ₹6,200 to ₹8,400 crore, and PDG raised $800 million of project financing for Mumbai which does not cover a site of this size on its own
Third question
How much of the 120 MW does the Tata Power arrangement cover, and on what matching basis? Volume, tariff and duration outside the agreement are unpublished
Fourth question
Where are the other 568 MW? PDG’s 1 GW Indian claim is 43% attached to specific sites
Why this record matters
Because MU2 publishes both megawatts and square metres, it is the only record in the registry that quantifies AI-readiness instead of asserting it. It is also one of very few large Indian campuses actually under construction
What changes the tier
A ready-for-service date, a named tenant, a project cost, or a power volume

10Sources

Sources: Princeton Digital Group India locations page, PDG 210 MW acquisition release, PDG LinkedIn announcement, Data Center Dynamics, W.Media, Baxtel, DataCenterMap, DataCenterLocations, DCPulse, Blackridge Research, DataM Intelligence, Flexidao and Tata Power Renewables announcements.