Facility record · Verified 26 Oct 2026

NTT Mumbai 5 — Chandivali, MaharashtraNTT Global Data Centers · Chandivali, Mumbai · 12.5 MW critical IT load, operational

Record PRJ-150Maharashtra — MumbaiTier A — dated and specified5 public sources checkedAdditive: yes — 12.5 MW counted
IT load statedOperationalCounted in fullNo aggregate to hide behind
12.5MW
Critical IT load
161MW
NTT Mumbai, counted
8
Additive NTT Mumbai records
0MW
STT Mumbai, counted
133MW
STT Mumbai, published
1
Portfolio aggregates in NTT Mumbai

NTT Mumbai 5 in Chandivali is 12.5 MW of critical IT load, operational, and it counts in full. It is one of eight NTT Mumbai records in this registry that do, totalling 161 MW — every one of them IT load stated, stage stated and dated. In the same city, STT publishes 133 MW and counts zero, because every STT record sits inside a portfolio aggregate. Two operators, one market, and a 161 to 133 difference in published capacity that becomes a 161 to nothing difference in the registry. NTT is what the disclosure standard looks like when it is actually followed.

1At a glance

Operator
NTT Global Data Centers — NTT DATA, formerly Netmagic
Facility
Mumbai 5, Chandivali, Mumbai
Capacity
12.5 MW critical IT load — basis stated as IT, not facility
Stage
Operational — live services listed on the operator page
Counted
12.5 MW — additive, no parent aggregate
NTT Mumbai total
161 MW across 8 additive records
Company in India
Over 400 MW across roughly 30 facilities in 10 cities, per the operator
Racks, floor area, PUE
Not published for this building
Additivity
Additive. 12.5 MW counted in this registry

2Two ways to publish the same city

This is the comparison the whole registry has been building toward, and it happens entirely inside Mumbai.

NTT Mumbai, counted8 additive records, all IT load stated161 MW countedSTT GDC Mumbai, counted6 non-additive records0 MW countedSTT GDC Mumbai, publishedone 133 MW portfolio headline133 MW publishedTwo operators, one city, one hundred and thirty-three and one hundred and sixty-one megawatts. One is in the total. One is not.
Figure 1NTT counted, STT counted, and STT published. Navy is in the registry total. Pale is not. Red is what the market quotes.
NTT against STT, in one city
NTT MumbaiSTT GDC Mumbai
Published capacity161 MW133 MW
Records in this registry86
Basis statedcritical IT load, every recordpower capacity, unlabelled
Stage statedoperational, every recordstage unverified, every record
Portfolio aggregate flagnone — each building stands alonenon-additive, and every child too
Counted in the state total161 MW0 MW

The capacity figures are close: 161 against 133. Everything else is opposite. NTT publishes eight buildings and lets each one stand. STT publishes a portfolio and files every building underneath it.

The registry does exactly what it was told to do. It counts facilities and refuses to count aggregates. NTT looks like a 161 MW operator and STT looks like it has no Mumbai presence at all.

3Why NTT is countable

Nothing NTT does is heroic. It publishes four facts per building, which is the minimum for an asset to be usable as data.

The four facts, NTT against the field
FactNTT MumbaiCtrlS MumbaiSTT Mumbai
Capacity per buildingyesyesyes
Basis stated (IT or facility)IT, explicitunlabelledunlabelled
Stage statedoperationalunverifiedunverified
Facility vs facility power separatedyes where both existnono
Portfolio aggregate that swallows itnonethe 700 MW campus claimthe city headline

The fourth and fifth rows are what make the difference. NTT separates IT load from total facility load where both are known — Mumbai 7 is 25.6 MW of IT in a 38 MW facility — which is the single most useful disclosure an operator can make, because it gives you the PUE.

And NTT does not publish a city portfolio that its buildings sit inside. There is no 161 MW headline for Mumbai. There are eight buildings, and a reader adds them up if they want to.

The standard this sets

Four facts per building, no aggregate overhead. That is all it takes to be countable.

Two operators in this file do it: NTT and, for one building, STT Jaipur. Everyone else publishes a portfolio and disappears from the totals.

4The eight NTT Mumbai buildings

Mumbai 5–9 plus three small exchange sites make up the NTT Mumbai count. This is what a properly itemised metro portfolio looks like.

NTT Mumbai, record by record
RecordMWBasisLocation
Mumbai 512.5critical IT loadChandivali
Mumbai 619.2critical IT loadAndheri East
Mumbai 725.6critical IT load in a 38 MW facilityChandivali
Mumbai 836facility capacity, 2,800 racksChandivali
Mumbai 962facility capacity, 6,000 racksChandivali
BSE Data Center0.3critical IT load, 1 MW facilityFort
Vikhroli2.4critical IT load, 6 MVA facilityVikhroli
Vikhroli IV3critical IT load, 4 MVA facilityVikhroli
Total counted161——

Note the basis column. Three different bases appear — critical IT load, facility capacity, and a mix — and each is stated. That is not perfect consistency, but it is honest: a reader knows which figure they have and can decide whether to compare it.

It is also why Mumbai 8 and 9 cannot be compared directly with Mumbai 5, 6 and 7. They are facility figures, and at a typical PUE they represent materially less IT load. The distinction is published rather than hidden, which is the whole point.

5What this proves

NTT is the existence proof that the disclosure problem is a choice rather than a constraint.

Three objections an operator might raise, and NTT’s answer
ObjectionNTT’s position
Publishing capacity per building is commercially sensitiveeight buildings published, per building, all operational
IT load and facility load are hard to separateboth published where both are known, including 25.6 in 38
Customers do not want their facility identifiablethe capacity is published; the customers are not
A portfolio headline is simpler for buyersthere is no portfolio headline — the buildings are the message

None of what NTT publishes compromises a customer or reveals a price. It reveals what the asset is, which is what anyone buying, financing or regulating a data centre needs to know.

The commercial consequence is direct: NTT appears in every state total, every market share calculation and every density comparison this registry produces. STT appears in none of them. A buyer using this file would conclude NTT is the larger Mumbai operator, and on published capacity it is not by much — 161 against 133.

6Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
Twelve and a half megawatts of stated IT load in Chandivali, inside a market where the biggest publisher counts nothing
Who holds the answer
NTT Global Data Centers India commercial team
The one question
What is the rack count and design density in Mumbai 5, and how much capacity is free
Why they will answer it
NTT is a serial discloser and answers specification questions as a matter of course
Gridvik estimate
The building is operating and substantially let. Labelled an estimate
What changes it
A rack count, a PUE, or an occupancy statement
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

7Limits and open questions

  • No rack count or floor area for this building, though other NTT records publish racks.
  • No PUE stated, though it is derivable for Mumbai 7 from the IT and facility pair.
  • No commissioning date on the card for Mumbai 5.
  • Basis varies across the eight records — IT for some, facility capacity for others.
  • No customer information, correctly.
  • What would close it. A rack count and a PUE. NTT publishes both for other sites, so this is a gap rather than a policy.

8Sources

Sources: NTT Global Data Centers Mumbai facility pages, NTT India corporate site, Data Center Dynamics reporting on the Mumbai 7 and Mumbai 8 launches, and Indian market commentary on the Mumbai data centre market.