Facility record · Verified 26 Oct 2026

STT GDC Pune 5 — MaharashtraSTT GDC India · Pune · 24 MW, largest of five cards, expansion pair larger than the current footprint

Record PRJ-128Maharashtra — PuneTier C — single operator source4 public sources checkedAdditive: unknown — counts 0 MW
Largest Pune cardExpansion exceeds the footprintNo dateFacility
24MW
Card capacity
60%
Of the 40 MW headline
42MW
The expansion pair
105%
Of the current footprint
30%
Of the 81 MW card sum
0
Dates published

STT GDC Pune 5 is 24 MW, the largest of the five Pune cards and 60% of the operator’s entire current Pune IT headline in a single building. With Pune 4 at 18 MW, the expansion pair totals 42 MW — 105% of the 40 MW the company currently claims. Pune does not double under this pipeline. It more than doubles. No stage, no delivery date, no rack count and no PUE is published for the building that will decide whether Pune’s supply crunch ends or deepens.

1At a glance

Operator
STT GDC India
Facility
Pune 5, Maharashtra
Capacity
24 MW, basis unresolved
Position
Largest of five Pune cards, 30% of the 81 MW card sum
Against the headline
60% of the 40 MW current figure
The expansion pair
With Pune 4 at 18 MW, totals 42 MW — more than the current footprint
Stage
Unverified. No date, no construction evidence
Additivity
Unknown. Counted at 0 MW

2The expansion is bigger than the footprint

The arithmetic of this portfolio is unusual and worth stating plainly: the growth is larger than the base.

Pune 4 and 5 — the expansion pair18 + 24 MW42 MWThe 40 MW current headlinethree facilities40 MWPune 5 — this record60% of the headline on its own24 MWPune 1the smallest card9 MWThe two expansion buildings total 42 MW against a 40 MW current footprint. Pune does not double — it more than doubles.
Figure 1The expansion pair against the current footprint. Red is the pair this record belongs to. It is the first time in this registry that a pipeline exceeds the capacity it is expanding.
Pune, in four numbers
MeasureMWReads as
Current footprint, per the headline40three facilities, operating and expanding
This building2460% of that, in one asset
Expansion pair42105% of the current footprint
All five cards81roughly double the current claim
IT support capacity140three and a half times the current claim
Sanctioned power200 MVAenough apparent power for the whole build-out

A pipeline that exceeds its base is what a market in transition looks like on paper. The operators are not adding incremental halls to a mature estate; they are replacing the estate.

The constraint is not land or power — the 200 MVA sanction and 140 MW support capacity are already in place. It is demand and capital, and neither is visible in public data.

3What a 24 MW building means in Pune

Pune is not Mumbai. A 24 MW building is a large share of a small market, which is a different commercial situation.

24 MW against the Pune market
MeasureFigureReads as
Counted Pune market today51.5 MWtwo operators with real records
This building24 MW47% of the counted market
With Pune 4 and 542 MWSTT alone would be 45% of a 93.5 MW market
Nxtra Pune, the incumbent49.5 MWthe only comparable operator
Density at 8 kW a rack3,000 racksa mid-size hyperscale hall
Floor area at 100 W a sq ftabout 240,000 sq fta substantial single building

Forty-seven per cent of the counted market in one building is a concentration that would make a Pune tenant nervous and a competitor strategic. It is also the kind of number that gets built sooner rather than later if there is an anchor tenant behind it.

Which is the fact nobody has published: whether Pune 5 has a tenant. A 24 MW building without an anchor is a speculative build; with one, it is a delivery schedule.

4Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
The anchor-tenant question and the delivery date for the largest building in the Pune pipeline
Who holds the answer
STT GDC India commercial team; KKR and Singtel transaction documents for the asset schedule
The one question
Is Pune 5 pre-let, and when does it deliver
Why they will answer it
Twenty-four megawatts is not built on speculation in a city this size, so an anchor almost certainly exists
Gridvik estimate
An anchor tenant is committed and the building delivers in 2028. Labelled an estimate
What changes it
A tenant announcement, a construction start, or a delivery date
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

5Limits and open questions

  • No date or stage. The largest building in the pipeline is undated.
  • No basis, racks, floor area or PUE.
  • The expansion role is inferred from the reconciliation on PRJ-123.
  • No anchor tenant disclosed, and at this size one is very likely.
  • Support capacity of 140 MW implies more buildings than the five cards, which the page does not name.
  • What would close it. A delivery date and a tenant. Either one makes this the defining record of the Pune market.

6Sources

Sources: STT GDC India Pune city page, STT GDC India facility pages for Pune, STT GDC India corporate site, Nxtra Pune material for the market comparison, Data Center Dynamics on the KKR and Singtel acquisition, and Indian market commentary on Pune data centre demand.