Facility record · Verified 26 Oct 2026

STT GDC Delhi 1 — DelhiSTT GDC India · Delhi · 0.9 MW, smallest building in the Indian estate

Record PRJ-145Delhi — national capital territoryTier C — single operator source4 public sources checkedAdditive: no — inside the 12 MW portfolio
Smallest in the estateNo stageFacility0.9 MW
0.9MW
Card capacity
900kW
In kilowatts
2.5%
Of the Delhi portfolio
11×
Smaller than Delhi 3
0MW
Counted in Delhi
0
Racks published

STT GDC Delhi 1 is 0.9 MW — nine hundred kilowatts. It is the smallest data centre building STT publishes anywhere in India, and one of five records under a megawatt in this registry. It is 2.5% of a 12 MW Delhi portfolio and 11 times smaller than Delhi 3, the same operator’s 10 MW building in the same city. And the whole Delhi portfolio is counted at zero, so this building is larger than the entire counted capacity of India’s capital. No stage, rack count, floor area or PUE is published.

1At a glance

Operator
STT GDC India
Facility
Delhi 1, national capital territory
Capacity
0.9 MW — 900 kilowatts
Rank
Smallest of roughly thirty STT buildings in India, and one of five records under a megawatt in this registry
Share of portfolio
2.5% of the 12 MW Delhi figure
Against its sibling
11 times smaller than Delhi 3 at 10 MW
Implied size
roughly 75 to 180 cabinets
Stage
Unverified. No stage, racks or PUE published
Additivity
Not additive. Counted at 0 MW

2What nine hundred kilowatts is

Nine hundred kilowatts is a data hall in a building, not a data centre. In Delhi, that may be exactly the right thing to own.

Delhi 3the workhorse10 MWDelhi 2a suite1 MWDelhi 1 — this recordsmallest in the estate0.9 MWCounted in Delhiall non-additive0 MWNine hundred kilowatts is the smallest STT building in India and larger than everything this registry counts in Delhi.
Figure 1The three Delhi cards and the counted state total. Red is this record. Pale is what the registry counts for the entire territory.
Bracketing 0.9 MW
Assumed densityCabinetsWhat it serves
5 kW a rack180a small enterprise floor
8 kW a rack112one contained aisle
12 kW a rack75a single dense row

In most markets a 900 kW site would be a rounding error. In Delhi it is a strategic asset, because it is essentially impossible to build a new data centre inside the territory. Land costs, construction restrictions and water constraints have pushed all new capacity across the state line into Noida and Greater Noida.

So this building’s value is not its megawatts. It is its address, its existing power connection and its grandfathering. Demolishing it would destroy something that could not be rebuilt.

3The smallest tier of the estate

Five records in this registry sit under one megawatt. Two of them are STT, and both are in Delhi and Bengaluru.

The sub-megawatt set
RecordMWCityWhy it survives
STT Delhi 10.9Delhian address inside a city that cannot be built in
STT Bengaluru 10.6Bengalurua legacy suite, possibly holding connectivity
CtrlS Patna Edge DC 10.5Patnathe first edge site in Bihar
Sify Vashi0.38Mumbaia legacy node in the original corridor
NTT Mumbai BSE0.3Mumbaiexchange-adjacent, where latency is the product

Four of the five survive because they hold something that cannot be moved — a location, a fibre route, or an exchange proximity. Only Bengaluru might be genuinely redundant.

That is the correct test for a sub-megawatt record: does it hold a position, or is it just small? Four hold positions. It is worth asking the operators about the fifth.

4Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
Whether a 900 kW floor inside Delhi comes up at all, and what it would cost relative to Noida
Who holds the answer
STT GDC India north India sales
The one question
Is Delhi 1 occupied, and would the operator ever release it
Why they will answer it
Delhi city capacity is irreplaceable and a tenant inside the territory will pay for it
Gridvik estimate
The site is single-tenant and held for a specific customer. Labelled an estimate
What changes it
An occupancy statement, a rack count, or a renewal date
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

5Limits and open questions

  • No stage, racks, floor area or PUE. Nothing but a capacity.
  • Counted at zero along with the rest of Delhi.
  • Whether it holds a position or is simply small cannot be determined from public material.
  • Basis unresolved — 0.9 MW is not labelled IT or gross.
  • Single source. No directory lists a 0.9 MW STT Delhi site separately.
  • What would close it. One line from the operator. This is the cheapest record in the estate to complete.

6Sources

Sources: STT GDC India Delhi city page, STT GDC India facility pages for Delhi, STT GDC India corporate site, and Indian market commentary on Delhi data centre constraints and the Noida alternative.