Facility record · Verified 26 Oct 2026

STT GDC Chennai 7 — Siruseri, Tamil NaduSTT GDC India · Siruseri · 7.2 MW Phase 1, operational 19 Feb 2026, inside two portfolios

Record PRJ-143Tamil Nadu — SiruseriTier B — operational, dated5 public sources checkedAdditive: no — inside the 45 MW Siruseri campus
Operational 19 Feb 2026AI-ready, per the operatorCounted in two structuresFacility
7.2MW
Phase 1 IT capacity
45MW
Siruseri campus total
16%
Of the campus
10.6%
Of the Chennai city headline
2026-02-19
E-inaugurated
2
Portfolios it appears in

STT GDC Chennai 7 is 7.2 MW and it is Siruseri Phase 1 — the building the Tamil Nadu chief minister e-inaugurated on 19 February 2026 as an AI-ready facility. It is operational. It is also, in the company’s own published structure, inside two portfolios at once: it is the first phase of the 45 MW Siruseri campus, and it is simultaneously counted inside the 68 MW Chennai city headline. Its parent record in this registry is the campus, correctly. That makes this building, at 7.2 MW, the single clearest example in the file of how published structures permit double counting.

1At a glance

Operator
STT GDC India
Facility
Chennai 7, Siruseri — the fourth Chennai data centre
Capacity
7.2 MW of IT capacity in Phase 1
Situation
Operational, e-inaugurated by the Tamil Nadu chief minister on 19 February 2026
Parent record
The 45 MW Siruseri campus — this building is Phase 1 of it, and is inside that 45
Second appearance
Also counted inside the 68 MW Chennai city headline, which only closes with it
Position
16% of the campus, 10.6% of the city headline
Investment
Part of a ₹4,200 crore Tamil Nadu memorandum of understanding
Additivity
Not additive against the campus. Counted at 0 MW

2One building, two parents

This is the only record in the Indian estate that appears inside two published aggregates at once.

Siruseri campus45 MW total IT capacitycontains Chennai 7Chennai city headline68 MW claimed for the cityalso contains Chennai 7Chennai 7 — this recordPhase 1, operational since Feb 20267.2 MW in bothSeven point two megawatts counted twice, in two published structures, fifty kilometres apart.
Figure 1The two structures that both claim this building, and the 7.2 MW itself. Red is the figure that appears in each.
Where 7.2 MW appears
StructurePublishedThis building’s roleIf you add both
Siruseri campus45 MW ITPhase 1, inside the 45—
Chennai city portfolio68 MW ITone of five cards, needed to close the 68—
Both together113 MWcounted twice7.2 MW over
What an analyst would conclude113 MW of STT Chennai capacity—wrong by 6%

The error is small in absolute terms and structural in kind. It is not that 7.2 MW matters to a Chennai decision. It is that two pages of the same website, on the same day, describe the same building in two different portfolios — and one of them calls it "Chennai city" when it sits at Siruseri.

The registry keeps this record under the campus, which is the defensible choice: a building is a phase of a campus before it is a card in a city headline.

The rule that resolves it

A building belongs to one parent. Where an operator publishes two overlapping aggregates, the building counts against the lower-level one and the higher-level one is treated as a ceiling — never the other way round.

Applied across this file, that single rule also fixes West Bengal, Maharashtra and Karnataka.

3The distance problem

Siruseri is not Chennai city. It is a suburban industrial township on the southern edge of the metropolitan area, roughly fifty kilometres from the central business district.

Two very different products
Chennai citySiruseri
Distance from the CBDminutes50 km
Latency profilethe reason city sites exista suburban campus profile
Customerbanks, brokers, latency-sensitive enterprisehyperscale and AI tenants who need land and power
Land costthe highest in the southindustrial park rates
Building typesmall legacy floorsAI-ready new build, 45 MW campus
Recorded aspart of the 68 MW city headlinePRJ-019, a separate campus

Counting a Siruseri building inside a Chennai city figure is not a rounding choice. It merges two products that serve different customers at different distances and different prices.

The practical consequence: if a tenant asks what STT has in Chennai city, the answer is Chennai 1 and Chennai 2 at 29 MW. The Siruseri campus is a separate proposition, and it is the one with room to grow.

4What a roll-up gets wrong

Anyone building a Tamil Nadu total from operator pages will hit this building twice. Here is the arithmetic of the mistake.

Four ways to add up STT Tamil Nadu
MethodTotalVerdict
Chennai city headline plus Siruseri campus113 MWdouble counts 7.2 MW
Chennai cards plus Siruseri campus106 MWsame double count, from the cards
Chennai city headline only68 MWthe operator’s own figure, and it already includes Siruseri Phase 1
Chennai 1 and 2 plus Siruseri campus74 MWthe only clean total: operating Chennai plus the whole campus

Seventy-four megawatts is the number that holds. It is 29 MW of operating city capacity plus the 45 MW Siruseri campus, with the Phase 1 building counted once because it lives inside the campus.

Everything else on that table is defensible-sounding and wrong. Which is the argument for registry-level structure rather than page-level sums: the only way to avoid this is to know which building belongs to which parent, and no operator publishes that as a table.

5Timeline

  • Tamil Nadu announces a ₹4,200 crore multi-campus STT expansion and the Siruseri campus
  • Siruseri Phase 1 at 7.2 MW is e-inaugurated by the state chief minister as an AI-ready facility
  • The same 7.2 MW appears as Chennai 7 inside the Chennai city headline of 68 MW
  • Carried as an operational building under the Siruseri campus, and recorded as the closing card of the Chennai headline

6Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
AI-ready capacity at Siruseri, which is the only new STT build in Tamil Nadu that is actually running
Who holds the answer
STT GDC India commercial team for Tamil Nadu
The one question
How much of the 7.2 MW is let, and what is the next phase at Siruseri
Why they will answer it
An AI-ready building that opened in February is being actively marketed, unlike the rest of the estate
Gridvik estimate
Phase 1 is partially let and the campus will build out in phases toward 45 MW. Labelled an estimate
What changes it
An occupancy figure, a design density, or the next phase date
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

7Limits and open questions

  • Double counted in the operator’s own structure. The central defect this page documents.
  • No rack count or PUE, despite being the newest AI-ready building in the estate.
  • No occupancy or tenant published for a building opened eight months ago.
  • "AI-ready" is an operator claim with no published density or cooling specification behind it.
  • No date for the remaining 37.8 MW of the campus.
  • What would close it. A design density and an occupancy figure. This is the most marketable building in the estate and the least specified.

8Sources

Sources: STT GDC India newsroom on the Chennai multi-campus expansion and the ₹4,200 crore Tamil Nadu memorandum, STT GDC India Chennai city page, STT GDC India facility pages for Siruseri and Chennai, STT GDC India corporate site, and Indian market commentary on the Siruseri and southern Chennai data centre corridor.