Facility record · Verified 26 Oct 2026

STT GDC Noida 1 — Uttar PradeshSTT GDC India · Noida · 17 MW on the card, scalable to 35 MW in narrative, under construction

Record PRJ-120Uttar Pradesh — NoidaTier C — two conflicting operator figures4 public sources checkedAdditive: no — inside the 63 MW portfolio
Under construction17 MW or 35 MWFacilitySmallest Noida card
17MW
Card capacity
35MW
Scalability narrative
18MW
Unresolved gap
2.1×
Difference between the two
63MW
Noida portfolio headline
0
Dates published

STT GDC Noida 1 is 17 MW on the facility card and 35 MW in a separate narrative on the same operator site. Both figures are published, neither has been withdrawn, and the 18 MW between them is larger than every Mumbai city building the same company runs. The building is under construction. No rack count, floor area, PUE or delivery date is published. This registry keeps 17 MW — the card value, because cards are what reconcile — and records the 35 as a scalability claim, because on a building that does not yet exist, scalability is a design intention rather than a capacity.

1At a glance

Operator
STT GDC India
Facility
Noida 1, Uttar Pradesh
Card capacity
17 MW
Narrative capacity
up to 35 MW in a separate description of the same building
Gap
18 MW, or 2.1 times the card value
Position
Smallest of the three Noida cards, inside a 63 MW portfolio headline
Stage
Under construction. No start, completion or phase date
Racks, floor area, PUE
None published
Additivity
Not additive. Counted at 0 MW

2Which number governs

Three readings of a 17 and a 35 on the same page, and no way to choose between them from outside the company.

Card valuethe figure in the portfolio sum17 MWScalability narrativeup to, in a separate description35 MWThe gapinvisible in every published total18 MWThe difference between the card and the narrative is larger than every Mumbai city building in the same operator’s estate, and it is not counted anywhere.
Figure 1The card value, the scalability claim, and the difference between them — which appears in no total anywhere.
Reading a scalability claim
If it meansThenConsequence
Phase one is 17 MW, the shell can reach 35both are true, on a schedule nobody has publishedNoida 1 is a 35 MW building with a 17 MW opening phase
17 MW is what is contracted, 35 is designthe card is the commercial figurethe portfolio headline should use 17
17 is an error and 35 is correctthe Noida portfolio is 85 MW, not 63the headline is 22 MW wrong

The first reading is the most likely, and it is also the most useful: a phased building where the first phase is the sellable capacity and the design ceiling is twice that. That is standard practice and entirely reasonable.

The problem is that a scalability figure and a capacity figure look identical in a table. If 35 MW enters a market model, Noida 1 becomes the largest building in the portfolio and the Noida headline becomes wrong. Nothing on the page stops that happening.

3Why the lower one is the right one to hold

The choice of 17 over 35 is a methodology decision, and it should be stated rather than assumed.

Why this registry uses the card value
ReasonDetail
Cards reconcileAcross eight STT cities the cards sum to 389.5 MW; the headlines to 354. Cards are the checkable layer
Scalability is not capacityA ceiling describes what a site could hold, not what will be energised
The building is under constructionNothing has been commissioned, so neither figure describes existing supply
Conservative arithmeticUnderstating a portfolio is recoverable. Overstating it contaminates every ratio built on it
The gap is recordedthe 18 MW is published here, not deleted

The same rule is applied consistently across this file. CtrlS’s 700 MW Chandanvelly scalability is not counted, STT’s 400 MW Palava design capacity is not counted, and the 1.2 GW and 1.4 GW ceilings on the two CtrlS Hyderabad parks are not counted. Each one is published on its own page as a claim.

That consistency is the point: a buyer can disagree with the choice, but they cannot claim the numbers were inflated.

4Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
The phase structure of a building described by two different capacities
Who holds the answer
STT GDC India commercial team
The one question
Is 17 MW phase one of a 35 MW building, and when does phase one deliver
Why they will answer it
Noida capacity is sold in phases and the phase boundary is the first thing a tenant asks about
Gridvik estimate
17 MW is phase one and the shell is designed for 35. Labelled an estimate — the operator has not said so
What changes it
A phase schedule, or withdrawal of one of the two figures
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

5Limits and open questions

  • Two capacities, no reconciliation. The core defect of this record.
  • No dates. Under construction with no start or completion.
  • No racks, floor area or PUE. Density cannot be computed.
  • No basis stated for either the 17 or the 35, though the city headline is labelled IT capacity.
  • Single source. No trade press or directory carries either figure.
  • What would close it. One sentence from the operator saying which figure describes what.

6Sources

Sources: STT GDC India Noida city page, STT GDC India facility pages for Noida, STT GDC India corporate site, and Indian market commentary on Noida data centre supply.