Facility record · Verified 26 Oct 2026

STT GDC Chennai 4 — Tamil NaduSTT GDC India · Chennai · 17 MW under construction, larger half of a 32 MW pipeline

Record PRJ-142Tamil Nadu — ChennaiTier C — stage stated, dates absent4 public sources checkedAdditive: no — inside the 68 MW portfolio
Under constructionNo handover dateFacility17 MW
17MW
IT capacity
32MW
The Chennai pipeline
5.7×
Chennai 1’s operating capacity
25%
Of the 68 MW headline
2,125
Racks at 8 kW, bracketed
0
Handover dates

STT GDC Chennai 4 is 17 MW under construction — the larger of the two pipeline buildings, and 5.7 times the entire operating capacity of Chennai 1. With Chennai 3 at 15 MW it makes a 32 MW pipeline against a 29 MW operating business, which is the answer to Chennai’s supply shortage. It is also 25% of the 68 MW city headline. No handover date, rack count, floor area or PUE is published, so the answer exists and its timing does not.

1At a glance

Operator
STT GDC India
Facility
Chennai 4, Tamil Nadu
Capacity
17 MW of IT capacity
Stage
Under construction — stated
Part of
A 32 MW Chennai pipeline with Chennai 3, against 29 MW operating
Against Chennai 1
5.7 times its operating capacity
Programme
Part of a multi-campus Chennai expansion announced at ₹4,200 crore
Racks, floor area, PUE, dates
None published
Additivity
Not additive. Counted at 0 MW

2The larger half of the answer

Chennai’s shortage has one obvious solution under construction, and this building is the bigger part of it.

Chennai 4 — this recordthe larger of the pair17 MWChennai 3its sibling15 MWChennai 1the smallest operating site3 MWSeventeen megawatts is more than five times the entire operating capacity of Chennai 1, and it is being built next to a market that cannot supply enough today.
Figure 1The two pipeline buildings and the smallest operating site, for scale. Red is this record.
The pair, in context
MeasureMWReads as
Chennai 315the first pipeline building
Chennai 417the larger of the two
Pipeline total32110% of the operating base
Operating today29Chennai 1 and 2
If both land61STT’s Chennai business more than doubles
Headline today68already includes all of it

That last line is the whole STT pattern in one table. The company’s published Chennai figure already assumes these buildings exist. If they land, the headline becomes true. If they do not, the headline was never capacity.

For the market the arithmetic is straightforward: 32 MW arriving roughly doubles one operator’s presence and adds about 10% to Tamil Nadu’s counted capacity. That is enough to move rents in a market this tight, and it is entirely dependent on a date no one has published.

3Two buildings, one programme

Chennai 3 and 4 are being built as a pair under a single ₹4,200 crore multi-campus announcement.

What the programme implies
ReadingCost per megawattPlausible?
The ₹4,200 crore is for these two buildings only₹131 crore a MWno — four times the Indian range
It funds a broader multi-campus programmearound ₹42 crore a MW at 100 MWyes — at the top of the market range
It includes land and power infrastructureunquantifiable from public materiallikely, and it is why the ratio does not divide

The lesson is procedural rather than financial: programme announcements and building cards are different data, and dividing one by the other produces a number that looks like diligence and is not. Indian build costs cluster between ₹30 and ₹45 crore a megawatt; anything far outside that is a scope mismatch, not a discovery.

Two buildings, one programme, no schedule. That is the state of the Chennai pipeline, and it is why this registry reports both figures and refuses to average them.

4Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
Forward capacity in the larger half of the Chennai pipeline, before it is let
Who holds the answer
STT GDC India commercial team for Tamil Nadu
The one question
When does Chennai 4 hand over, and is it behind Chennai 3 in the sequence
Why they will answer it
Chennai is pre-let years ahead, and the second building’s tenants are being signed now
Gridvik estimate
Chennai 4 delivers in 2028, a year behind Chennai 3. Labelled an estimate
What changes it
A handover sequence, a pre-let announcement, or a construction milestone
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

5Limits and open questions

  • No handover date. The defining absence, shared with Chennai 3.
  • No racks, floor area or PUE.
  • No indication which building delivers first. The numbering suggests Chennai 3, but nothing states it.
  • Programme investment is unscoped and cannot be attributed to this building.
  • Counted at zero, correctly.
  • What would close it. A handover sequence for the pair. One line would let every tenant in Chennai plan.

6Sources

Sources: STT GDC India Chennai city page, STT GDC India Chennai multi-campus expansion announcement, STT GDC India facility pages for Chennai, STT GDC India corporate site, and Indian market commentary on Chennai data centre supply and rents.