STT GDC Palava 4 — MaharashtraSTT GDC India · Palava, Dombivli · 60.5 MW, largest single building card in the Indian estate

Record PRJ-117Maharashtra — PalavaTier C — single operator source4 public sources checkedAdditive: no — inside the 400 MW campus
No dates publishedEngineered figure, not a round oneFacilityTwin of Palava 5
60.5MW
Listed capacity
121MW
This building plus Palava 5
91%
Of the current 133 MW portfolio
49MW
Largest building in it today
400MW
Campus design capacity
0
Dates published

STT GDC Palava 4 is 60.5 MW — the largest single building card in the company’s Indian estate, ahead of Navi Mumbai 2 at 49 MW. The figure is not round, which usually means an engineer produced it rather than a marketing team. It also appears twice: Palava 5 is 60.5 MW as well, so the campus will hold 121 MW in two matched buildings — 91% of the entire current Mumbai portfolio, in buildings that do not yet exist. No basis, rack count, PUE or date is published for either of them.

1At a glance

Operator
STT GDC India
Facility
Palava 4, Palava, Dombivli
Capacity
60.5 MW, basis unstated
Position
Largest single building card in the Indian estate, above Navi Mumbai 2 at 49 MW
Twin
Palava 5 at an identical 60.5 MW — PRJ-118
Combined
121 MW, or 91% of the current 133 MW Mumbai portfolio
Campus
400 MW design capacity on 46 acres, tracked as PRJ-061
Status
Stage unverified. No date, no phase, no construction evidence for this specific building
Additivity
Not additive. Counted at 0 MW

2Sixty point five is an engineered number

A number ending in .5 is worth pausing on. It almost never comes from a plan; it comes from equipment.

Round and non-round figures, and what they usually mean
FigureWhereReading
400 MWPalava campus designa target, agreed at a board or a government meeting
50 MWPalava phase onea round phase, likely a power allocation
60.5 MWPalava 4 and Palava 5a sum of installed equipment
49 MWNavi Mumbai 2either a design or a contractual figure
36.8 MWCtrlS Mumbai DC 4the same signature — see PRJ-097
7.4 MWCtrlS Hyderabad DC 2the same signature again

Sixty point five megawatts is what you get when you add up transformer ratings, UPS modules and cooling plant and land on a total that is not quite sixty and not quite sixty-one. That makes it the most credible capacity figure on this campus.

It also tells you the campus is being designed rather than sketched. Somebody has laid out two halls and sized the electrical plant. That is a much stronger signal of intent than a 400 MW headline.

3Two buildings, 121 MW

The matched pair is the story of this batch, and it is only visible because the registry publishes cards rather than aggregates.

Palava 4 and Palava 5two identical buildings at 60.5 MW each121 MWNavi Mumbai 2 and 3the current largest pair91 MWPalava 1first phase50 MWMumbai city, all three4 + 1 + 9 MW14 MWSixty point five megawatts is the biggest single card in the estate, and it appears twice. Two identical buildings at Palava will hold 121 MW — more than ninety per cent of the entire current portfolio.
Figure 1The largest cards in the estate. Red is the matched pair at Palava; navy is the current largest pair, on a different node.
The pair against everything operating
GroupingMWReads as
Palava 4 and Palava 5121two buildings, 91% of today’s portfolio
Entire current Mumbai portfolio133six buildings across three nodes
Navi Mumbai 2 and 391the current workhorse pair
All three Mumbai city buildings14one ninth of the new pair
Mumbai 2, the smallest1121 times smaller than the pair

Two buildings on a greenfield campus will hold more than ninety per cent of what the company operates across Mumbai today. That is how fast the Indian market is scaling: the new campus is not an increment, it is a replacement in capacity terms.

For the market, the risk is timing. If both land inside two years, Mumbai supply loosens materially and pricing pressure follows. If they slip, the current tightness persists and the operating portfolio keeps its pricing power. Nothing published tells you which.

4Where it sits on the campus

The three named buildings account for less than half of the campus design capacity.

Palava, building by building
BuildingMWRecordStage
Palava 150PRJ-116unverified, phase one
Palava 460.5this recordunverified
Palava 560.5PRJ-118under development
Named total17143% of the campus—
Unnamed remainder229no names, no datesdesign capacity only
Campus design400PRJ-061groundbreaking March 2026

The numbering is odd and worth noting: buildings 1, 4 and 5 are named, and 2 and 3 are not published. That usually means the middle phases are either not yet designed or are being held for a specific anchor tenant whose requirements are not settled.

For a buyer, the numbering is a useful scheduling clue. It suggests a sequence in which phase two and three will be defined later, which means the campus will be built over a longer period than a single design-and-build would take.

5Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
The schedule for the two largest buildings in the Indian estate, neither of which has a date
Who holds the answer
STT GDC India commercial team; the park developer for power and utilities
The one question
When do Palava 4 and 5 deliver, and is the 60.5 MW a design figure or a sanctioned load
Why they will answer it
Two 60 MW buildings set the market price for Mumbai capacity in 2029 and every tenant knows it
Gridvik estimate
The pair delivers after phase one, likely 2028 to 2029, and the 60.5 MW is a design figure. Labelled an estimate
What changes it
A phase schedule, a power sanction, or an anchor tenant
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

6Limits and open questions

  • No dates at all. No construction evidence for this specific building.
  • No basis, racks, floor area or PUE. The 60.5 MW is an unlabelled number.
  • Buildings 2 and 3 are missing from the published numbering.
  • 229 MW of the campus is unnamed and not counted anywhere.
  • The pair is inferred to be a standard design from the identical capacity. That is a reasonable reading, not an operator statement.
  • What would close it. A phase schedule. The capacity is already the most credible number on the campus.

7Sources

Sources: STT GDC India Mumbai city page, STT GDC India corporate site, STT GDC Palava campus material, Data Center Dynamics on the Palava groundbreaking, and Indian market commentary on the Palava and Dombivli corridor.