Facility record · Verified 26 Oct 2026

Nxtra MUM 3 — Mahape, Navi MumbaiNxtra by Airtel · Mahape 1, Navi Mumbai · 18 MW listed IT power, 1,600 racks

Record PRJ-070Maharashtra — Mahape, Navi MumbaiTier D — listed only7 public sources checkedAdditive: yes, within the Mumbai cluster
Stage unverifiedAI-grade densityFacilityCluster contains a failed 50 MW
18MW
Listed IT power
1,600
Racks
11.3kW
Per rack
1.55
Declared PUE ceiling
60MW
Across Nxtra’s two Mahape halls
50MW
Promised here and never built

MUM 3 at Mahape is listed by Nxtra by Airtel at 18 MW of IT power across 1,600 racks — 11.3 kW a rack, with a declared PUE below 1.55. That density is 77% higher than the operator’s older Mumbai halls and it is the clearest numerical evidence in this portfolio that new Indian capacity is being specified for denser equipment. Mahape is also the most instructive node in the registry, because it holds simultaneously 45 MW reported live, 40 MW that broke ground in January 2026, and 50 MW promised for mid-2024 that was never built at all.

1At a glance

Operator
Nxtra Data Limited, the data centre subsidiary of Bharti Airtel
Facility
MUM 3, named Mahape 1, in the TTC Industrial Area at Mahape, Navi Mumbai
Listed capacity
18 MW of IT power across 1,600 racks
Density
11.3 kW a rack. Gridvik arithmetic from the two published figures, and 77% above the operator’s older Mumbai halls
Efficiency
Declared PUE below 1.55. One of only two Nxtra Mumbai facilities that publishes a PUE
Status
Stage unverified by the operator’s card. An independent tracker describes this facility as commissioned, with no leaseable power under construction and no plans to add any
Not disclosed
Commissioning date, floor area, tenant list and power source
Sibling
MUM 4 at Mahape 2 is listed separately at 42 MW across 3,600 racks, or 11.7 kW a rack. Together the two Mahape halls carry 60 of Nxtra’s 71 MW in Mumbai
Additivity
Additive within the Mumbai cluster. Not additive to the national platform aggregate

211.3 kW a rack — the AI tell

Density is the one specification that separates a modern Indian hall from a legacy one, and it is derivable from numbers the operator publishes.

Nxtra MUM 442 MW, listed42 MWNxtra MUM 318 MW, listed18 MWNTT NAV1A45 MW reported live45 MWL&T Vyoma40 MW, ground broken January 202640 MWZR Power50 MW promised for 2024, nothing built0 MW builtThe one red proposition out-promised everything else in the node and delivered nothing. In Mahape, the size of the announcement has no relationship to the likelihood of the building.
Figure 1Mahape as a scoreboard. The red bar is a 50 MW project announced for mid-2024 with nothing built; every other bar is a building that exists or has broken ground.
Nxtra’s Mumbai cluster by density
FacilityMWRackskW a rackReading
MUM 1 — Chandivali46006.7legacy inner-city hall
MUM 2 — Airoli71,1006.4legacy hall, prime location
MUM 3 — Mahape 1181,60011.3modern, AI-capable
MUM 4 — Mahape 2423,60011.7modern, AI-capable, the largest

Those four rows are the whole story of the Indian data centre transition in one table. Two halls at about 6.5 kW a rack built for cloud and enterprise colocation; two at about 11.5 kW built for what is being ordered now. The same operator, the same city, and a 77% difference in what each cabinet can carry.

At 11.3 kW a rack, a hall can host GPU servers with rear-door or in-row liquid assistance without a full rebuild. It is not 170 kW a rack — the density TCS has claimed for its Hyderabad campus — but it is the density at which conventional infrastructure stops being the constraint. That is why this building is worth 18 MW of a supplier’s attention and the Chandivali building is not.

3Mahape: promise against delivery

This node is unusual because it contains the registry’s clearest controlled comparison between an announcement and a building.

Four claims on one node
ProposalClaimOutcome
ZR Power50 MW, ₹1,700 crorenothing built. Announced in 2021–22 with a mid-2024 operational target and no evidence of construction since
NTT NAV1A45 MW, about 5,000 racks, 400,000 square feetreported live. Part of an 8-acre campus planned for up to 150 MW across four buildings
L&T Vyoma40 MW on 10 acresground broken 21 January 2026. Too early to judge
Nxtra MUM 3 and MUM 460 MW across 5,200 rackslisted as operating, one of them confirmed commissioned by an independent tracker

The comparison is deliberately uncomfortable. ZR Power announced the largest single number in the node — 50 MW for ₹1,700 crore, which is ₹34 crore a megawatt — with a target of mid-2024. Four years on, there is no building. Nxtra announced nothing, built two halls, and lists 60 MW. L&T, a company with an engineering business that can actually execute, broke ground in January 2026.

The lesson is not that announcements are worthless. It is that the two things which predict delivery in this market are an operator with existing buildings and a contractor with a construction business. A first-time developer with a big number is the least reliable signal available.

The ₹34 crore a megawatt warning

ZR Power’s ₹34 crore per megawatt was well below the ₹52 to ₹70 crore cost of building. That should have been read as evidence that the outlay would not cover the project, not as evidence of efficiency.

Nearly four years later the point is settled: it did not.

4The Mumbai cluster, reconciled

Adding the four cards gives the account its proper size, and gives the market a defensible number for one operator’s Mumbai footprint.

Nxtra Mumbai, end to end
MeasureValueBasis
Facilities4Chandivali, Airoli, Mahape 1, Mahape 2
IT power71 MW4 + 7 + 18 + 42
Racks6,900600 + 1,100 + 1,600 + 3,600
Average density10.3 kW a rack71,000 kW ÷ 6,900 racks
Mumbai share of the 250 MW national figureabout 28%the annual report capacity
Mumbai share of the 300 MW March 2026 figureabout 24%the press release capacity
The contradictionthe same operator has described the national platform as 120–130 MW, 250 MW and 300 MWso the Mumbai share cannot be stated precisely

Seventy-one megawatts and 6,900 racks is a real, operating, profitable business — and it is 28% of a national platform whose own size the operator has described three different ways in six months. That is not a criticism of Nxtra specifically; it is the state of Indian data centre reporting, and it is why Gridvik publishes the arithmetic instead of the claim.

5Timeline

  • ZR Power announces a 50 MW data centre at Mahape for ₹1,700 crore with an operational target of mid-2024. Nothing is built
  • NTT brings up NAV1A at Mahape, reported at 45 MW, about 5,000 racks and 400,000 square feet, within an 8-acre campus planned for up to 150 MW
  • Nxtra brings Mahape 1 and Mahape 2 into service. An independent tracker later records Mahape 1 as commissioned with no leaseable power under construction
  • L&T breaks ground on a 40 MW facility at Mahape, in the same node that has carried a 50 MW promise since 2022
  • The operator lists MUM 3 at 18 MW across 1,600 racks with a declared PUE below 1.55, and MUM 4 at 42 MW across 3,600 racks
  • No commissioning date for either Mahape hall is published by the operator, and no tenant is named

6Procurement

Procurement window and scope
Gridvik assessment · 26 Oct 2026
What this site buys
At 11.3 kW a rack: high-density air handling or in-row cooling, high-ampacity busway, dense power distribution, containment, DCIM with thermal mapping, and UPS sized for a heavier load factor
Why Mahape is the buying node
Sixty of Nxtra’s 71 MW in Mumbai sit in two buildings here, both at modern density. The AI-relevant procurement in this account happens at this address
Neighbours worth a single visit
NTT NAV1A at 45 MW, L&T Vyoma at 40 MW under construction, and Nxtra’s two halls are within a short drive. One trip covers 163 MW of built and building capacity
Likely window
Both halls are believed complete, so this is refresh and expansion rather than first fit-out. The new-build capital is at Nxtra’s AI campuses in Mumbai, Chennai and Kolkata
Decision stage
Operating. PUE published, tenants unnamed
Quality of evidence
Better than most facility records. Four numbers including a PUE, plus an independent tracker on status and a well-documented surrounding node
Our confidence
High on 18 MW, 1,600 racks and the PUE ceiling. Medium on commissioned status, since the operator does not date its own card
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

7Assumptions and method

Every figure and where it comes from
FigureBasisConfidence
18 MW, 1,600 racksNxtra Mumbai page facility cardHigh
11.3 kW a rackGridvik arithmetic: 18,000 kW ÷ 1,600 racksArithmetic
PUE below 1.55Operator cardCompany declaration, not an audit
77% denserGridvik arithmetic against the 6.4 kW a rack of MUM 2Arithmetic
71 MW and 6,900 racks for MumbaiGridvik addition of the four published cardsArithmetic on published figures
45 MW live at NTT NAV1ATrade reportingMedium
40 MW L&T VyomaGroundbreaking reported January 2026Medium
50 MW ZR Power, not builtAnnouncement of 2021–22 with a mid-2024 target; no construction evidence locatedHigh as a failure
Commissioned statusIndependent tracker, not the operatorMedium

8Limits and open questions

What Gridvik will not do
We will not date the commissioning, name the tenants, publish a revenue figure, or treat the 11.3 kW density as evidence that AI workloads are actually hosted here
First question
When were the two Mahape halls commissioned, and at what occupancy? This is 60 MW of Mumbai capacity and the operator has never dated it
Second question
What is the design intent behind 11.3 kW a rack? It is high enough for accelerated computing and not high enough for the densest GPU halls, which suggests a deliberate middle position
Third question
Does Nxtra intend to build further at Mahape, or is the land now more valuable developed for something else? The tracker note that no leaseable power is planned suggests the campus is finished
Why this record matters
It shows a node where a 50 MW announcement and 60 MW of actual buildings can be compared over four years, and it contains the density evidence that new Indian capacity has changed specification
What changes the tier
A commissioning date, an occupancy signal, a named tenant, or a further Mahape build

9Sources