Facility record · Verified 26 Oct 2026

Nxtra NCR 1 — Sector 62, NoidaNxtra by Airtel · Sector 62, Noida, Delhi NCR · 4.5 MW listed IT power, 1,250 racks

Record PRJ-072Uttar Pradesh — Noida, Delhi NCRTier D — listed only5 public sources checkedAdditive: yes, within the NCR cluster
Stage unverifiedThree capacity figuresFacilityLegacy density
4.5MW
Listed IT power
1,250
Racks
3.6kW
Per rack
3kW
Maximum per cabinet, per a broker sheet
26MW
Nxtra’s NCR cluster
—
Commissioning date

NCR 1 at Sector 62, Noida, is listed by Nxtra by Airtel at 4.5 MW of IT power across 1,250 racks — 3.6 kW a rack. In a market where new Indian halls are specified at 11 kW a cabinet and where TCS has claimed 170 kW, that is a legacy building operating at a fraction of modern density. It is also, and this is the reason to record it carefully, the kind of building that still makes up most of India’s installed capacity.

1At a glance

Operator
Nxtra Data Limited, the data centre subsidiary of Bharti Airtel
Facility
NCR 1, at Sector 62, Noida, in the Delhi National Capital Region
Listed capacity
4.5 MW of IT power across 1,250 racks
Density
3.6 kW a rack. Among the lowest in this registry
Carrier neutrality
Stated as carrier neutral
Cooling
One third-party sheet describes the site as operating with air and liquid cooling at 2N redundancy
Status
Stage unverified on the operator’s card. A directory describes the same site as built
Not disclosed
Commissioning date, current occupancy, tenant list and power source
Additivity
Additive within Nxtra’s 38.5 MW Delhi NCR cluster, across four published cards

23.6 kW a rack

Three and a half kilowatts a cabinet is a number from a different era of computing, and it is worth putting beside the modern figures to see how far the market has moved.

The same operator, four generations of density
FacilitykW a rackWhat it can host
Nxtra NCR 1, Noida3.6single-socket enterprise servers, storage, network gear
Nxtra NCR 2, Noida2.3the lowest in the portfolio
Nxtra MUM 2, Airoli6.4dense cloud and enterprise colocation
Nxtra MUM 4, Mahape11.7accelerated computing with assisted cooling
TCS HyperVault, Hyderabad, claimedabove 170frontier AI training halls

The spread between the top and bottom of that table is 47 times. Any market statement that describes "Indian data centre capacity" as a single number is averaging buildings that cannot be compared.

The commercial consequence for this specific building is straightforward. At 3.6 kW a cabinet it is well suited to what most Indian enterprises still buy: racks of servers, storage and network equipment for regulated and government-adjacent workloads, close to Delhi, with dual-path power. It is not a candidate for GPU tenancy and will not become one without a rebuild of its cooling and power distribution.

That is not a criticism. Buildings like this carry a large share of India’s enterprise IT, they are profitable, and they have long lives. They simply sit outside the part of the market that is growing fastest.

Why the low number matters

If a third of India’s installed capacity runs at 3 to 6 kW a cabinet, then any forecast of AI capacity built by dividing megawatts by a modern rack density will overstate the number of racks the country can serve.

The rack is no longer a unit of capacity. The megawatt is.

3Three sources, three capacities

This building is a good example of how Indian facility data diverges, because three separate listings describe it with three different numbers.

The same site, three descriptions
SourceCapacityRacks or area
Operator’s Noida page4.5 MW of IT power1,250 racks
Third-party directoryabout 4.0 MWabout 1,200 racks, about 109,000 square feet
Broker capacity sheetabout 6.0 MW marketedmaximum 3 kW a cabinet, about 86,000 square feet

The three figures can be partly reconciled and not fully. At the broker’s stated maximum of 3 kW a cabinet, 1,250 racks would carry 3.75 MW — close to the operator’s 4.5 MW design and below the 6 MW marketed number, which is consistent with a facility that sells power in blocks and markets more than any single rack can draw.

What cannot be reconciled is the floor area, which varies by 27% between two third-party sheets. That is the usual signature of one source counting usable white space and another counting the whole building.

Gridvik records the operator’s 4.5 MW across 1,250 racks because it is the only figure published by the party that owns the building, and notes the other two without adopting either.

4Timeline

  • Sector 62 in Noida is established as one of the NCR’s data centre locations, close to the expressway and the Delhi border
  • The operator’s Noida page lists NCR 1 at 4.5 MW of IT power and 1,250 racks, carrier neutral, with no commissioning status
  • Airtel describes Nxtra’s platform growing from around 120–130 MW to 1 GW, with new AI campuses in Mumbai, Chennai and Kolkata rather than Noida
  • No stage change, no date and no additional detail for this facility in the public record

5Procurement

Procurement window and scope
Gridvik assessment · 26 Oct 2026
What this site buys
Refresh at low density: UPS and switchgear replacement, precision cooling maintenance, containment, PDUs, monitoring and physical security
What it does not buy
Liquid cooling, high-ampacity busway or dense power packages. Three kilowatts a cabinet is not a modern specification
Account structure
Nxtra’s national engineering and procurement function, not the Noida site. NCR is not where the operator’s new capital is going
Likely window
Continuous small-bore refresh. No NCR expansion programme is in the public record
Decision stage
Operating. No expansion evidenced
Quality of evidence
Medium. An operator card with two numbers and two conflicting third-party descriptions
Our confidence
High on 4.5 MW and 1,250 racks. Nil on current occupancy and date
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

6Limits and open questions

What this record is
A 4.5 MW, 1,250-rack facility at Sector 62, Noida, at legacy density
What it is not
Evidence of live load, a date, an occupancy figure, or a building capable of hosting accelerated computing
What Gridvik will not do
We will not adopt the 6 MW marketed figure as capacity, reconcile the floor areas, or assume the site is fully let
The question worth asking
What is the current load? A 4.5 MW design at 3.6 kW a cabinet is likely to be power-constrained long before it is space-constrained, which changes both its value and its upgrade path
Why it stays in the registry
Because buildings at this density are the majority of India’s installed base and are systematically absent from the market’s AI-focused reporting
What changes the tier
An occupancy signal, a commissioning date, or a refurbishment announcement