Facility record · Verified 26 Oct 2026

NTT Bengaluru 4A — Devanahalli, KarnatakaNTT Global Data Centers · Building A, Bengaluru 4 campus, Prestige Tech Cloud, Devanahalli · 22.4 MW critical IT load · 7 data halls · live June 2026

Record PRJ-173Karnataka — DevanahalliTier A — dated and specified7 public sources checkedAdditive: no — child of PRJ-172
Dated launchHall structure published220 kV GIS substationMost-used NTT moduleChild of a campus aggregate
22.4MW
Critical IT load
7
Data halls
3.2MW
Per hall
~33.4MW
Facility at 1.49
4
NTT buildings at 22.4 MW
Jun 2026
Live

Bengaluru 4A went live in June 2026 with 22.4 MW of critical IT load across seven data halls of 3.2 MW — the first of three identical buildings on a campus that will reach 67.2 MW. It runs off a dedicated 220 kV gas insulated substation with a 220 kV LILO connection to the state grid and generators holding 48 hours of fuel. It is also the fourth NTT building in this registry at exactly 22.4 MW — Noida 2 Building A and the three Bengaluru 4 buildings. That makes it the operator’s most-used module and NTT’s newest large building in India. Three point two megawatts per hall is the most useful number here: it is the smallest unit NTT sells, and it is why a campus can be one third live and still open for business.

1At a glance

Operator
NTT Global Data Centers — NTT DATA
Facility
Bengaluru 4A, Building A, Prestige Tech Cloud, Devanahalli
Capacity
22.4 MW critical IT load — operator-stated
Data halls
Seven of 3.2 MW each
Facility load at 1.49
about 33.4 MW — derived from the campus ratio
Power
Dedicated 220 kV GIS substation, 220 kV LILO from the state grid, four dedicated POE routes
Resilience
Generators with 48-hour HSD backup; IGBC Platinum rated; seven-layer security
Live
June 2026, after a December 2025 commissioning milestone
Parent
PRJ-172, the 67.2 MW Bengaluru 4 campus
Counted
Non-additive. 0 MW counted at building level

2Seven halls of 3.2 MW

The internal structure is the most useful disclosure on this building, because it tells a tenant what the smallest thing they can buy actually is.

Seven data halls3.2 MW each22.4 MWLive since June 2026Building A of three22.4 MWBuildings B and Ctwo more 22.4 MW buildings44.8 MW plannedCritical IT load. The hall structure is what makes a partial campus usable: one hall can be commissioned without completing a building.
Figure 1Critical IT load at the hall, building and campus level. The hall is the unit of commissioning, which is why partial campuses work.
The hall arithmetic
LevelCapacityNote
Data hall3.2 MW critical ITthe smallest unit NTT publishes in India
Halls per building7operator-stated
Building A total22.4 MW7 x 3.2
Campus total67.2 MW3 buildings of 22.4
Facility load per hallabout 4.8 MWat the 1.49 campus ratio, derived
Share of campus live33%one of three buildings

Three point two megawatts is roughly 400 to 600 cabinets at 6 to 8 kW, or 190 cabinets at 17.2 kW. It is a real commitment but not a hyperscale one, and it lets an operator place a single anchor tenant into a single hall without committing a building.

That granularity also explains why the campus announcement and the campus delivery diverge without anyone lying: Building A is complete, the halls inside it are fitted out against demand, and the market reads “22.4 MW live” whether four halls or seven are actually energised.

The question a tenant should ask

Not how many megawatts are live, but how many halls are fitted out and at what density.

NTT publishes the hall size. It does not publish the fit-out status, and that gap is where a 22.4 MW building can be 40% available or fully let.

3220 kV and 48 hours of diesel

The power architecture is published in unusual detail and it is the part of this building that will still matter in fifteen years.

Published engineering
ItemDetail
Substation220 kV gas insulated, dedicated to the campus
Grid connection220 kV LILO arrangement from the state grid
Generator backup48 hours of HSD fuel storage
FibreFour dedicated points of entry
SustainabilityIGBC Platinum rated, renewable power integration
SecuritySeven-layer system
CoolingCampus able to support liquid cooling

A dedicated 220 kV GIS substation is the single clearest marker of a serious hyperscale campus in India. It is also the item that most often decides whether an announced capacity is ever built, because the grid connection is slower than the building.

NTT has now done this twice — at NAV1 in Mahape in 2022 and here in Devanahalli in 2026 — and in both cases the substation was the engineering story. Forty-eight hours of fuel is also worth noting: most Indian facilities publish 24, and the difference is a business-continuity claim rather than a cost saving.

The combination is what a financial-services or sovereign tenant looks for: own substation, dual grid entry, two days of fuel, four fibre paths, and a certified green building. None of that appears in a megawatt figure.

4The fourth 22.4 MW building

22.4 MW is now NTT’s most-used building capacity in India. Four records in this registry carry it, and they span two cities and two years.

NTT's building modules, by frequency
CapacityBuildingsCities
22.4 MWNoida 2 A, Bengaluru 4A, 4B, 4CGreater Noida, Devanahalli
30.4 MWNAV1B, Noida 2 BNavi Mumbai, Greater Noida
25.6 MWMumbai 7, NAV1CMumbai, Navi Mumbai
30 MWNAV1ANavi Mumbai
17.4 MWChennai 2A, 2BChennai
19.2 MWMumbai 6Mumbai
12.5 MWMumbai 5Mumbai

Four buildings at 22.4 MW, three of them on this campus. The pattern is clear enough to be useful commercially: when NTT announces a new Indian campus at a multiple of 22.4, the building is known. When it announces 67.2, it means three of them.

The registry uses the module catalogue exactly this way — to size a building from its siblings before anyone has published a floor area, a rack count or a commissioning date for it.

Bengaluru 4A is the module at its most documented: 22.4 MW, seven halls, 220 kV, June 2026, IGBC Platinum. Buildings 4B and 4C are the same building with none of that published. One record carries what the other two can safely be assumed to be.

5Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
New Bengaluru hyperscale capacity in 3.2 MW halls, with a dedicated 220 kV substation and two days of generator fuel
Where the capacity is
Prestige Tech Cloud, Devanahalli — the airport corridor, about 30 km north of the city centre
Who holds the answer
NTT Global Data Centers India commercial team
The one question
How many of the seven halls are fitted out, and at what kW per cabinet
Why they will answer it
The building is new, the hall structure is public and the campus needs anchors to finance Buildings B and C
Gridvik estimate
About 33.4 MW of facility load at the campus ratio, with four to six halls delivered. Labelled an estimate
What changes it
A hall fit-out schedule, or a density specification
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

6Limits and open questions

  • 22.4 MW is critical IT load, not facility load. The campus ratio of 1.49 gives about 33.4 MW of plant, which is derived.
  • No rack count is published for this building, so density per cabinet cannot be computed.
  • Hall fit-out status is unknown. Seven halls exist as a design; how many are energised is not published.
  • No PUE, occupancy or tenant list.
  • IGBC Platinum and the seven-layer security claim carry no certificate numbers in the published material.
  • The December 2025 “ready for commissioning” milestone and the June 2026 opening are six months apart; both are published and the registry keeps both.
  • What would close it. A rack count and a hall fit-out figure. Both are two lines on a facility page.

7Sources

Sources: NTT DATA announcement of 13 June 2026, NTT Global Data Centers Bengaluru 4 campus page, press release material distributed in December 2025 covering the 3.2 MW hall structure and the 220 kV substation, Data Center Dynamics reporting, and Economic Times Datacentres launch coverage.