Facility record · Verified 26 Oct 2026

NTT Mumbai Vikhroli IV — Vikhroli West, MaharashtraNTT Global Data Centers · Godrej and Boyce Industry Estate, Vikhroli West · 3 MW critical IT load · 4 MVA facility load

Record PRJ-157Maharashtra — Vikhroli WestTier A — operator-stated4 public sources checkedAdditive: yes — 3 MW counted
IT load statedMVA, not MWThree conflicting ratios3 to 6 kVA per rackCounted in full
3MW
Critical IT load
4MVA
Total facility load
10MVA
Third-party listing
1.20–3.00
Implied ratio range
3–6kVA
Per rack, stated
3.4%
Of NTT Mumbai's 161 MW

NTT's Vikhroli IV data centre carries 3 MW of critical IT load and 4 MVA of total facility load, with 3 to 6 kVA per rack, on the Godrej and Boyce Industry Estate in Vikhroli West. It sits about a kilometre from Vikhroli, the other 2012-vintage NTT site, and the two together are 5.4 MW — 3.4% of what NTT counts in Mumbai. The published numbers do not agree with each other. Four megavolt-amperes behind three megawatts implies a ratio of 1.20 to 1.33, better than the operator’s own 1.48 hyperscale halls. A third-party listing puts total power at 10 MVA, which implies 3.00. Anywhere between 1.20 and 3.00 is possible, and the truth is probably 2.4. The page publishes all of it and resolves none of it.

1At a glance

Operator
NTT Global Data Centers — NTT DATA, formerly Netmagic
Facility
Mumbai Vikhroli IV (VIK DC4), Godrej and Boyce Industry Estate, Vikhroli West
Capacity
3 MW critical IT load — operator-stated
Facility load
4 MVA — operator-stated, in MVA
Third-party figure
10 MVA total power — a directory listing, not the operator
Rack power
3 to 6 kVA per rack — identical specification to Vikhroli
Positioning
Disaster recovery and business continuity — the operator claims the highest levels in India
Implied ratio
1.20 to 3.00 depending on the read. Unresolved
Counted
Additive. 3 MW counted in this registry

2The pair that is 3.4% of Mumbai

Vikhroli and Vikhroli IV are two buildings on the same stretch of LBS Marg in Vikhroli West, about a kilometre apart, both operated by NTT, both small, both with the same 3 to 6 kVA rack specification.

Chandivali, 5 buildingsMumbai 5, 6, 7, 8, 9155.3 MWVikhroli, two buildingsVIK DC2 and Vikhroli IV5.4 MWVikhroli IV3 MW critical IT load3 MWVikhroli2.4 MW critical IT load2.4 MWThe Vikhroli pair is 3.4% of what NTT counts in Mumbai. Both buildings are in Vikhroli West, on the same stretch of LBS Marg.
Figure 1One campus and one pair of buildings. Navy is five buildings of IT and facility load mixed. Red is two buildings of critical IT load.

Five point four megawatts across two buildings, against 155.3 across the Chandivali five. The pair exists for a reason that has nothing to do with capacity: it gives NTT a second Vikhroli site for recovery, on a different estate, inside the same city and away from the Chandivali campus.

The two Vikhroli buildings side by side
MeasureVikhroli (VIK DC2)Vikhroli IV (VIK DC4)
Critical IT load2.4 MW3 MW
Facility load, operator6 MVA4 MVA
Facility load, third partynot listed10 MVA
Rack power3 to 6 kVA3 to 6 kVA
EstateMehra Industrial EstateGodrej and Boyce Industry Estate
Positioninggeneral colocation, built 2012disaster recovery and continuity
Counted here2.4 MW3 MW
The pair is the product

Neither building can be sold on density or efficiency. Together they can be sold on something no hyperscale campus in Navi Mumbai offers: two separate Mumbai-city buildings, under one operator, for recovery.

That is 5.4 MW of edge product carrying 3.4% of a 161 MW book — and it is the only part of NTT’s Mumbai estate that is genuinely scarce.

3Four numbers, three ratios

Vikhroli IV is the clearest example in this registry of a record where the published numbers cannot all be describing the same thing.

Listed 10 MVAthird-party total power figure300%4 MVA per feedtwo feeds, about 7.2 MW240%4 MVA, naiveMVA treated as MW133%4 MVA at 0.9 pfabout 3.6 MW of facility load120%Facility load as a percentage of 3 MW of IT. The bottom two readings are physically implausible for a direct-expansion building, which is the point.
Figure 2Facility load as a percentage of 3 MW of IT. The bottom two bars describe a building more efficient than a hyperscale hall. For a direct-expansion site with 3 to 6 kVA racks, that is not credible.
Why the numbers do not close
ReadingRatioPlausible?Why
4 MVA at 0.9 pf = 3.6 MW1.20nobetter than NTT’s own new hyperscale halls, on a DX-cooled legacy site
4 MVA treated as 4 MW1.33nosame problem, slightly less extreme
4 MVA is a per-feed rating, dual feed2.40probably yesconsistent with the sister building at 2.25
10 MVA at 0.9 pf = 9 MW3.00possiblybut 10 MVA does not come from any operator statement

Two of these readings are effectively impossible. A 3 MW hall with direct expansion cooling and 3 to 6 kVA racks cannot run at 1.20, because the fixed plant alone is a larger multiple of that. So the 4 MVA figure is almost certainly not a site total — it is a per-path rating on a dual-feed design, which makes the real facility load about 8 MVA and the ratio about 2.4.

That is an inference, and this page labels it as one. The registry does not correct the operator’s figure. It counts the 3 MW of IT, publishes the 4 MVA as stated, shows the 10 MVA listing alongside it, and lets the reader see the gap.

What this costs if the lower reading were taken at face value

A tenant evaluating Vikhroli IV against Chandivali would conclude it is a third more efficient than a 2023 hyperscale hall, and price accordingly.

On the 2.40 reading it is 62% less efficient. The difference on 3 MW of IT is roughly Rs 12 crore a year at Rs 8 per kWh and 80% loading.

4The disaster recovery claim

NTT describes Vikhroli IV as offering the highest levels of disaster protection and recovery in India. That is a marketing statement, and there is no published standard behind it — not an Uptime Institute certification number, not a TIA-942 rating, not an audited RTO.

What is verifiable about the recovery case
AttributeWhat is publishedVerifiable?
Separate building from Vikhroliyes, different estate, about 1 kmyes
Separate power feeddual feed statedpartly
Geographic separation from Chandivaliabout 20 km, different part of Mumbaiyes
Certification levelnot published as a ratingno
Stated recovery time objectivenot publishedno
“Highest levels in India”operator marketing languageno

The defensible part of the claim is structural, and it is enough to sell on: two independent Mumbai-city buildings on two separate industrial estates, both inside the city rather than out in the Navi Mumbai belt. For financial-services tenants that must stay close to the Fort and BKC corridors, that is a real constraint and a real product.

The indefensible part is "highest levels in India". Nobody can check it, which is exactly why the operator says it.

5Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
Mumbai-city disaster recovery capacity at 3 to 6 kVA per cabinet, in a second building
Where the capacity is
Godrej and Boyce Industry Estate, Vikhroli West — with Vikhroli a kilometre away for a paired deployment
Who holds the answer
NTT Global Data Centers India commercial team
The one question
Is the 4 MVA a site total or a per-feed rating, and what recovery standard is actually certified
Why they will answer it
Recovery is the product here, and an unverifiable claim is a weak sales position against a tenant who asks
Gridvik estimate
About 500 to 1,000 cabinets at 3 to 6 kVA, with the 3 MW largely committed. Labelled an estimate
What changes it
A per-feed clarification, a certification number, or a stated RTO
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

6Limits and open questions

  • The four numbers on this page do not reconcile. 4 MVA and 10 MVA cannot both be the total facility load of a 3 MW building, and neither supports a credible ratio on its own.
  • The 2.40 ratio is an inference, from a per-feed reading of a dual-feed design. It is labelled as an inference, not a published figure.
  • "Highest levels of disaster recovery in India" is unverifiable and is treated here as marketing language, not data.
  • Rack count, floor area and PUE are all unpublished for this facility.
  • The 10 MVA figure comes from a directory listing with no operator confirmation.
  • No dated commissioning or occupancy evidence.
  • What would close it. A power factor, a per-feed clarification and a rack count. Three lines on a facility page would collapse this record from four ratings to one.

7Sources

Sources: NTT Mumbai Vikhroli IV facility page, NTT DATA global data center locations index, Inflect facility listing for NTT DC-4, and Datacenters.com facility listing.