Facility record · Verified 26 Oct 2026

Nxtra CHE 3 — Siruseri, ChennaiNxtra by Airtel · Siruseri 2, SIPCOT IT Park, Chennai · 16 MW listed IT power

Record PRJ-066Tamil Nadu — Siruseri, ChennaiTier D — listed only5 public sources checkedAdditive: no
Stage unverifiedNo commissioning dateFacilityInside the city aggregate
16MW
Listed IT power
35%
Of the Chennai portfolio
2nd
Largest of four in Chennai
—
Commissioning date
—
Rack count
No
Additive to 46 MW

CHE 3, also called Siruseri 2, is listed by Nxtra by Airtel at 16 MW of IT power in Siruseri, Chennai — the second largest of the operator’s four Chennai facilities and about 35% of the 46 MW city portfolio. The card gives a capacity and a name. It does not give a commissioning date, a rack count, a floor area, a customer or any statement of whether the building is live. This is a real facility recorded at the depth the public evidence supports.

1At a glance

Operator
Nxtra Data Limited, the data centre subsidiary of Bharti Airtel, about 61% owned by Airtel after the March 2026 raise
Facility
CHE 3, named on the operator’s site as Siruseri 2
Location
Siruseri, in the SIPCOT IT Park south of Chennai — the same estate as CHE 2 and Siruseri DC 3, and a short drive from the east coast cable landings
Listed capacity
16 MW of IT power, per the operator’s facility card
Share of the city
about 35% of the 46 MW reported across Chennai; 33% of the 49 MW that the four cards sum to
Status
Stage unverified. The card does not say whether the facility is live, in commissioning or planned
Not disclosed
Commissioning date, rack count, rack density, floor area, PUE, customer and power source
Additivity
Not additive. It sits inside the Chennai city aggregate and must not be added to it

216 MW is a third of Chennai

Siruseri DC 327 MW27 MWCHE 3 — Siruseri 216 MW, the record on this page16 MWCHE 2 — Siruseri 14 MW4 MWCHE 1 — Santhome2 MW2 MWFour published cards summing to 49 MW against a 46 MW city headline. CHE 3 is 35% of the headline and cannot be added to it.
Figure 1The four Chennai cards as published, with CHE 3 in red. Two Siruseri buildings — DC 3 and CHE 3 — carry 43 of the city’s 46 MW.

The shape of the portfolio is the useful information here. Nxtra’s Chennai capacity is concentrated in two large buildings in the SIPCOT estate: Siruseri DC 3 at 27 MW and CHE 3 at 16 MW, together 43 MW. The other two, CHE 2 at 4 MW and CHE 1 at 2 MW, are small legacy sites — one in the same estate and one in the city.

That gives a supplier a clear map. Siruseri is where the megawatts are, and therefore where anything involving capacity — cooling, power distribution, UPS, switchgear — will be bought. The city sites matter for connectivity, not for load.

Chennai, by concentration
TestResultReading
Two largest buildings43 MW93% of the city headline
Two smallest buildings6 MW7% of the city headline
CHE 3 alone16 MW35% of the city headline
Racks implied at the portfolio’s 5 kW a rackabout 3,200arithmetic, not a published figure
Racks implied at 11 kW a rack, the Mumbai new-build rateabout 1,450the same megawatts in a much denser hall

The last two rows are the reason density matters even on a thin record. The same 16 MW is either 3,200 conventional racks or 1,450 dense ones, and the second building costs meaningfully more per megawatt. No published figure settles which this is.

3The 3 MW gap is not this building

The Chennai page reports 46 MW. The four cards sum to 49. The obvious question is whether one building accounts for the difference, and the arithmetic rules that out.

Why no single building explains the gap
FacilityCard capacityCould it be the missing 3 MW?
CHE 1 — Santhome2 MWNo. Too small, and removing it would leave a 1 MW error the other way
CHE 2 — Siruseri 14 MWNo. Too large
CHE 3 — Siruseri 216 MWNo. Far too large
Siruseri DC 327 MWNo. Far too large
Conclusion3 MWthe difference is partial counting, not an omitted facility

That is a useful conclusion reached without any additional source. Since no card equals 3 MW, the gap must come from a subset of a single building — for example a commissioned phase counted in the headline but the full design counted on the card, or one card including fit-out capacity the headline excludes. Nxtra does not explain it, and Gridvik does not allocate it.

The practical instruction is the same as for the parent record: for Chennai, use 46 MW as the operator’s headline and 49 MW as the sum of parts. Do not average them, and do not assign the difference to CHE 3 because it happens to be the second largest.

4Timeline

  • Nxtra launches a 38 MW hyperscale facility in Chennai, its third large Chennai data centre, described as 270,000 square feet and LEED certified
  • Airtel completes the landing of the SEA-ME-WE-6 cable in Chennai, 220 Tb/s of capacity, to be integrated with Nxtra’s Chennai facilities
  • CHE 3 / Siruseri 2 appears on the operator’s Chennai page with a 16 MW IT power card. No commissioning or launch announcement has been located for this specific facility
  • No stage change, no date and no additional detail in the public record

5Limits and open questions

What this record is
A facility listing with a published capacity of 16 MW and a location in the SIPCOT IT Park
What it is not
Evidence of live capacity, of a commissioning date, or of a customer
What Gridvik will not do
We will not allocate the 3 MW city gap to this building, publish a rack count, or treat the card as a live-load figure
The one question worth asking
Is CHE 3 operating, and at what rack density? Either answer would move this record from Tier D to Tier A and would set the value of the largest remaining unbuilt share of Nxtra’s Chennai capacity
What changes the tier
A commissioning statement, a rack count, a PUE for this building, or a customer reference

6Sources

Sources: Nxtra Chennai data centre page, Nxtra by Airtel site, Airtel press release of November 2021, Airtel SEA-ME-WE-6 landing release, Airtel FY26 annual report.