Campus aggregate · Verified 26 Oct 2026

NTT NAV2, Airoli — Navi Mumbai, MaharashtraNTT Global Data Centers · Airoli and Dighe, Navi Mumbai · 500 MW facility power announced · 315 MW proposed · 43 MW operational

Record PRJ-162Maharashtra — Navi MumbaiTier A — rated and reported7 public sources checkedAdditive: no — aggregate, 0 MW counted
Aggregate, not additive500 announced vs 43 liveLender-verified numbersThree or thirteen buildings83 MW already leased
500MW
Facility power announced
315MW
Proposed, ICRA
107MW
Phase one
83MW
Leased
43MW
Operational, Aug 2025
₹51.4cr
Capex per MW

NTT announced NAV2 in March 2025 as 500 MW of facility power and 336 MW of IT capacity across three data centres — its largest campus in India. Seven months later a credit rating agency published what actually exists: a 54-acre site in Navi Mumbai, 107 MW of capacity in phase one spread across four data centres, a project cost of about ₹5,500 crore, 83 MW leased, 43 MW operational and 24 MW under construction, with 315 MW proposed overall. Every one of those numbers is defensible. They describe four different things: a plan, a phase, a contract book and a building site. The most useful pair on this page is 83 leased against 43 live — roughly half of everything NTT has signed at Airoli has not been delivered yet. The registry counts zero of it, because a campus aggregate is not a building.

1At a glance

Operator
NTT Global Data Centers — NTT DATA, via the NTT GDC NAV2 special purpose vehicle
Campus
NAV2, Airoli and Dighe, Navi Mumbai — NTT’s largest announced Indian campus
Land
54 acres — from the lender’s report
Announced capacity
500 MW facility / 336 MW IT, three buildings, March 2025
Phase one
107 MW across four data centres
Proposed ultimate
315 MW, in multiple phases
Project cost
about ₹5,500 crore for phase one, debt to equity 55:45
Leased
83 MW of 107 MW — 76%, as of August 2025
Operational
43 MW, up from 21 MW in August 2024
Building
24 MW under construction
Counted
Non-additive. 0 MW counted in this registry

2Eight numbers for one campus

This is the single most-reported data centre project in India and the one where the published figures diverge most. Put them on one axis and the reason becomes obvious: they are not eight estimates of one quantity. They are four different quantities.

Facility powerNTT announcement, Mar 2025500 MWIT capacityNTT announcement, Mar 2025336 MW ITUltimate capacityICRA, Oct 2025315 MWPhase 1 IT, developerPanchshil listing125 MWPhase 1 capacityICRA, Oct 2025107 MWLeasedICRA, Aug 202583 MW leasedOperationalICRA, Aug 202543 MW liveUnder constructionICRA, Aug 202524 MW buildingEvery number NTT, its lenders and its developer have published for NAV2. The bottom four are the only ones describing the same asset on the same date.
Figure 1Everything published on NAV2, by source and date. Top three bars are the announcement. Bottom four are the lender describing the same site fourteen months before this record.
Who says what, and what class of fact it is
FigureSourceWhat it measuresClass
500 MWNTT, March 2025facility power at full builda plan
336 MWNTT, March 2025IT capacity across three buildingsa plan
315 MWICRA, October 2025proposed capacity of the project companya plan
125 MWdeveloper listingphase one IT capacitya phase
107 MWICRA, October 2025phase one capacity across four DCsa phase
83 MWICRA, August 2025leased capacitya contract
43 MWICRA, August 2025operational areaa building
24 MWICRA, August 2025under constructiona building site

Two things worth noting. First, 336 MW of IT at a ratio of 1.5 gives 504 MW of facility load — which is what NTT said: 500 MW. The announcement is internally consistent and obeys the same house ratio as NAV1A. It is a real plan.

Second, 315 against 336 is a 21 MW gap between the company and its own lender. The most likely explanation is scope: the project company may not include every building the marketing announcement counted. The registry does not choose between them.

The rule this page establishes

Never compare an announcement to a building. 500 MW, 107 MW, 83 MW and 43 MW are all true statements about NAV2 and only the last one can be visited.

Any market report that lists Airoli as 500 MW of supply is quoting a plan as if it were stock.

383 leased against 43 live

The credit rating report is the most valuable document in Indian data centre research, because it is written for people who lend money and it carries a date.

Phase 1 as ratedICRA, four data centres, 54 acres107 MWLeased76% of phase one83 MWOperational, Aug 2025up from 21 MW in Aug 202443 MWUnder constructionas reported by ICRA24 MWEighty-three megawatts are contracted. Forty-three are live. Sixteen are leased, not live, and not yet under construction.
Figure 2Phase one, and what has happened to it. The 24 MW under construction is the gap between the pale bar and the navy bar being closed one building at a time.
The delivery gap, computed
MeasureMWHow it is derived
Phase one capacity107ICRA
Leased83ICRA, 76% of phase one
Operational43ICRA, August 2025
Under construction24ICRA
Leased and not yet building1683 minus 43 minus 24
Undeveloped within phase one40107 minus 43 minus 24
Operational as a share of leased52%43 divided by 83

Fifty-two per cent. NTT has signed contracts for 83 MW at Airoli and has 43 MW standing up. Sixteen megawatts are leased, not live, and not yet under construction — which means they sit inside the 40 MW of phase one that has not been started.

That is not a criticism of NTT; it is how hyperscale campuses are sold, with anchor tenants committing years ahead so the next building can be financed. But it does mean the market’s supply number for Navi Mumbai is 17.6% of the Airoli announcement, not 100% of it.

And the growth rate is the honest good news: operational capacity went from 21 MW to 43 MW in twelve months. That is NTT doubling a 54-acre campus’s live capacity in a year while building 24 MW more.

4₹51.4 crore per megawatt

The lender publishes a project cost, which almost never happens. Divide it and you get the number every developer in India works backwards from.

The capital cost benchmark
MeasureValueBasis
Phase one project cost₹5,500 croreICRA, about USD 620 million at ₹88.40
Phase one capacity107 MWICRA
Cost per MW₹51.4 crore5,500 divided by 107
Cost per MW in dollarsabout USD 5.8 millionat the fixed ₹88.40 rate
Debt₹2,276 crore55:45 debt to equity
Cost incurred by June 202569%of the ₹5,500 crore
Leased capacity, at costabout ₹4,266 crore83 MW at ₹51.4 crore each

₹51.4 crore per megawatt is the number to hold against every other Indian project. It says what a hyperscale megawatt costs to construct in Navi Mumbai in 2025, debt and land included.

It also explains the announcement behaviour. At ₹51.4 crore per megawatt, 500 MW of facility power is a ₹25,700 crore commitment. Nobody funds that on an announcement. They fund 107 MW at a time, against 76% leasing, and announce the rest.

What 83 MW leased actually means

Eighty-three megawatts of signed capacity, valued at construction cost, is about ₹4,266 crore of the phase one book.

That is the single largest contracted data centre commitment visible anywhere in this registry, and it is the reason NAV2 gets financed while smaller operators in the same city wait for a tenant.

5Three buildings or thirteen

The building count for NAV2 has been published as three, four and thirteen. None of these are typos; they are different scopes, and getting them wrong changes the campus by a factor of four.

How many buildings does NAV2 have
SourceCountScope
NTT, March 20253data centres in the announced campus
ICRA, October 20254data centres within phase one alone
The Hindu BusinessLine, 202213data centre buildings for the Airoli campus master plan
W.media, March 20253 liveincluding a 50 MW single-building IT load, described as India’s largest

Four buildings in phase one against three in the whole announcement is the one that cannot be explained by scoping. Either phase one is a larger part of the campus than the announcement implies, or the lender is counting buildings inside buildings.

The thirteen comes from a 2022 statement, three years before the 2025 announcement, and most likely belongs to a master plan that has since been rescoped into phases. The registry records it and flags it rather than retiring it.

What can be said with confidence: NAV2 contains a single building with 50 MW of IT load, which at a 1.5 ratio is 75 MW of facility load — bigger than NTT’s entire NAV1 phase one across two buildings.

6Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
The largest live block of hyperscale capacity in Maharashtra, at 54 acres and 43 MW currently energised
Where the capacity is
Airoli and the Dighe stretch of the TTC belt, Navi Mumbai
Who holds the answer
NTT Global Data Centers India commercial team
The one question
What is energised today, as distinct from leased, and when does the 24 MW under construction hand over
Why they will answer it
76% of phase one is already contracted, so the remaining question is delivery timing, not availability
Gridvik estimate
About 40 MW of phase one remains undeveloped, of which 16 MW is already leased. Labelled an estimate from ICRA’s August 2025 position
What changes it
The next ICRA report, or an operator statement of energised capacity
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

7Limits and open questions

  • 500 MW and 336 MW are a plan. They are not supply and they are not counted anywhere in this registry.
  • 107 MW of phase one and 315 MW proposed come from a lender’s report dated October 2025, describing a position as of August 2025. It is the best available evidence and it is fourteen months old.
  • The operational figure is an area measure as reported by ICRA. Whether it corresponds exactly to energised IT load is an assumption.
  • Building count is unresolved at three, four or thirteen.
  • 315 MW against 336 MW is a scope gap of 21 MW between the company and its project lender. Not adjudicated.
  • ₹51.4 crore per MW includes land and finance costs as reported for the project company; it is not a pure construction cost.
  • No PUE, rack count or tenant list. The 50 MW single building has no published floor area.
  • What would close it. An energised-capacity figure from the operator, and the next rating report.

8Sources

Sources: ICRA rating rationale for NTT Global Data Centers NAV2 Private Limited, Data Center Dynamics reporting on the March 2025 NAV2 announcement, W.media on the launch and the 50 MW single building, The Hindu BusinessLine on the Airoli campus master plan, Datacentermap and Baxtel listings, developer listing for NAV2 phase one, and independent Mumbai market analysis.