Planned facility · Verified 26 Oct 2026

NTT Bengaluru 4B — Devanahalli, KarnatakaNTT Global Data Centers · Building B, Bengaluru 4 campus, Prestige Tech Cloud, Devanahalli · 22.4 MW planned critical IT load

Record PRJ-174Karnataka — DevanahalliTier B — capacity clear, stage unverified5 public sources checkedAdditive: no — child of PRJ-172
Stage unverifiedCapacity statedIdentical to Building ASeven halls, no fit-out dataChild of a campus aggregate
22.4MW
Planned critical IT load
7 x 3.2MW
Data halls
67%
Campus delivered if built
~33.4MW
Facility at 1.49
22.4MW
Live today, Building A only
0MW
Counted here

Bengaluru 4B is the middle of three identical buildings on NTT’s Devanahalli campus: 22.4 MW of critical IT load across seven data halls of 3.2 MW by campus design. Building A is live and dated. Building B has no published construction start, topping out or commissioning date. It is the building that matters most on this campus, because it is the one that takes delivery from 33% to 67% — and because it has to be financed against the leasing of a building that opened four months ago. Nothing else about it is uncertain. The module is known from Building A to the megawatt, the hall structure is published, and the 220 kV substation on site was sized for 100 MW of facility load. This is a five-section page because the public record is a capacity and a parent. The registry does not pad it.

1At a glance

Operator
NTT Global Data Centers — NTT DATA, with Prestige Group as development partner
Facility
Bengaluru 4B, Building B, Prestige Tech Cloud, Devanahalli
Capacity
22.4 MW planned critical IT load — campus design
Data halls
Seven of 3.2 MW, per the campus design
Facility load at 1.49
about 33.4 MW — derived from the campus ratio
Stage
Planned, unverified — no construction evidence published
Sibling
Building A, live June 2026 at 22.4 MW — see PRJ-173
Parent
PRJ-172, the 67.2 MW Bengaluru 4 campus
Counted
Non-additive. 0 MW counted at building level

2The middle third

The campus is three identical buildings, and the register of what has been published about them is short enough to reproduce in full.

Building Alive June 202622.4 MW liveBuilding Bplanned, no evidence22.4 MW plannedBuilding Cplanned, no evidence22.4 MW plannedCritical IT load. Every building is the same module, so the only open question on this campus is how many of them exist.
Figure 1Critical IT load. Navy has a date. Red and pale have a capacity and nothing else.
What is published about each building
BuildingCapacityHallsPublished stage
Bengaluru 4A22.4 MW7 x 3.2 MWlive June 2026
Bengaluru 4B22.4 MW7 x 3.2 MW by designnone
Bengaluru 4C22.4 MW7 x 3.2 MW by designnone

That is the entire public record at building level. The campus announcement covers all three, the June 2026 launch covers one, and the other two are carried by the campus total.

This is not unusual and it is not a criticism of the operator. It is the normal state of Indian data centre capacity: a campus is announced once and delivered three times, and only the first delivery gets a press release.

What the registry can and cannot say

It can say that Building B is 22.4 MW of critical IT with seven 3.2 MW halls, because the campus design says so and the operator has published the hall structure.

It cannot say whether Building B has broken ground. No source in the reviewed set does.

3What Building B adds

Two things follow from building it, and one of them is financial rather than technical.

The campus, before and after
MeasureWith Building A onlyWith Building B
Critical IT load live22.4 MW44.8 MW
Facility load live at 1.49about 33.4 MWabout 66.8 MW
Data halls liveup to 7up to 14
Share of the campus delivered33%67%
Share of the 100 MW facility plan33%67%
Campus land used8.5 acres, unchanged8.5 acres, unchanged

The financial point is the one that decides the timing. A three-building campus is normally financed one building at a time, and each building is financed against the leasing of the last. Building B exists when Building A is let, not when the market asks.

Building A is four months old at this record’s cutoff. If NTT follows the pattern it has followed everywhere else in this file — 76% of phase one leased at Airoli before the next buildings went up — then Building B is a 2027-2028 building rather than a 2026 one.

The technical point is easier. The site already has a dedicated 220 kV GIS substation sized for the 100 MW campus plan. Building B needs no new grid connection, which removes the slowest item on any Indian data centre schedule.

So the constraint on this building is demand, not infrastructure. That is a different and better position than most of the campuses in this registry, where the constraint is still the substation.

4Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
Nothing yet. This is a planned second building on a live campus
Where the capacity is
Prestige Tech Cloud, Devanahalli — the Bengaluru airport corridor
Who holds the answer
NTT Global Data Centers India commercial team
The one question
Is Building B in construction, and what leases in Building A would trigger it
Why they will answer it
Two thirds of their newest campus is undelivered and needs anchors to be financed
Gridvik estimate
About 33.4 MW of facility load and up to seven halls of 3.2 MW, identical to Building A. Labelled estimates on an unverified stage
What changes it
A construction start, or an occupancy figure for Building A
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

5Limits and open questions

  • Stage is unverified. No construction, planning or commissioning evidence was found for Building B in the reviewed set.
  • 22.4 MW counts zero here and must never be added to Building A’s 22.4 MW to claim 44.8 MW of live capacity.
  • The seven-hall structure is a campus design figure published at the December 2025 commissioning milestone. It has not been independently confirmed for Building B.
  • 33.4 MW of facility load is derived from the campus ratio of 1.49, not published for this building.
  • No floor area, rack count, PUE or cost allocation for Building B specifically.
  • This is a five-section page on purpose. A capacity, a sibling and an absence of stage is the whole public record.

6Sources

Sources: NTT Global Data Centers Bengaluru 4 campus page, NTT DATA announcement of 13 June 2026 covering Building A, press release material distributed in December 2025 describing the three buildings and seven 3.2 MW halls, and Data Center Dynamics reporting on the Bengaluru 4 campus.