Iron Mountain Navi Mumbai — the 5.5-acre campusIron Mountain Data Centers · Navi Mumbai, Maharashtra · MUM-1, MUM-2, MUM-3 · 8.8 MW live · 93.8 MW at completion · 120 MVA substation

Record PRJ-187Maharashtra — Navi MumbaiTier B — operator-published, itemised in part6 public sources checkedAdditive: no — campus claim, counts 0
Two buildings energised81 MW of 93.8 is unbuiltSubstation matches the claim2027 or Q1 2028, unresolvedMUM-1 and MUM-2 count as zero
93.8MW
Campus at completion
8.8MW
Energised today
5.5acres
Campus
17.1
MW per acre at completion
1.6
MW per acre today
120MVA
Substation capacity

The Navi Mumbai campus is 5.5 acres — 2.2 hectares — and it holds 8.8 MW of IT capacity today across MUM-1 and MUM-2, which is 1.6 MW per acre. MUM-3 adds 85 MW at full build, taking the campus to 93.8 MW and 17.1 MW per acre. The same piece of land, 10.6 times the megawatts. That is not a marketing artefact — the operator has approved a 120 MVA substation, and 120 MVA divided by 85 MW is 1.41, which is exactly a design PUE of about 1.4 with no headroom. The substation is the proof that the 85 MW figure is an engineering number rather than a headline.

1At a glance

Campus
5.5 acres / 2.2 hectares, Navi Mumbai, Maharashtra
Buildings
MUM-1 (2015), MUM-2 (Feb 2023), MUM-3 (ground broken Jan 2026)
Energised
8.8 MW IT — MUM-1 2.5 MW, MUM-2 6.3 MW
At completion
93.8 MW; the operator states 90+ MW and separately 93 MW
Land efficiency today
1.6 MW per acre
Land efficiency at completion
17.1 MW per acre — the highest campus ratio in this registry
MUM-3 scale
85 MW full build; 130,000 sq m / 1,398,000 sq ft
MUM-3 substation
120 MVA dedicated; implies a facility-to-IT ratio of 1.41
MUM-3 location
Rabale, within the MIDC industrial area, Navi Mumbai
Contractor
Stirling & Wilson
Delivery
2027 on operator and press pages; Q1 2028 on two operator pages
Record type
Campus aggregate. Non-additive, counts 0

2Ten times the megawatts on the same 5.5 acres

MUM campus, at completion93.8 MW on 5.5 acres17.1 MWBOM3, Chandivali48 MW on 3.71 acres12.9 MWBOM1, Navi Mumbai62 MW on 5.94 acres10.4 MWBOM2, Mahape120 MW on 13.3 acres9.0 MWKolkata 1, NTT25 MW on 7.5 acres3.3 MWMUM campus, today8.8 MW on 5.5 acres1.6 MWThe same 5.5 acres appears twice. One bar is six years of operating history; the other is one unbuilt building's promise. The ratio between them, 10.6 times, is what vertical data centres do.
Figure 1 — Navi Mumbai land efficiency against the peer set. The campus at completion would be the densest site in this registry; today it is the least dense of the operating Mumbai builds.

Land efficiency is the cleanest comparison in Indian data centres because land is the one input nobody can add. Every operator in Mumbai is buying the same scarce parcels, and the only way to put more megawatts on a fixed footprint is to build upward and to push power density per square metre.

What the 5.5 acres carries
StageMWMW per acreWhat it means
MUM-1 alone, 20152.50.45Single-storey era, enterprise colocation
MUM-1 + MUM-2, 20238.81.6Two buildings, same parcel, no new land
MUM-3 at full build8515.5One building, 9.7 times the output of the first two
Campus at completion93.817.1Densest campus in the registry
For comparison — BOM3 Chandivali4812.9Densest announced single facility in the registry
For comparison — Kolkata 1253.3Low-rise, land-rich, 7.5 acres
Read the table as a history of Indian data centre design

MUM-1 at 2.5 MW on 5.5 acres is 0.45 MW per acre — a 2015 building on a site bought for expansion that had not happened yet. MUM-2 doubled the output without buying land.

MUM-3 puts 85 MW on the remainder. The 5.5 acres does not change. What changes is storeys, cooling architecture and the substation behind the wall.

This is the single most useful ratio for anyone pricing Indian land: the site is fixed and the megawatts are a design decision. AirTrunk pays ₹118 crore an acre in Chandivali because 12.9 MW per acre is the only way the land cost works.

3120 MVA for 85 MW

Almost every capacity claim on this registry is unverifiable from the outside. MUM-3 is one of the rare exceptions, because the power infrastructure is published and it has to be sized to the load.

What 120 MVA supports
RatioValueReading
MUM-3 IT capacity85 MWThe headline claim at full build
Dedicated substation120 MVAApproved at the same time as the 2023 announcement
Substation ÷ IT load1.41The implied facility-to-IT ratio
Declared design PUE, AirTrunk comparablebelow 1.4The Indian hyperscale norm in 2026
At 1.41 with no headroomzero spareThe substation is sized to the claim, not above it
If the load were 32 MW as announced in 20233.75Three and a half times oversized — implausible

The arithmetic cuts both ways and both readings are useful. A 120 MVA substation for 85 MW of IT load is a facility-to-IT ratio of 1.41, which is precisely what a modern Indian hyperscale build runs at. That makes the 85 MW credible.

But when the same 120 MVA was announced alongside a 32 MW building in June 2023, the implied ratio was 3.75 — nobody builds a substation three and a half times oversized. Which means the substation was sized for a bigger building than the one announced, and the 85 MW figure was always the real plan.

The check a buyer can actually run

This is the method that makes capacity data defensible. Do not trust the megawatt number; look for the substation, the transformer capacity or the power purchase agreement and divide. A ratio between about 1.35 and 1.5 validates the claim. A ratio of 2 or 3 means the claim is low, and a ratio below 1.2 means the claim is inflated.

Applied across this registry, it separates the 85 MW that will get built from the 3 GW that is a letter of intent.

432 MW to 85 MW in thirty months

  • MUM-3 announced at 32 MW IT load, Tier III designed, on a five-acre parcel. Investment US$170 million. Go-live H2 2025. A 120 MVA substation is approved with the announcement.
  • The original go-live passes with no commissioning announcement.
  • Iron Mountain takes 100% of Web Werks. MUM-3 becomes a wholly owned build rather than a joint venture asset.
  • Ground broken. The facility is now published as 85 MW hyperscale-ready and AI-oriented, 130,000 sq m, with Stirling & Wilson building it.
  • Operator pages split between 2027 delivery and Q1 2028 completion. No commissioning date, no phasing plan, no capex for the 85 MW configuration published.
What changed between the announcement and the groundbreaking
ItemJune 2023January 2026Change
IT capacity32 MW85 MW2.66×
Go-liveH2 20252027, or Q1 2028+2 to 2.5 years
ArchitectureTier III, traditional raised floorAI-ready, high-density, specialised coolingDifferent product
Substation120 MVA120 MVAUnchanged
CapexUS$170 millionNot publishedUnknown

The unchanged substation is the tell. A 120 MVA connection is what a 85 MW building needs. It was never what a 32 MW building needed. The published capacity went up to meet the infrastructure that had already been approved.

What is not published is capital cost. At the US$170 million for 32 MW rate the implied cost was US$5.31 million per MW. Applying that same rate to 85 MW gives US$451 million, and applying AirTrunk’s published programme rate of US$6.0 million per MW gives US$510 million — about ₹4,510 crore. Both are Gridvik estimates, not disclosed figures, and both are labelled as such.

5Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
One parcel, three buildings, one 120 MVA connection — the cleanest vertical-scaling case in the registry
Where the capacity is
Rabale, Navi Mumbai, Maharashtra. 8.8 MW energised; 85 MW under construction
Who holds the answer
Iron Mountain Data Centers India; Stirling & Wilson on the build
The one question
Which phase of the 85 MW lands first, and when
Why they will answer it
A 120 MVA connection has a commissioning date with the distribution utility
Gridvik estimate
First MUM-3 capacity in H2 2028; the full 85 MW not before 2030. Labelled an estimate
What changes it
A substation energisation notice, a phase-one handover, or a published capex figure
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

6Limits and open questions

  • 93.8 MW is a completion sum, not a plan. The operator states 90+ MW on one page and 93 MW on another; 93 uses 8.3 MW for MUM-1 and MUM-2 while the location pages now sum to 8.8 MW.
  • MUM-3 delivers in 2027 or Q1 2028 depending on which operator page is read. Both are live.
  • The 120 MVA inference assumes a power factor of 1.0. At 0.95 the implied ratio falls to 1.34 and the claim looks conservative rather than exact.
  • No capex is published for the 85 MW configuration. Every per-megawatt cost on this page is a Gridvik estimate at a stated rate.
  • The campus ratio of 17.1 MW per acre is not a facility ratio. It mixes two operating buildings with one unbuilt one; the registry keeps BOM3 Chandivali as the densest single announced facility at 12.9 MW per acre.
  • MUM-3 may sit on a separate five-acre parcel. The 2023 announcement describes a five-acre parcel acquired for the third building, separate from the 5.5-acre MUM-1 and MUM-2 campus. If so the combined site is about 10.5 acres and the completion ratio falls to 8.9 MW per acre, behind Chandivali and BOM1. Unresolved, and the reason this registry does not claim the campus record.
  • Zero megawatts counted. MUM-1 and MUM-2 count as zero in the source file; MUM-3 is flagged non-additive.
  • What would close it. A phase schedule with megawatts attached to dates.

7Sources

Sources: Iron Mountain Mumbai and MUM-1, MUM-2 location pages; the Iron Mountain India platform page; the January 2026 MUM-3 groundbreaking release; Data Center Dynamics coverage of the groundbreaking and of the 2023 joint venture announcement; W.media; ETTelecom; the Baxtel MUM-3 entry; the Web Werks and Iron Mountain June 2023 announcement; and SiliconIndia on the five-acre parcel acquisition.