Facility record · Verified 26 Oct 2026

CtrlS Patna Edge DC 1 — PatnaCtrlS Datacenters · Plot 18, Pataliputra Industrial Area, Patna 800013 · 0.5 MW IT load, 109 racks

Record PRJ-086Bihar — PatnaTier C — operator listed7 public sources checkedAdditive: yes
OperationalEdge facilitySmallest record in registryCarrier neutral
0.5MW
IT load
109
Racks
4.6kW
Per rack
300m
To the next CtrlS site
12.1MW
Counted capacity, all Bihar
4%
Of Bihar’s counted base

Patna Edge DC 1 is operated by CtrlS Datacenters at 0.5 MW of IT load across 109 racks — 4.6 kW a rack — at Plot 18 in the Pataliputra Industrial Area. It is the smallest record in this registry and one of the few that is unambiguously operational, which makes it more useful than half the gigawatt announcements in the file. Three hundred metres away the same company has just opened a building it describes as 1,670 racks and, depending on which statement you read, 10, 11.6 or 12 MW.

1At a glance

Operator
CtrlS Datacenters Limited, the Hyderabad-based Rated-4 operator, founded 2007
Facility
Patna Edge DC 1, Plot 18, Pataliputra Industrial Area, Patna 800013
Listed capacity
0.5 MW of IT load across 109 racks
Density
4.6 kW a rack
Status
Operational. Described by the operator as its existing Patna facility, distinct from the building 300 metres away
Security and connectivity
Stated as carrier neutral with three-zone security; the company applies a nine-zone standard at its larger sites
Neighbours
CtrlS Patna Edge DC 2 at Plot 32 and 33, about 300 metres away; Jay Prakash Narayan International Airport about 9 km
Not disclosed
Commissioning year, current occupancy, PUE and tenant list
Additivity
Additive, and not to be combined with DC 2 — the two are separate facilities with separate power

2109 racks in a state with no data centres

Bihar had no commercial data centre sector until recently. Its first AI-ready facility opened in October 2026. This building predates all of that, and it is the reason it matters: it is the only record in the state that was operating before the announcements began.

CtrlS Bodh Gaya AI factory150 MW, letter of intent only150 MWCtrlS Patna Edge DC 211.6 MW, 1,670 racks, operational11.6 MWCtrlS Patna Edge DC 1 — this building0.5 MW, 109 racks, operational0.5 MWOne letter of intent is 12 times everything built in the state. The red bar is the only record in Bihar that was running before 2026.
Figure 1Three records and a letter of intent. The grey bar is not capacity — it is a memorandum of understanding announced on 13 October 2026.
Bihar, all four records
RecordMWRacksStatus
CtrlS Patna Edge DC 10.5109operational
CtrlS Patna Edge DC 211.61,670operational
CtrlS Bodh Gaya AI factory150not statedletter of intent
CtrlS state investment announcementno capacity—announced

Twelve point one megawatts counted across the state, all of it one company. The 150 MW Bodh Gaya project is a letter of intent and is not in the count. That is what a virgin market looks like in a registry: two buildings, one operator, and a state target of 1,000 MW issued by the chief minister at the opening of the second one.

The comparison worth carrying is that a single 109-rack building, at 0.5 MW, is 4% of all counted data centre capacity in Bihar. In Maharashtra the equivalent record would be a rounding error. Here it is a load-bearing fact.

Why small operational records matter more than large planned ones

A 0.5 MW building with a power connection, a customer list and a billing meter is evidence. A 150 MW letter of intent is a document.

In a state starting from nothing, the first is the only thing that tells you what the market actually pays.

3The 300-metre pair

The two CtrlS buildings in Patna are the sharpest old-against-new comparison in this registry, because they are on the same street and the company describes both of them.

One street, two generations
MeasureEdge DC 1Edge DC 2
IT load0.5 MW10 MW announced, 11.6 MW on the operator’s page, 12 MW at the opening
Racks109about 1,000 announced, 1,670 on the operator’s page
Density4.6 kWabout 7.2 kW on the operator’s figures
AddressPlot 18Plot 32 and 33, near P&M Mall
Distance apart—about 300 metres
Investmentnot disclosed₹400 crore
Openedearlier13 October 2026

Three capacity statements for one new building is the finding. The August 2024 announcement said 10 MW and about 1,000 racks. The operator’s portfolio page says 11.6 MW and 1,670 racks. The inauguration release says 12 MW of IT load. Each is plausible and none reconciles: 1,670 racks at 12 MW is 7.2 kW a rack, while 1,000 racks at 10 MW is 10 kW a rack.

Gridvik records DC 1 on this page and will record DC 2 separately with all three figures shown, because the gap between 1,000 and 1,670 racks is the difference between a mid-size edge site and a large one, and because the density implied differs by 40%.

4What ₹400 crore buys

Cost per megawatt, and why it looks low
ItemValueNote
Announced investment₹400 crorefrom the August 2024 land announcement and repeated at the opening
Capacity basis10 MW announced, 11.6 MW card, 12 MW at openinguse 12 MW as the most generous
Implied costabout ₹33 crore a megawattGridvik arithmetic
Comparable build cost in this registry₹52 to ₹70 crore a megawattfor colocation shells without land
Why it is lowerland came through the state industrial authority, and IT equipment is not usually in the number—

Thirty-three crore a megawatt is not a bargain; it is a different accounting boundary. Land acquired through a state development authority, a shell built to whatever specification the operator chose, and a fit-out that may or may not include customer equipment will all move that number by a factor of two. Anyone comparing ₹33 crore with a ₹60 crore benchmark without asking what is inside the number is comparing two different things.

The number that does hold up is the company’s own trajectory. CtrlS says it will have built over 4.4 GW of capacity by 2030. A rating agency’s projection has its operational capacity rising from about 150 MW in the current financial year to 950–1,000 MW by 2029. The analyst number is about a fifth of the company number, and both are public, and neither is wrong — one is a target and the other is a forecast.

5Timeline

  • CtrlS develops an edge facility at Plot 18 in the Pataliputra Industrial Area, one of its earliest tier-2 sites
  • The company acquires land 300 metres away through the state industrial area development authority and announces ₹400 crore, 10 MW and about 1,000 racks
  • The operator’s portfolio page lists Patna Edge DC 1 at 0.5 MW and 109 racks, and Patna Edge DC 2 at 11.6 MW and 1,670 racks
  • The second Patna building is inaugurated with a stated 12 MW of IT load; a ₹10,000 crore, 150 MW Bodh Gaya AI factory is announced as a letter of intent
  • No commissioning year, PUE or occupancy figure for Patna Edge DC 1 in the public record

6Procurement

Procurement window and scope
Gridvik assessment · 26 Oct 2026
What this site buys
Very little. A 109-rack edge site at 4.6 kW a rack is on maintenance and refresh, not expansion
What the site next door buys
Everything a new 1,670-rack building needs: switchgear, UPS, cooling, containment, fire suppression, security and DCIM. That is the commercial event in Bihar this year
Why the small site still matters to a vendor
It is the live reference. A vendor selling into DC 2 will be asked what already works in Patna, and this is the answer
Account structure
CtrlS is unlisted and centrally procures from Hyderabad, with a ₹7,000 crore commitment from a Canadian pension fund behind its expansion
Likely window
Now, on DC 2. The building opened in October 2026 and fit-out of remaining capacity follows demand
Quality of evidence
Strong. The operator publishes racks and IT load for both Patna sites
Our confidence
High on 0.5 MW and 109 racks. Medium on the commissioning year, which is not published
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

7Limits and open questions

What this record is
A 109-rack, 0.5 MW operational edge facility in Patna — the smallest record in this registry and the oldest commercial data centre in Bihar
What it is not
A current occupancy figure, a PUE, or any evidence of what it earns
What Gridvik will not do
We will not merge it with DC 2, and we will not adopt any of the three DC 2 figures until the operator settles on one
First question
When was this building commissioned, and how full is it? A 109-rack site in a state capital is either a profitable monopoly or an empty shell, and the difference matters to anyone pricing the Bihar market
Second question
Is DC 2 at 1,000 racks or 1,670? The gap decides whether Patna has a mid-size edge site or a genuine regional facility
Third question
Will Bihar reach 1,000 MW in five years, as the chief minister said at the opening? The counted base today is 12.1 MW and the only signed document is a letter of intent
Why this record matters
It is proof that the registry counts what exists, not what is promised — and in a state with one operator and a gigawatt target, that distinction is the entire product
What changes the tier
A commissioning year, a PUE, an occupancy figure, or a single reconciled capacity for DC 2

8Sources

Sources: CtrlS Datacenters Patna data centre page, CtrlS corporate site and colocation pages, DataCenterMap Patna listings, PeeringDB facilities register, Data Center Dynamics on the Patna land acquisition, The Hindu BusinessLine on the ₹400 crore Patna investment, Times of India and Reuters reports on the October 2026 inauguration and Bodh Gaya letter of intent.