Facility record · Verified 26 Oct 2026

STT GDC Palava 5 — MaharashtraSTT GDC India · Palava, Dombivli · 60.5 MW, twin of Palava 4 and the only Palava card marked under development

Record PRJ-118Maharashtra — PalavaTier C — single operator source4 public sources checkedAdditive: no — inside the 400 MW campus
Under constructionTwin of Palava 4Facility91% of the estate, in two buildings
60.5MW
Listed capacity
121MW
The pair
91%
Of the current 133 MW portfolio
171MW
Named on the campus
229MW
Unnamed on the campus
0
Dates published

STT GDC Palava 5 is 60.5 MW, identical to Palava 4, and it is the only card on the campus the operator labels under development. Two buildings with the same non-round capacity is what a standardised design looks like from outside: one set of drawings, built twice. Together they will hold 121 MW — 91% of the company’s entire current Mumbai portfolio — on a campus designed for 400 MW, of which 229 MW still has no building name. No dates, no basis, no rack count, no PUE.

1At a glance

Operator
STT GDC India
Facility
Palava 5, Palava, Dombivli
Capacity
60.5 MW, identical to Palava 4
Stage
Under development — the only Palava card the operator labels this way
The pair
121 MW, or 91% of the current 133 MW Mumbai portfolio
Campus
171 MW named across three cards, 229 MW unnamed, 400 MW design
Racks, floor area, PUE
None published
Dates
None. No start, no completion, no phase
Additivity
Not additive. Counted at 0 MW

2Two identical buildings

A capacity that repeats to the decimal across two buildings is the strongest public evidence of how this campus is being built.

Palava 4 and 5two identical 60.5 MW buildings121 MWPalava 1the first phase, 50 MW50 MWNavi Mumbai 4under construction on the other node36 MWAll three Mumbai city buildingsthe entire city tail14 MWTwo identical buildings of 60.5 MW each, a 50 MW first phase, and a 36 MW building on another node. All four are counted at zero megawatts in this registry.
Figure 1The pair, the first phase, a building on the other node, and the entire city tail — four of the largest pending assets in Maharashtra, none of them counted.
What identical cards imply
SignalReading
Same capacity to 0.1 MWone design, built twice — standardised halls
Same campus, same siteshared substation, shared cooling plant, shared security perimeter
Non-round figurean equipment sum, not a marketing target
One marked under development, one nota two-building sequence, not a simultaneous build
No dates on eitherthe schedule is the missing half of the story
No basis on eitherthe 60.5 MW may be IT or gross, and the gap is a third of the building

Standardisation is how hyperscale capacity is delivered at this size: one design, one supply chain, one commissioning procedure, repeated. It is faster and cheaper per megawatt than bespoke, and it is the reason a campus can go from groundbreaking to 121 MW in a few years.

It also means the pair will succeed or fail together. Shared plant is efficient, and it is also shared risk.

3What the pairs tell you about the build

This batch contains three matched or near-matched pairs. Reading them together is more informative than reading any one card.

Pairs across the file
PairCapacityWhat it tells you
Palava 4 and 560.5 + 60.5 MWa single design built twice on a new campus
Navi Mumbai 2 and 349 + 42 MWtwo generations on one node, close but not identical
CtrlS Mumbai DC 4 and DC 536.8 + 32 MWa large building and its smaller successor
CtrlS Mumbai DC 1 and DC 240 MW combinedtwo old buildings published as one card — see PRJ-095
Palava 1 against Navi Mumbai 250 against 49 MWthe new phase is 1 MW bigger than the flagship

The pattern is a market standardising. Early Indian data centres were bespoke buildings of odd sizes. The current generation is a repeated module of 50 to 60 MW, which is a direct consequence of how much power a substation can deliver and how much cooling plant fits on a plot.

That standardisation is the most useful thing a buyer can learn from these cards, and no operator states it. It is only visible when you put the numbers side by side.

4The zero that keeps appearing

Every building on this page — 121 MW of Palava, 36 MW under construction at Navi Mumbai, 14 MW of city capacity — is counted at zero in this registry’s state totals.

What Maharashtra actually counts against what it operates
GroupMW publishedMW countedWhy
STT current Mumbai portfolio1330flagged non-additive against its own aggregate
STT Navi Mumbai 4360under development, aggregate inclusion unresolved
STT Palava 1, 4 and 51710inside the 400 MW campus aggregate
STT Palava campus claim4000design capacity, not built
CtrlS Mumbai DC 1 to DC 5118.80inside the 700 MW campus claim
CtrlS Kolkata DC 1160inside the 60 MW Kolkata campus claim

The rule that stops double counting — never add a child to its parent — is correct on its own terms. Applied to operators who publish a campus ceiling and then individual buildings, it produces a state total that excludes almost everything operating.

This is recorded on the pages rather than buried, because it is the single biggest known defect in this registry and the fix is a data-model decision rather than new research: count the facility, hold the campus as a ceiling.

Read this before quoting the state total

Maharashtra publishes 88 records and counts 786.4 MW. Several of the largest operating buildings in the state are inside that 786.4 and several are not, and the difference is a flag rather than a fact.

Until the flag is fixed, quote facility records with their operators named, not just the state total.

5Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
The schedule and pre-let status of the two 60.5 MW buildings that will define Mumbai pricing in 2029
Who holds the answer
STT GDC India commercial team; the park developer for utilities timing
The one question
Which of the pair delivers first, and what is the commissioning sequence across the campus
Why they will answer it
Two identical buildings mean a published schedule is a simple answer, and tenants are already underwriting it
Gridvik estimate
The pair delivers in sequence after the 50 MW phase one, likely 2028 into 2029. Labelled an estimate
What changes it
A phase schedule, a power sanction, or an anchor tenant announcement
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

6Limits and open questions

  • No dates. Under development with no start or completion date.
  • No basis, racks, floor area or PUE. The 60.5 MW is unlabelled.
  • Standardisation is inferred from identical capacities, not stated by the operator.
  • Shared plant is assumed from a shared campus, which matters for resilience and is unverified.
  • 229 MW of the campus remains unnamed.
  • What would close it. A commissioning sequence for the three named buildings.

7Sources

Sources: STT GDC India Mumbai city page, STT GDC India corporate site, STT GDC Palava campus material, Data Center Dynamics on the Palava groundbreaking and on the KKR and Singtel acquisition, and Indian market commentary on the Palava and Dombivli data centre corridor.