CapitaLand Mumbai Tower 2 — Airoli, Navi MumbaiCapitaLand India Trust and CIDCF · Airoli, Navi Mumbai · 37 MW IT · 55 MW gross power · Stage in conflict · Additive, 37 MW counted

Record PRJ-197Maharashtra — Navi MumbaiTier C — stage unresolved4 public sources checkedAdditive: yes — 37 MW counted
Filing says under developmentLater release implies complete37 MW countedBoth scopes statedNo tower-level confirmation
37MW
IT capacity
55MW
Gross power
1.49
Gross to IT ratio
18MW
Headroom
4.7%
Of Maharashtra
1
Conflicting release

Tower 2 at Airoli carries 37 MW of IT capacity behind 55 MW of gross power capacity. Those numbers are solid: they come from a fund filing dated 31 December 2025. The status is not solid. The same filing records the tower as under development. CapitaLand Investment’s 15 October 2026 release says the whole 108 MW Navi Mumbai facility is completed and fully leased, which implies Tower 2 has since come on stream — but no tower-specific commissioning statement has been located. This registry counts the 37 MW and refuses to resolve the stage. A capacity with a confident number and a disputed status is more useful than a confident status with an unverifiable number.

1At a glance

Facility
Mumbai Tower 2, Airoli, Navi Mumbai, Maharashtra
Operator
CapitaLand India Trust with CapitaLand India Data Centre Fund
IT capacity
37 MW — 3 MW more than Tower 1
Gross power capacity
55 MW
Gross to IT ratio
1.49
Status per 31 Dec 2025 filing
Under development
Status implied by 15 Oct 2026 release
Completed, as part of the 108 MW campus
Tower-specific confirmation
None located
Occupancy
Fully leased at campus level per the October 2026 release
Share of Maharashtra’s 786.4 MW
4.7%
Counted in this registry
37 MW — additive; stage flagged in conflict

2What is filed against what is implied

Site01Design02Structure03Plant04Leased05Commissioned06Navy = verified · Red = current stage · Grey = not yet evidenced
Figure 1 — Tower 2 against a standard delivery ladder. Four stages are evidenced; commissioning is not, and the lease is evidenced only at campus level.
The evidence, in order of strength
DocumentDateWhat it saysStrength
CIDCF acquisition filing31 Dec 2025Tower 2 under development; 37 MW IT, 55 MW grossLegal, specific
CLI investor summary2026First Navi Mumbai development completed in 2025 as a 108 MW facilityCorporate, campus level
CLI press release15 Oct 2026Facility completed and fully leased to a global hyperscalerCommunications, campus level
Tower-level commissioningnone—Missing
Distribution utility energisationnone located—Missing
Why the registry will not resolve this

There is a simple way to make this page look tidier: read the October 2026 release as confirmation and mark Tower 2 operational. It would also be a guess, and a guess hidden inside a capacity dataset is exactly the defect this product exists to fix.

The filing is ten months older but it is a legally prepared document about a specific tower. The release is newer and describes a campus. Neither is a commissioning certificate.

So the record carries stage_conflict and the 37 MW. A buyer who needs certainty on this tower has to ask CapitaLand, and now knows to.

3Seventy-one megawatts of IT in one node

Airoli, tower by tower
TowerIT MWGross MWRatio
Tower 134501.47
Tower 237551.49
Both towers711051.52
Campus stated figure—108—
AirTrunk BOM1, same node62 facility62—
Airoli published total133170Mixed scopes

Airoli holds 133 MW of published IT or facility capacity between CapitaLand’s two towers and AirTrunk’s BOM1, which is 17% of Maharashtra’s entire counted 786.4 MW in a single node of Navi Mumbai.

Tower 2 at 37 MW is the larger of the two CapitaLand towers by 3 MW, and it is the one whose status is disputed. That is the worst possible combination for a buyer relying on public data: the bigger number is the less certain one.

At the 1.49 ratio, fully energised Tower 2 would draw 55 MW from the grid. That is a load the local distribution network notices, and it is the reason an energisation date exists somewhere even though it has not been published.

4Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
The stage question — a 37 MW tower that is either finished or not, in a node with no vacancy
Where the capacity is
Airoli, Navi Mumbai. 37 MW IT, 55 MW gross
Who holds the answer
CapitaLand India Trust, which must state asset completion in its results
The one question
Is Tower 2 commissioned, and in which reporting period
Why they will answer it
It is a yes-or-no question about a disclosed asset, and it moves revenue recognition
Gridvik estimate
Commissioned in calendar 2026 given the campus-level claim. Labelled an estimate and not recorded as fact
What changes it
A CLINT quarterly results note, or a utility energisation record
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

5Limits and open questions

  • Stage unresolved. Under development at 31 December 2025; implied complete by October 2026; never stated for this tower.
  • 37 MW is IT capacity per the filing and is what the registry counts.
  • 55 MW gross power is what the tower would draw at full load.
  • The lease is evidenced only at campus level. No source attributes a specific megawatt to this tower’s occupancy.
  • No floor area is published, so no density figure exists.
  • 37 MW is counted once through this record; the campus aggregate is excluded.
  • What would close it. One sentence from CapitaLand naming this tower and its completion period.

6Sources

Sources: the CapitaLand India Data Centre Fund release of 31 December 2025; the CapitaLand Investment release of 15 October 2026; CapitaLand data centre listing pages; and CLINT results disclosures.