Planned phase group · Verified 26 Oct 2026

NTT NAV1C and NAV1D — Mahape, Navi MumbaiNTT Global Data Centers · Mahape, Navi Mumbai · 40 MW combined planned IT load · stage unverified

Record PRJ-161Maharashtra — Navi MumbaiTier B — capacity clear, stage disputed5 public sources checkedAdditive: no — child of PRJ-158
Q2 FY23 target, expiredSplit into two buildingsSplit sums to 41.6, not 40One address confirmedChild of a campus aggregate
40MW
Announced combined IT
25.6MW
NAV1C, listed
16MW
NAV1D, listed
41.6MW
Sum of the listings
60MW
Facility at 1.5
0MW
Counted here

NAV1C and NAV1D were announced by NTT as a single combined phase of 40 MW of critical IT load at Mahape, with a Q2 FY23 target. That target expired three years ago and the operator has never restated it. Current construction listings have split the phase into two buildings: NAV1C at 25.6 MW, under construction, and NAV1D at 16 MW, planned. Those add to 41.6 MW — 1.6 MW more than the operator said the whole phase was. At NTT’s 1.5 ratio the phase carries 60 to 62.4 MW of facility load, which is 40% of the 150 MW campus plan. This is a thin record by public-data standards: a capacity, a schedule, one street address, and a discrepancy. That is what the page covers.

1At a glance

Operator
NTT Global Data Centers — NTT DATA, formerly Netmagic
Phase
NAV1C and NAV1D, Mahape, Navi Mumbai
Capacity as announced
40 MW combined critical IT load
Capacity as listed today
25.6 MW under construction, 16 MW planned — 41.6 MW
Schedule
Q2 FY23 — expired, never restated
Stage
NAV1C has construction evidence; NAV1D has none
Address
NAV1C listed at EL 234-238, TTC Industrial Area, Mahape
Facility load at 1.5
60 MW as announced, 62.4 MW as listed
Parent
PRJ-158, the 150 MW NAV1 campus plan
Counted
Non-additive. 0 MW counted in this registry

2The phase group that got split

NAV1’s first two buildings publish a critical IT load each. The second phase did not: NTT gave one number for two buildings and never divided it.

Combined, as announcedNAV1C and NAV1D together, Q2 FY23 target40 MWSum of current listings25.6 plus 16 MW41.6 MWNAV1C, construction listingEL 234-238, TTC Industrial Area25.6 MWNAV1D, planned listingno construction evidence16 MWCritical IT load. The combined figure has been split into two buildings by later listings, and the split is 1.6 MW larger than the sum NTT published.
Figure 1Critical IT load. The pale bar is what NTT published. Red is what the later listings add to. Navy and blue are the two buildings that produced it.
The phase, three ways
SourceWhat it statesSum
NTT facility pageNAV1C and NAV1D, 40 MW IT combined, Q2 FY2340.0 MW
Construction and planning listingsNAV1C 25.6 MW, NAV1D 16 MW41.6 MW
Difference1.6 MW, or 4% above the operator’s own total+1.6 MW

Sixteen tenths of a megawatt is small. What matters is that it exists at all, because it means the combined figure and the split figures were produced at different times by different routes. The registry keeps both, publishes the combined number where the operator gave one — as it did for NAV1C and NAV1D — and does not invent a resolution.

The one piece of hard evidence that this phase exists physically is an address. NAV1C is listed at EL 234-238, TTC Industrial Area, Mahape. That is more than any other unbuilt NTT phase in this file can offer.

Three years past the schedule

A Q2 FY23 target for 40 MW at one of India’s four largest data centre campuses has not been publicly restated.

Either it slipped and nobody said so, or it was delivered and nobody updated the page. The registry cannot tell which, and neither can a tenant.

3The module catalogue

The reason a thin record like this is still worth reading: NTT does not design every building from scratch. It repeats modules, and once you have two records of a module you can price a third before it exists.

Every NTT India building in this registry, by stated capacity
CapacityBuildingsTypeYear
0.3 MWBSE, Fortlegacy exchange site—
1.5 MWNoida 1 (DEL1)retrofit2011
2.4 MWVikhroli (VIK DC2)purpose built2012
3 MWVikhroli IV (VIK DC4)purpose built—
12.5 MWMumbai 5hyperscale—
19.2 MWMumbai 6, Andheri Easthyperscale—
22.4 MWNoida 2 Building Ahyperscale2024
25.6 MWMumbai 7, and NAV1Chyperscale2022 / building
30 MWNAV1Ahyperscale2022
30.4 MWNAV1B, and Noida 2 Building Bhyperscaleboth unverified
36 MW facilityMumbai 8hyperscale2023
62 MW facilityMumbai 9hyperscale2023

Two capacities appear twice, in two different cities: 25.6 MW at Mumbai 7 and NAV1C, and 30.4 MW at NAV1B and Noida 2 Building B. That is not coincidence. It is a building type.

The practical use is direct. Mumbai 7 is the one 25.6 MW building that publishes both an IT and a facility figure — 25.6 and 38 MW. That is how the registry can say NAV1C, at 25.6 MW, carries about 38.4 MW of facility load without anyone at NTT ever stating it.

4What this phase is worth

Two buildings at 41.6 MW of IT, inside a 150 MW campus plan, three years past schedule.

NAV1C and NAV1D against the campus
MeasureValueBasis
Announced IT load40 MWoperator, Q2 FY23 target
Listed IT load41.6 MW25.6 plus 16
Facility load at 1.560 to 62.4 MWderived from the house ratio
Share of the 150 MW campus40 to 42%60 or 62.4 of 150
Campus delivered or building without itabout 30%NAV1A plus NAV1B at 90.6 MW
Largest single building in the phase25.6 MW ITNAV1C, about 38.4 MW facility

Forty per cent of a 150 MW campus rests on a phase whose schedule has not been publicly restated since 2022. That is the same structural problem as NAV1B, one step further out in time — and it is the reason the NAV1 campus plan, which reconciles so neatly to 150 MW, is a plan and not a position.

The registry counts none of it. The building-level records for NAV1A and NAV1B carry the delivered capacity; the campus aggregate carries the plan; this record carries the gap between the two.

5Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
Nothing yet. This is a phase to track, not a phase to tender
Where the capacity is
Mahape, TTC Industrial Area — NAV1C has a confirmed street address
Who holds the answer
NTT Global Data Centers India commercial team
The one question
Is NAV1C commissioning, and does NAV1D have a construction start
Why they will answer it
The phase is 40% of the campus they announced in 2022 and the schedule is three years stale
Gridvik estimate
NAV1C at roughly 38.4 MW of facility load and about 6,000 cabinets at NTT’s standard density. Labelled an estimate on an unverified stage
What changes it
A commissioning date for NAV1C, or any construction evidence for NAV1D
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

6Limits and open questions

  • The 40 MW combined figure is the operator’s; the 25.6 and 16 MW split is from listings. Neither is adjudicated here.
  • Q2 FY23 is treated as stale. The registry will not call this phase live or under construction on the strength of a 2022 schedule.
  • NAV1C has a TIA directory address, which is evidence the site exists. It is not evidence the building is commissioned.
  • NAV1D has no construction evidence at all. It is carried as planned.
  • Facility load is derived at 1.5, a ratio proved by NAV1A and corroborated by Mumbai 7, not stated for these buildings.
  • No rack counts, no floor areas, no PUE for either building.
  • This is a short page on purpose. The public record is a capacity, a stale date, one address and a 1.6 MW discrepancy. Filling it with more would be invention.

7Sources

Sources: NTT Global Data Centers Navi Mumbai facility page, TIA facility directory listing for NAV1C, Datacentermap Navi Mumbai listings, Data Center Dynamics reporting on the NAV2 announcement which describes the pending NAV1 phases, and independent Mumbai market analysis.