Facility record · Verified 26 Oct 2026

AirTrunk BOM2 — Mahape, Navi MumbaiAirTrunk, via Lumina CloudInfra · Mahape, Navi Mumbai · 120 MW facility capacity · 5.4 ha · 220 kV substation

Record PRJ-181Maharashtra — Navi MumbaiTier B — specified, stage unverified6 public sources checkedAdditive: yes — 120 MW counted
Design PUE declared220 kV substation9.0 MW per acreStage unverifiedAt-least 120 MW
120MW
Facility capacity, at least
9.0
MW per acre
5.4ha
Site
22,700m²
Built-up per building
220kV
Substation
<1.4
Declared design PUE

AirTrunk BOM2 at Mahape is 120 MW of facility capacity on 5.4 hectares, with 22,700 square metres of built-up area per building, a 220 kV substation and a declared design PUE below 1.4. It is the largest of the three Mumbai sites in the AirTrunk pipeline and one of the most land-efficient facilities in this registry at 9.0 MW per acre. It also sits in the most contested square kilometre in Indian data centres. Within the same Mahape and Airoli industrial belt: NTT’s NAV1 at 150 MW of plan, NTT’s NAV2 announced at 336 MW, CtrlS, Princeton Digital Group, L&T’s Vyoma site, and AirTrunk’s own BOM1 five kilometres away. Stage is unverified, as with every card in the portfolio. What is certain is the substation, the acreage and the efficiency target — and in a belt with this much capacity chasing the same grid, those three numbers are the whole competition.

1At a glance

Operator
AirTrunk — via Lumina CloudInfra
Facility
BOM2, Mahape, Navi Mumbai
Capacity
120 MW facility capacity, at least
Site
5.4 ha / 13.34 acres
Built-up area
22,700 m² per building
Power
220 kV substation
Efficiency
Declared design PUE below 1.4
Land efficiency
9.0 MW per acre
Stage
Unverified — no stage stated on the operator card
Counted
Additive. 120 MW counted, with the stage flagged

29.0 MW an acre

Two AirTrunk sites now bracket the top of the land-efficiency table, and that is not an accident of geography.

NTT NAV2announced campus, 54 acres336 MW planAirTrunk BOM2120 MW at least, 13.3 acres120 MWPDG MU2Mumbai campus, separate parcel60 MWAirTrunk BOM162 MW at least, 5.9 acres62 MWNTT NAV1A30 MW IT live since 202230 MWPublished capacities in one industrial belt. Pale is a plan, red is an unverified card, navy is built capacity.
Figure 1Published capacities in the Mahape and Airoli belt. Red is an unverified card, pale is a plan, navy is built capacity.
BOM2 from its own numbers
MeasureValueBasis
Facility capacity120 MWoperator card, at least
Site area5.4 ha / 13.34 acresoperator card
MW per acre9.0120 divided by 13.34
Built-up area22,700 m² per buildingoperator card, building count not stated
Built-up per MWabout 2,036 sq ftif one building, and an estimate
Substation220 kVoperator card
Design PUEbelow 1.4operator card

The 2,036 square feet per megawatt in the fifth row is deliberately shown with a heavy caveat. The card says 22,700 square metres per building and does not say how many buildings there are. If there are two, the ratio doubles to about 4,072; if four, it quadruples.

This is exactly the floor-area problem set out on record PRJ-171, in its purest form: a published area that cannot be turned into a per-megawatt figure without a building count that has not been published.

The acreage figure, by contrast, is usable. Nine megawatts an acre on 13.34 acres, with a 220 kV connection, is a site configured for wholesale hyperscale rather than enterprise colocation.

And the PUE is the same sub-1.4 declaration as the rest of the portfolio. Two AirTrunk sites with declared efficiency, four NTT buildings with none, and one registry-derived 1.48 — that is the complete state of PUE disclosure in the Indian market.

3Four operators in one belt

Mahape and Airoli are one industrial belt in Navi Mumbai, and this registry can now price the competition inside it.

Who is in the belt
OperatorRecorded capacityWhat it is
NTT NAV2, Airoli336 MW proposedannounced campus, 54 acres
AirTrunk BOM2, Mahape120 MWunverified card, 13.34 acres
AirTrunk BOM1, Airoli62 MWunverified card, 5.94 acres
AirTrunk BOM3, Chandivali48 MWunverified, urban infill, 33 kV
NTT NAV1, Mahapeabout 100 MW ITfour buildings, 150 MW facility plan
NTT NAV1A, Mahape30 MW ITlive since 2022, 5,000 racks
PDG and CtrlSseparate parcelsnot linked to any of the above at parcel level

The registry’s note against this record is specific and worth repeating: BOM2 shares Mahape geography with PDG, CtrlS and L&T Vyoma, and no parcel-level link has been established between them. Two sites can be five hundred metres apart and be entirely separate businesses.

What matters commercially is the aggregate. Between NTT’s NAV1 and NAV2 and AirTrunk’s BOM1 and BOM2, roughly 600 MW of published capacity sits inside one belt that currently has about 30 MW of dated, live building in this registry.

That ratio — twenty to one between announced and energised — is the single best summary of the Indian data centre market this file has produced, and it is visible only because both operators publish their pipeline at parcel level.

The constraint on all of it is the same: 220 kV power in Navi Mumbai. Every operator in this table has or needs a high-voltage substation on the same grid, and that grid is the reason the belt has taken six years to deliver 30 MW.

4Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
Wholesale hyperscale capacity in Mahape, at 220 kV, with a declared sub-1.4 design PUE
Where the capacity is
Mahape, Navi Mumbai — the belt shared with NTT NAV1 and NAV2, CtrlS and PDG
Who holds the answer
AirTrunk India commercial team
The one question
Is BOM2 energised or in development, and how many buildings the 120 MW is spread across
Why they will answer it
It is the largest of the three Mumbai sites and the pipeline needs anchors
Gridvik estimate
One to three buildings of 30 to 60 MW each, in development rather than live. Labelled an estimate
What changes it
A stage statement, or a building count with floor areas
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

5Limits and open questions

  • Stage is unverified. The operator card states no operating or construction status.
  • 120 MW is facility capacity, at least — a floor, not IT load.
  • The 22,700 sq m figure is per building and the building count is not published, so no per-megawatt floor ratio can be computed.
  • Design PUE below 1.4 is a specification, not an operating measurement.
  • No parcel-level link has been established between this site and the PDG, CtrlS or L&T sites in the same belt.
  • The 600 MW belt aggregate mixes proposed campus plans with unverified facility cards and built capacity, and is indicative only.
  • No rack count, tenant list or occupancy.
  • What would close it. A stage statement and a building count. Two lines would resolve most of this page.

6Sources

Sources: AirTrunk location page for BOM2, AirTrunk’s announcement of the Lumina CloudInfra acquisition of April 2026, Data Center Dynamics coverage of the acquisition, Datacentermap and Baxtel Navi Mumbai listings for the surrounding sites, and the registry’s own NTT records PRJ-158 to PRJ-162 for the belt comparison.