Nxtra BLR 1 — Whitefield, BengaluruNxtra by Airtel · Plot 111 and 112, EPIP Zone, Whitefield, Bengaluru · 5.4 MW listed IT power, 2,000 racks

Record PRJ-075Karnataka — Whitefield, BengaluruTier D — listed only6 public sources checkedAdditive: yes, within the Bengaluru cluster
Stage unverifiedLowest tier of densityFacilityNo PUE published
5.4MW
Listed IT power
2,000
Racks
2.7kW
Per rack
45.4MW
Nxtra’s Bengaluru cluster
11%
Of Karnataka’s 400 MW
—
Commissioning date

BLR 1 at Whitefield is listed by Nxtra by Airtel at 5.4 MW of IT power across 2,000 racks — 2.7 kW a rack, the second lowest density in this registry. It is the smallest of the operator’s four Bengaluru buildings by power and the second largest by cabinet count, which tells you almost everything about when it was designed. Whitefield is where Bengaluru’s data centre industry started, and its buildings were laid out when a cabinet meant a rack of servers drawing under three kilowatts.

1At a glance

Operator
Nxtra Data Limited, the data centre subsidiary of Bharti Airtel
Facility
BLR 1, at Plot 111 and 112, EPIP Zone, Whitefield, Bengaluru
Listed capacity
5.4 MW of IT power across 2,000 racks
Density
2.7 kW a rack. Only one facility in this registry is lower
Efficiency
No PUE published for this building, unlike the operator’s three other Bengaluru facilities, which all declare below 1.55
Carrier neutrality
Stated as carrier neutral
Status
Stage unverified on the operator’s card. Independent listings place the site in operation
Not disclosed
Commissioning date, floor area, current load, tenant list and power source
Additivity
Additive within Nxtra’s 45.4 MW Bengaluru cluster

22.7 kW a rack

Two numbers describe this building and a division describes what it is for.

DC220 MW, 4,000 racks20 MWBLR 2 — Hoskote 114 MW, 2,800 racks14 MWBLR 3 — Hoskote 26 MW, 1,000 racks6 MWBLR 1 — Whitefield5.4 MW, 2,000 racks5.4 MWThe smallest building by power holds the second most racks in the cluster. Whitefield is space-rich and power-poor.
Figure 1Four Bengaluru cards. The red bar is the smallest by power and holds the second largest rack count — a building designed before density mattered.
The density floor of the registry
FacilitykW a rackRacks
Nxtra NCR 2, Noida2.31,500
Nxtra BLR 1, Whitefield2.72,000
Nxtra NCR 1, Noida3.61,250
Nxtra DC2, Bengaluru5.04,000
Nxtra MUM 4, Mahape11.73,600
TCS HyperVault, Hyderabad, claimedabove 170—

At 2.7 kW a cabinet this building is space-constrained long before it is power-constrained. Two thousand cabinets occupy the floor area of a 5.4 MW building, where the same load at Mahape density would fit into roughly 460. That inverts the usual Indian data centre problem, where land and power are scarce and cabinets are the thing operators build to fill.

Its commercial life is therefore long and undramatic. Two kilowatts a cabinet serves exactly what a large share of Bengaluru’s enterprise market still buys: racks of servers, storage arrays, network equipment and backup infrastructure for software and services companies in the surrounding EPIP zone. It will not host a GPU. It will keep earning.

The unrecognised half of the market

India’s installed base is mostly buildings like this one — under six kilowatts a cabinet, profitable, unexciting, and invisible in AI coverage.

Any supplier whose strategy is only AI capacity is ignoring the majority of the sites that actually exist.

3Whitefield: the original corridor

Whitefield is Bengaluru’s first data centre corridor and it is still one of the densest concentrations of IT infrastructure in India, but the new capacity has moved east.

What surrounds this building
NeighbourPosition
Iron Mountain BLR-180,000 square feet and about 4 MW in Whitefield, roughly 1.6 miles away
STT Bengaluru DC 2 and DC 3KIADB EPIP layout in Whitefield, within a few miles
CapitaLand Bangalore 01inside International Tech Park Bangalore in Whitefield
NTT Bengaluru facilitiesincluding a newer campus near the airport with 100 MW planned
The EPIP zone itselfBengaluru’s original export promotion industrial park, surrounded by software campuses and the customers they house
Why the growth movedWhitefield is built up. Hoskote, further east on the highway, has the land and is where Karnataka is planning a 500 MW data park

That is the shape of the market in one city. The customers stayed in Whitefield; the capacity is moving to Hoskote, about 30 kilometres east, because land, substations and water are available there and are not here.

For an operator this is the familiar dilemma. An old building in the right location with the wrong density is worth keeping for its contracts and cross-connects, and worth nothing for growth. Nxtra’s answer, visible in its own four cards, has been to build the new capacity at Hoskote and leave Whitefield to run.

4Bengaluru’s four buildings

The cluster arithmetic is the useful frame, and Bengaluru turns out to be the operator’s most rack-heavy cluster relative to its power.

Nxtra Bengaluru, four cards
FacilityLocationMWRackskW a rack
DC2locality not stated204,0005.0
BLR 2Hoskote142,8005.0
BLR 3Hoskote61,0006.0
BLR 1Whitefield5.42,0002.7
Totalfour buildings45.49,8004.6

Forty-five megawatts across 9,800 racks. Compare that with Nxtra’s Mumbai cluster at 71 MW across 6,900 racks. Bengaluru has 42% more cabinets on 36% less power. The same operator, two cities, and two very different physical estates.

That is what a mature software market looks like in infrastructure terms: many enterprise tenants in many small footprints, rather than a few hyperscalers in dense halls. Karnataka’s government estimates the state has about 400 MW of data centre capacity today, which would put Nxtra at roughly 11% of the state.

5Timeline

  • Whitefield is established as Nxtra’s Bengaluru base and as one of India’s earliest data centre corridors, alongside the city’s software industry
  • The operator’s Bengaluru page lists BLR 1 at 5.4 MW of IT power and 2,000 racks, with no PUE and no commissioning status
  • Karnataka announces three sustainable data parks totalling 1,000 MW, including 500 MW near Hoskote, powered from Pavagada and supplied with 60 MLD of treated water
  • Karnataka approves a Sustainable Data Centre Policy for 2026–31 targeting 1 GW of IT capacity by 2031 with a ₹1,300.45 crore framework
  • No stage change, no date and no additional detail for BLR 1 in the public record

6Limits and open questions

What this record is
A 5.4 MW, 2,000-rack facility in Whitefield at 2.7 kW a cabinet
What it is not
A confirmed live-load figure, a dated commissioning, or a building with any upgrade path to modern density
What Gridvik will not do
We will not infer a PUE, assume the 2,000 racks are occupied, or describe the building as AI-ready because the operator’s page uses that phrase for the cluster
The question worth asking
What is the actual electrical load today? A building this power-light relative to its cabinet count is either very full and very underutilised electrically, or half empty
Why it stays in the registry
Because buildings at this density are most of India’s installed base, and because the contrast with Hoskote in the same cluster is the clearest evidence of how the specification changed
What changes the tier
A commissioning date, a load figure, a PUE, or a redevelopment announcement

7Sources

Sources: Nxtra Bengaluru data centre page, Nxtra by Airtel site, DataCenterMap Bangalore listings, DataCenterHawk, Baxtel, PeeringDB, Karnataka government data park announcements, Economic Times and ETDatacenters on the Karnataka data centre policy.