Facility record · Verified 26 Oct 2026

NTT Noida 2, Building A — Greater Noida, Uttar PradeshNTT Global Data Centers · Tech Zone IV, Greater Noida · 22.4 MW critical IT load · 300,000 sq ft · opened January 2024

Record PRJ-164Uttar Pradesh — Greater NoidaTier A — dated and specified6 public sources checkedAdditive: no — child of PRJ-023
Dated launchIT load statedFloor area publishedFirst seismic dampers in IndiaChild of a campus aggregate
22.4MW
Critical IT load
300,000sq ft
Building area
74.7kW
IT per 1,000 sq ft
13,393sq ft
Per MW of IT
52.8MW
Campus when complete
6
Acres

NTT Noida 2 Building A opened in January 2024 in Tech Zone IV, Greater Noida, with 22.4 MW of critical IT load across 300,000 square feet — the first of two buildings on a six-acre campus planned for 52.8 MW. It was the first data centre campus in India to incorporate seismic dampers, and it came with liquid immersion and direct contact liquid cooling as standard NTT issue. The most valuable number on this page is not the 22.4. It is 13,393 — square feet of building per megawatt of IT. Set that against NTT’s other documented buildings and a pattern appears: 13,333 at NAV1A, 13,455 at Vikhroli, 12,917 at the 2011 Noida retrofit. Four buildings, three cities, thirteen years, all within 4% of 13,300 square feet per megawatt. That is a design constant, and it is what lets this registry estimate a building’s floor area — or its capacity — from the other half of the pair.

1At a glance

Operator
NTT Global Data Centers — NTT DATA
Facility
Noida 2 Building A, Tech Zone IV, Amrapali Dream Valley, Greater Noida
Capacity
22.4 MW critical IT load — operator-stated
Building area
300,000 sq ft / about 28,000 m²
Campus
52.8 MW across two buildings on six acres
Opened
January 2024, announced 11 January
Engineering
Seismic dampers — the first data centre campus in India to use them; liquid immersion and direct contact liquid cooling
Facility load at 1.5
about 33.6 MW — derived, not published
Parent
PRJ-023, the 52.8 MW Noida 2 campus
Counted
Non-additive. 0 MW counted at building level

2The 13,300 standard

Indian data centre capacity is usually published as a single number, which makes nothing comparable. NTT publishes two numbers for this building, and the second one is a Rosetta stone.

Vikhroli, 20123,000 sq m of server space13,455 sq ftNoida 2 Building A, 2024300,000 sq ft13,393 sq ftNAV1A, 2022400,000 sq ft13,333 sq ftNoida 1, 2011 retrofitabout 1,800 sq m12,917 sq ftSquare feet of building per megawatt of critical IT load. Three cities, thirteen years, and a spread of 4% around 13,300.
Figure 1Square feet of building per megawatt of critical IT load, for every NTT facility in this registry where both halves are public.
The constant, computed
BuildingIT loadFloorsq ft per MW
Noida 1, 2011 retrofit1.5 MWabout 19,375 sq ft12,917
NAV1A, 202230 MW400,000 sq ft13,333
Noida 2 Building A, 202422.4 MW300,000 sq ft13,393
Vikhroli, 20122.4 MWabout 32,292 sq ft13,455
Spread across all four——4.2%
Working constant——13,300 sq ft per MW

Four per cent across thirteen years is not a coincidence and it is not a rounding artefact. It is a building type: a standard hall module with a fixed relationship between floor plate, electrical room, cooling plant and rentable load.

Which gives this registry a working tool. Multiply any NTT IT figure by 13,300 and you have a floor area estimate. Divide any NTT floor area by 13,300 and you have a capacity estimate. Neither is a published figure, and both are labelled as estimates wherever they appear.

What this does to the rest of the file

NAV1B is published at 30.4 MW. The standard predicts about 405,800 sq ft. A directory listing gives it 577,576 sq ft — 42% above the standard. Either the building is a different type or the listing is wrong. That question is open on record PRJ-160.

Noida 2 Building B is also published at 30.4 MW. The standard predicts the same 405,800 sq ft. No floor area has ever been published for it.

374.7 kW per thousand square feet

The same two figures expressed the way a facilities engineer would use them: how much IT load a square foot of building carries.

Power density per unit of floor
MeasureNoida 2 Building ANAV1A, for comparison
Critical IT load22.4 MW30 MW
Building area300,000 sq ft400,000 sq ft
IT kW per 1,000 sq ft74.7 kW75.0 kW
Facility kW per 1,000 sq ft at 1.5112 kW112.5 kW
Floor per MW of IT13,393 sq ft13,333 sq ft
Difference0.4%baseline

Two buildings, two campuses, two years apart, and the density per square foot of building is identical to within half a percent. This is not how the Indian market describes capacity anywhere else — and it is exactly the kind of check that catches an inflated figure.

It also puts a ceiling on the AI narrative for this building. At 74.7 kW of IT per 1,000 square feet, a 300,000 square foot floor carries 22.4 MW no matter how the cabinets are arranged. Denser cabinets do not create capacity; they consume less of the floor to use the same capacity.

The number that would matter for AI is not on this page. It is kW per cabinet, and NTT has not published a rack count for Noida 2 Building A.

4First seismic dampers in India

NTT made a specific and checkable engineering claim at the launch: this was the first data centre campus in India to incorporate seismic dampers.

What was announced with the launch
ItemDetail
Seismic dampersFirst data centre campus in India to use them, per the operator
CoolingLiquid immersion cooling and direct contact liquid cooling available
AutomationMonitoring and optimisation of power and water resources
ConnectivityCarrier neutral, interconnected with NTT’s other Indian campuses
India footprint at launch268 MW across 18 facilities, over 3.1 million sq ft
Investment contextPart of an USD 11 billion commitment for 2022 to 2027

Seismic dampers are not marketing. Delhi NCR sits in a seismic zone where structural protection is a real engineering cost, and being first to install the equipment is a genuine differentiator with financial-services tenants who carry business continuity obligations.

The 268 MW and 18 facilities at launch are also worth holding onto, because they are NTT’s own total for India as of January 2024 and they sit against 181 MW of additive NTT records in this registry. The difference is the aggregate — campuses, planned phases and the 500 MW NAV2 announcement, none of which is a building.

That is the cleanest illustration of the registry’s central rule: an operator’s own 268 MW is a portfolio statement, and 181 MW is what can be pointed at.

5Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
New Delhi NCR hyperscale capacity with seismic protection and liquid cooling, opened 2024
Where the capacity is
Tech Zone IV, Greater Noida — the newer NCR corridor, not Sector 63
Who holds the answer
NTT Global Data Centers India commercial team
The one question
What is the kW per cabinet in a liquid-cooled hall, and what is left of the 22.4 MW
Why they will answer it
The building is two years old, publicly dated and the second building on the campus is unverified
Gridvik estimate
About 1,900 to 3,700 cabinets at 6 to 12 kW of IT each, and roughly 33.6 MW of facility load. Labelled an estimate
What changes it
A rack count, a hall density specification, or an occupancy figure
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

6Limits and open questions

  • 22.4 MW is critical IT load and is not comparable with NTT’s facility-load figures at Mumbai 8 and Mumbai 9.
  • 33.6 MW of facility load is derived at the 1.5 house ratio and is not published for this building.
  • The 13,300 sq ft per MW constant is four data points, not a specification. It is used only as a labelled estimate.
  • The 19,375 sq ft used for Noida 1 converts from a metric server-space figure and is approximate.
  • No rack count, no PUE, no occupancy, no tenant list.
  • Seismic dampers are an operator claim with no certification number attached.
  • What would close it. A rack count and a per-cabinet kW figure. Two lines, and neither is published.

7Sources

Sources: NTT newsroom release of 11 January 2024 announcing the Noida 2 campus, Data Center Dynamics reporting on the launch, Times of India and Economic Times coverage of the seismic dampers and the 268 MW India footprint, NTT DATA global data center locations index, and Datacentermap Noida listings.