STT GDC Noida 2 — Uttar PradeshSTT GDC India · Noida · 22 MW under construction, no delivery date

Record PRJ-121Uttar Pradesh — NoidaTier C — single operator source4 public sources checkedAdditive: no — inside the 63 MW portfolio
Under constructionNo delivery dateFacility6.7% of counted Noida
22MW
Card capacity
63MW
Noida portfolio headline
326MW
Counted Noida market
6.7%
Share of the counted market
5.5×
Every Mumbai city building combined
0
Dates published

STT GDC Noida 2 is 22 MW and labelled under construction. No start date, no completion date, no rack count, no PUE. It is 5.5 times the entire Mumbai city portfolio the same company operates, and it is 6.7% of the counted Noida market on its own — a market that counts 326 MW across every operator. That combination is the problem with the Noida pipeline in one building: it is big enough to move prices, and it has no date attached to it.

1At a glance

Operator
STT GDC India
Facility
Noida 2, Uttar Pradesh
Capacity
22 MW, basis unstated
Stage
Under construction. No start, completion or phase date
Position
Second largest of three Noida cards, behind Noida 3 at 28 MW
Against the market
6.7% of the 326 MW counted in Noida and Greater Noida
Racks, floor area, PUE
None published
Additivity
Not additive. Counted at 0 MW

2Twenty-two megawatts is a market event

Noida is a large submarket with a handful of big records. A 22 MW building arriving into it moves the total by a visible amount.

Yotta Greater Noida upcomingannounced, counted120 MWYotta D2 Greater Noidaoperational, counted60 MWAdani Noida Project 1operational, counted35 MWNoida 2 — this recordunder construction, counts 022 MWCtrlS Noidacounted8 MWTwenty-two megawatts under construction is a material share of a market where the counted base is 326 MW — and it contributes nothing to the count until it opens.
Figure 1Counted Noida capacity by record, with this building in red. It is larger than the whole of CtrlS Noida and more than a third of Adani’s operational building.
What 22 MW changes
MeasureFigureReads as
Counted Noida market326 MWevery operator, every record
This building22 MW6.7% of the market in one delivery
STT’s counted share today0 MWthe operator is invisible in the count
STT’s share once both buildings open45 MW13.8% of the market, from a standing start
Mumbai city portfolio, for scale14 MWsmaller than this one building

Two STT buildings opening in Noida would give the company nearly 14% of the counted market from nothing. That is the shape of the Indian market: a single delivery cycle reorders the league table.

It also means the counted number is a lagging indicator by construction. The buildings that will define 2028 supply are already designed and mostly already funded, and none of them are in the count.

3What an undated pipeline does to pricing

An undated 22 MW is not neutral information. It changes behaviour even before it changes supply.

Two responses to the same announcement
PlayerReading of an undated 22 MWBehaviour
Incumbent operatorsfuture supply is coming, so do not over-commit on pricesofter renewals, shorter terms
Large tenantswait, or sign early at today’s price with an expansion optionsplit behaviour, which is why dates matter
Investorspipeline is real, so the platform is worth morecapital keeps flowing in
New entrantsthe market is filling, so differentiate on densityAI-ready positioning

Because the date is unpublished, every player guesses differently, and the guesses do not cancel out. That is exactly the asymmetry this registry exists to remove — except here the operator has not published the fact that would remove it.

The practical advice for a tenant negotiating in Noida now: ask the incumbent to price a 2028 expansion before you sign, and treat an undated 22 MW as already committed.

4Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
The delivery date for a 22 MW building that will move Noida pricing when it lands
Who holds the answer
STT GDC India commercial team; the Noida authority for construction approvals
The one question
When does Noida 2 deliver, and is any of the 22 MW pre-let
Why they will answer it
A tenant choosing between Noida operators is asking exactly this question already
Gridvik estimate
Delivery in 2027 with a pre-let anchor. Labelled an estimate
What changes it
A construction start, a handover date, or an anchor-tenant announcement
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

5Limits and open questions

  • No dates of any kind. The defining absence in this record.
  • No basis, racks, floor area or PUE. Density cannot be computed.
  • No construction detail. "Under construction" covers everything from site clearance to fit-out.
  • Cannot be reconciled into its own headline. The three Noida cards overshoot the 63 MW portfolio figure by 4 MW.
  • Single source. No directory corroborates the 22 MW.
  • What would close it. A delivery date. One date turns this record from a risk into supply.

6Sources

Sources: STT GDC India Noida city page, STT GDC India facility pages for Noida, STT GDC India corporate site, and Indian market commentary on the Noida and Greater Noida data centre market.