Facility record · Verified 26 Oct 2026

STT GDC Jaipur 1 — RajasthanSTT GDC India · Jaipur · 6 MW IT load, ready for service 3 June 2026

Record PRJ-149Rajasthan — JaipurTier A — dated and specified4 public sources checkedAdditive: yes — 6 MW counted
Ready for service 3 Jun 2026IT load statedCounted in fullThe template record
6MW
IT load
2026-06-03
Ready for service
6MW
The whole Rajasthan market
2
Counted STT records
1
STT records with a date
0
Caveats

STT GDC Jaipur 1 is 6 MW of IT load, ready for service from 3 June 2026. Capacity, basis, status and date — four things that almost no other record in this file has, published together. This is the best-specified data centre record in the registry, and it is one of only two STT records anywhere that counts. It is also the entirety of the Rajasthan data centre market in this file: one building, six megawatts. Every other STT page in this run needed a caveat. This one does not, and that contrast is the point.

1At a glance

Operator
STT GDC India
Facility
Jaipur 1, Rajasthan
Capacity
6 MW of IT load — basis stated
Status
Ready for service from 3 June 2026
Counted
6 MW — the entirety of Rajasthan’s counted capacity in this registry
Position in the estate
One of two counted STT records, alongside Ahmedabad 1 at 4 MW
Announcement
3 June 2026
Racks, floor area, PUE
Not published
Additivity
Additive. 6 MW counted in this registry

2Four facts, published together

The standard this registry has been asking for across thirty pages, met in one record.

Published capacity6 MW IT load, stated basis6 MWStatusready for service, dated3 Jun 2026Counted in the registrythe whole of Rajasthan6 MWCapacity, basis, status and date — four things almost no other record in this file has. Jaipur is the template.
Figure 1Everything this record publishes, and what it contributes to the total. Red is the counted figure. There is nothing to caveat.
The four facts, and how rare they are
FactJaipur 1Most STT records in this file
Capacity6 MWa number, usually unlabelled
BasisIT load, statedunstated in the majority
Statusready for servicestage unverified across roughly twenty buildings
Date3 June 2026absent on almost every card
Countedyestwo records out of about thirty

Everything on the left of that table could be published for every building in the estate with no competitive cost. A capacity, a basis, a status and a date is not commercially sensitive — it is the minimum description of an asset.

The reason it matters is that these four facts are the difference between a directory and a dataset. Without them you have a list of names and numbers. With them you have a model that can be dated, compared and forecast from.

3A six megawatt market

Rajasthan has exactly one data centre record in this registry, and this is it.

Rajasthan, in full
RecordMWStatusCounted
STT GDC Jaipur 16ready for service 3 Jun 2026yes
Anything elsenothing——
State total6 MW—6 MW

Six megawatts is the smallest state total in the registry, and it is also the cleanest — because it is a single building with a published date, there is nothing to reconcile and nothing to dispute.

That is a useful lesson about data quality: the smallest markets are often the most reliable. A one-record state can be verified completely. A 242-record registry cannot, which is why the methodology matters more than the volume.

4Ready for service, not commissioned

The status word matters, and the operator chose it precisely.

What ready for service means
StatusWhat it assertsWhat it does not assert
Ready for servicethe facility can accept a customer and provide servicethat any customer has taken capacity
Commissionedsystems tested and accepted by the operator or a third partycommercial availability
Operationalin servicethat it is full
Under constructionbeing builtanything about completion

"Ready for service" is the honest commercial milestone: the building works and can be sold, and nothing is claimed about occupancy. This registry records it as the operator’s stated milestone and does not infer a commissioning certificate behind it.

That distinction matters more than it sounds. A building that is ready for service could be entirely empty, and a building that is operational could be entirely full. Only the operator knows which, and only the operator can say.

5What this record proves

The contrast between this page and the thirty that preceded it is the argument for the whole product.

Two records, same operator, same registry
STT Mumbai portfolioSTT Jaipur 1
Published capacity133 MW6 MW
Basis statednoyes
Status statednoyes
Date publishednoyes
Counted0 MW6 MW
Pages needed to explain iteightone

A 6 MW building with four published facts counts in full. A 133 MW portfolio with none of them counts for nothing. That is not a coincidence — it is the rule working exactly as designed, applied to a company that is inconsistent about disclosure.

The lesson for the operator is that publishing more would make them countable. The lesson for the buyer is that the records which look small are often the ones you can actually rely on.

The template

Capacity, basis, status, date — four fields. Every building in India could carry all four, and the first operator to do it becomes the reference dataset.

Jaipur shows it costs nothing to publish. It is the single most quotable record in this registry.

6Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
Six megawatts of brand-new capacity in a state with no competition and a supportive industrial policy
Who holds the answer
STT GDC India north and west region sales
The one question
How much of the 6 MW is free, and what is the design density
Why they will answer it
A building ready for service in June 2026 is being actively marketed right now
Gridvik estimate
The building is new, lightly let and pricing aggressively to fill. Labelled an estimate
What changes it
An occupancy figure, a rack count, or a PUE
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

7Limits and open questions

  • No racks, floor area or PUE. Even the best-specified record in the file stops short of density.
  • No occupancy. Ready for service says nothing about how full it is.
  • Single source, though the date makes it verifiable.
  • Rajasthan has no second record, so a state total of 6 MW is one operator’s one building. That is accurate and also fragile — if the building is withdrawn, the state has no data centre record left.
  • What would close it. A rack count and a PUE. Two figures and this becomes a complete facility record, not just a complete disclosure.

8Sources