Nxtra MUM 4 — Mahape, Navi MumbaiNxtra by Airtel · Mahape 2, Thane-Belapur Road, Navi Mumbai · 42 MW listed IT power, 3,600 racks

Record PRJ-071Maharashtra — Mahape, Navi MumbaiTier D — listed only7 public sources checkedAdditive: yes, within the Mumbai cluster
Stage unverifiedDocumented replanFacilityConfused with a neighbour by directories
42MW
Listed IT power
3,600
Racks
11.7kW
Per rack
600,000sq ft
Three-tower park
60MW
Across both Mahape halls
+49%
Density against the 2021 plan

MUM 4 at Mahape 2 is listed by Nxtra by Airtel at 42 MW of IT power across 3,600 racks — 11.7 kW a rack, with a declared PUE below 1.55. It is the largest single building in Nxtra’s Mumbai cluster. The interesting part is what sits behind it. In 2021 this 600,000 square foot, three-tower park was announced at 58 MW across 7,500 racks. It now carries 60 MW across 5,200 racks — the same steel, 31% fewer cabinets, and 49% more power in each one. That is the AI transition in Indian data centres, documented in one site.

1At a glance

Operator
Nxtra Data Limited, the data centre subsidiary of Bharti Airtel
Facility
MUM 4, named Mahape 2, in the Thane-Belapur Road / TTC Industrial Area corridor at Mahape, Navi Mumbai
Listed capacity
42 MW of IT power across 3,600 racks
Density
11.7 kW a rack. The highest in Nxtra’s portfolio and 82% above its two older Mumbai halls
Efficiency
Declared PUE below 1.55
Building
Part of a three-tower hyperscale park of about 600,000 square feet. One third-party record dates the site to 2025 with expansions through 2026
Status
Stage unverified on the operator’s card. The park is described elsewhere as operating with expansions in progress
Not disclosed
Commissioning date for this specific building, tenant list, occupancy and power source
Additivity
Additive within the 71 MW Mumbai cluster. Not additive to the national platform aggregate

2The same park, replanned

Almost every record in this registry compares an announcement with nothing. This one compares two versions of the same engineering plan, five years apart, and the difference is the whole industry’s direction of travel.

The 2021 plan58 MW across 7,500 racks7.7 kWAs built today60 MW across 5,200 racks11.5 kWKilowatts per rack. Same three towers, same 600,000 square feet, 3% more power and 31% fewer racks than the original design.
Figure 1Power per rack, then and now. The megawatts barely moved. The cabinets fell by 31%. Everything that changed is in the density.
The 2021 design against what is listed now
Measure2021 planListed 2026Change
IT power across the park58 MW60 MW+3%
Racks across the park7,5005,200−31%
Power per rack7.7 kW11.5 kW+49%
Built-up area600,000 sq ft600,000 sq ftunchanged
Design PUEbelow 1.5below 1.55slightly worse, and honestly so

Read the first three rows together and the meaning is unambiguous. Nxtra did not build a bigger park. It built the same park for different equipment: 2,300 fewer cabinets, each carrying half again as much power. A design that in 2021 assumed cloud and enterprise servers at 7.7 kW a cabinet is now being filled at 11.5 kW, which is where accelerated computing starts.

The PUE moving from below 1.5 to below 1.55 is the honest cost of that change. Denser equipment is harder to cool, and pretending otherwise would be a marketing number. A 0.05 increase in PUE on 60 MW is roughly 3 MW of additional overhead load — a building’s worth of power spent on cooling the same compute.

For anyone forecasting Indian capacity, this is the most useful data point in the registry. When an operator replans for AI, the megawatt number stays roughly constant and the rack number falls. Markets that forecast capacity in racks are therefore forecasting the wrong quantity.

The number to remember

A cabinet in a 2021 Indian design carried 7.7 kW. In the same building today it carries 11.5 kW. The next generation is being specified at 100 kW and above.

Every forecast built on rack counts has already been overtaken by this shift.

3What 42 MW in one building means

Forty-two megawatts in a single facility is large for India and it puts this building in a different class from the rest of the portfolio.

Scale comparisons inside the operator’s own estate
BuildingMWRackskW a rackPosition
MUM 4 — Mahape 2423,60011.7the largest and densest
MUM 3 — Mahape 1181,60011.3sibling, same park
Siruseri DC 3, Chennai275,4005.0large but conventional
MUM 2 — Airoli71,1006.4legacy
MUM 1 — Chandivali46006.7legacy

MUM 4 alone is 59% of Nxtra’s 71 MW Mumbai cluster and about 17% of the 250 MW the company reports nationally on its annual report basis. It is also, on the density test, the only building in the estate that could host a modern accelerated-computing tenancy without a rebuild.

That concentration is worth stating plainly for a supplier: if you sell cooling or power distribution to Nxtra in Mumbai, this building is more than half your addressable opportunity in the city. The other 29 MW are legacy halls at 5 to 7 kW a rack that buy refresh, not transformation.

4Not the same as BOM1

At least one widely-read directory entry merges this park with a neighbouring project. The two are different companies and different buildings, and the error is worth correcting in public.

Two parks on the same corridor
ItemNxtra Mumbai III / MUM 3–4Digital Edge BOM1
OwnerNxtra Data, Bharti AirtelDigital Edge, with NIIF
SiteMahape / Thane-Belapur corridora 47-acre campus in the same Navi Mumbai belt
Scale announced58 MW across 7,500 racks, since replannedabout 300 MW at full build on the campus
Investmentpart of a ₹5,000 crore national programme$2 billion campus, per reporting
First phasethree towers, 600,000 sq ftBOM1, completed in late 2025
The directory errorone listing attributes the $2 billion and 47-acre figures to Nxtra’s park—

The conflation is understandable — same corridor, same year, both describe a three-letter building code next to a large number — and it is exactly the kind of error that propagates into market sizing. Two campuses of 300 MW and 60 MW became one campus of $2 billion in at least one database.

Gridvik records Nxtra’s Mahape park at 60 MW across 5,200 racks, the sum of the operator’s two published cards, and does not attribute Digital Edge’s site, capital or capacity to it.

5The Mumbai cluster, complete

With both Mahape halls counted, Nxtra’s Mumbai cluster is fully mapped for the first time in this registry.

Nxtra Mumbai, four buildings
FacilityMWRacksShare of cluster
MUM 4 — Mahape 2423,60059%
MUM 3 — Mahape 1181,60025%
MUM 2 — Airoli71,10010%
MUM 1 — Chandivali46006%
Total71 MW6,900100%

Seventy-one megawatts and 6,900 racks. On the 250 MW national figure that is about 28% of the platform in one city, and 85% of it is in two buildings on one corridor. For a vendor, that is a remarkably simple targeting problem: two addresses, one procurement function, and a stated ambition to reach 1 GW nationally.

6Timeline

  • Airtel announces a ₹5,000 crore, 400 MW expansion of Nxtra. The Navi Mumbai park is described as 58 MW of IT power and 7,500 racks across three towers of 600,000 square feet, with a design PUE below 1.5
  • The first Nxtra Mumbai III buildings are brought into service. Third-party records date the site to 2025 with expansions through 2026
  • Airtel announces a $1 billion investment in Nxtra and describes a platform of about 300 MW going to 1 GW, with Mumbai as the focus of land acquisition
  • The operator lists MUM 4 at 42 MW of IT power across 3,600 racks with a declared PUE below 1.55, and MUM 3 at 18 MW across 1,600 racks
  • No commissioning date, occupancy figure or tenant name has been published for either Mahape building

7Procurement

Procurement window and scope
Gridvik assessment · 26 Oct 2026
What this site buys
High-density distribution and cooling for 11.7 kW cabinets: high-ampacity busway, in-row and rear-door cooling, dense UPS, switchgear, DCIM with thermal mapping, leak detection if liquid is used
Why it is the account
It is 59% of Nxtra’s Mumbai megawatts and the only AI-grade building in the estate. The other three halls buy refresh
Co-located opportunity
Mahape also holds NTT’s NAV1A at 45 MW, STT’s Navi Mumbai campus and L&T’s 40 MW site under construction. One trip covers well over 150 MW of built and building capacity
Likely window
Expansions were indicated through 2026 and the halls are believed occupied. Treat this as refresh, densification and capacity extension rather than first fit-out
Decision stage
Operating or near complete. Tenants unnamed
Quality of evidence
Good for a facility card: four numbers including a PUE, a documented 2021 baseline to compare against, and independent records on the park
Our confidence
High on 42 MW, 3,600 racks and PUE. Medium on exact commissioning status
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

8Limits and open questions

What Gridvik will not do
We will not date the commissioning, name the tenants, or adopt the Digital Edge campus figures that directories have attached to this park
First question
When did MUM 4 come into service, and what share of its 3,600 racks is contracted? This is 17% of the national platform and it has never been dated
Second question
Was the reduction from 7,500 to 5,200 racks a design change or a reporting change? The arithmetic implies a deliberate replan for denser equipment, but no operator statement confirms it
Third question
Will the third tower follow the same density, or will it be specified higher? Nothing in the public record says
Why this record matters
It is the only place in the registry where an operator’s own before-and-after design numbers can be compared, and the comparison shows the market moving from 7.7 to 11.5 kW a cabinet in five years
What changes the tier
A commissioning date, an occupancy signal, a named tenant, or specification details for the third tower

9Sources