CapitaLand Chennai 01 — Ambattur, ChennaiCapitaLand India Trust and CIDCF · Ambattur, Chennai, Tamil Nadu · 34 MW IT · 53 MW gross · 13 data halls · 110 kV substation · Rs 1,940 crore

Record PRJ-198Tamil Nadu — ChennaiTier A — released, itemised5 public sources checkedAdditive: yes — 34 MW counted
Thirteen halls and a substation publishedBoth scopes statedTenant-ready only by end-2026Rs 57.1 crore per MW of ITFour-acre parcel is single-source
34MW
IT capacity
53MW
Gross power
13
Data halls
2.6MW
Per hall
₹1,940cr
Planned investment
₹57.1cr
Per MW of IT

Chennai 01 at Ambattur is CapitaLand’s first data centre development in Tamil Nadu: 34 MW of IT capacity behind 53 MW of gross power, split across 13 data halls — 2.6 MW per hall — on a four-acre parcel with about 600,000 square feet of built area and a dedicated 110 kV substation. It was unveiled on 15 October 2026, tenant-ready and completion targeted by end-2026, with a planned investment of ₹1,940 crore. That is ₹57.1 crore per megawatt of IT — a disclosed, itemised, single-building cost, which is rare enough in India to be worth a page on its own.

1At a glance

Facility
CapitaLand Chennai 01, Ambattur, Chennai, Tamil Nadu
Ownership
CapitaLand India Trust with CapitaLand India Data Centre Fund
Unveiled
15 October 2026
Completion target
End-2026, tenant-ready
IT capacity
34 MW
Gross power capacity
53 MW
Gross to IT ratio
1.56 — the highest in the CapitaLand family
Data halls
13, averaging 2.6 MW of IT each
Substation
110 kV dedicated
Site
4 acres; about 600,000 sq ft built, a floor area ratio of 3.4
Planned investment
₹1,940 crore — ₹57.1 crore per MW of IT
Design
High-density, liquid-cooling ready, carrier-neutral, targeting LEED Gold
Counted in this registry
34 MW — additive

2Rs 57.1 crore per megawatt

NTT Kolkata 125 MW, Rs 2,000 cr, 7.5 acresRs 80.0 crSTT Kolkata 26 MW, Rs 450 cr, 5.59 acresRs 75.0 crCapitaLand Chennai 0134 MW IT, Rs 1,940 cr, 4 acresRs 57.1 crNTT NAV2 phase one107 MW, Rs 5,500 cr, 54 acresRs 51.4 crNTT Bengaluru 467.2 MW, Rs 2,400 cr, 8.5 acresRs 35.7 crFive disclosed Indian data centre investments on one scale. Two of the three cheapest are also the two largest by megawatt — scale is the only thing that moves this number.
Figure 1 — disclosed Indian data centre investment per megawatt of IT or phase capacity. Kolkata is expensive because the market is small and the land is cheap but the power is not; Bengaluru is cheap because it is 67 MW in three buildings.
How the Rs 1,940 crore breaks down
BasisCalculationResult
Per megawatt of IT₹1,940 cr ÷ 34 MW₹57.1 crore
Per megawatt of gross power₹1,940 cr ÷ 53 MW₹36.6 crore
Per data hall₹1,940 cr ÷ 13 halls₹149 crore
Per square foot₹1,940 cr ÷ 600,000 sq ft₹32,333 per sq ft
Against NTT NAV2 phase one₹51.4 cr per MW+11%
Against NTT Bengaluru 4₹35.7 cr per MW+60%
Against NTT Kolkata 1₹80.0 cr per MW−29%
The pattern in the ladder

The two cheapest builds in this table are the two largest: Bengaluru 4 at 67.2 MW for ₹35.7 crore a megawatt and NAV2 phase one at 107 MW for ₹51.4 crore. The two most expensive are the two smallest: Kolkata 1 at 25 MW for ₹80 crore and STT Kolkata 2 at 6 MW for ₹75 crore.

Chennai 01 at 34 MW and ₹57.1 crore sits exactly where that logic puts it — mid-sized, mid-cost. There is no Chennai premium visible in the number.

This is the single most useful thing a per-megawatt cost figure does: it tells you whether a market is expensive or a building is small. Most of the time it is the building.

One caveat that changes the reading. ₹1,940 crore is a planned total development investment as stated by the CLINT chief executive, not a certified project cost and not necessarily restricted to this building. Treat the per-megawatt figure as a stated basis rather than an audited one.

3Thirteen halls on four acres

What the building geometry implies
MeasureValueReading
Built area600,000 sq ft / 55,742 m²Published
Site4 acres / 17,424 m²BusinessLine, single source
Floor area ratio3.4Three to four storeys
IT per acre8.5 MWHigh for a four-acre parcel
Gross power per acre13.25 MWAbove AirTrunk Chandivali at 12.9 on a facility basis
Square feet per MW of IT17,647Against NTT’s 13,300 standard
IT per data hall2.6 MWAgainst NTT Bengaluru 4 at 3.2 MW per hall
Halls13The most halls per building in this registry

The floor area ratio of 3.4 says three or four storeys over a nearly full four-acre footprint. That is the same vertical logic as every other urban Indian build in this file, at a smaller scale: there is no way to put 34 MW of IT on four acres at ground level.

13 data halls averaging 2.6 MW is the more interesting number. It is the most halls in any single building this registry has recorded, and it is a deliberate design choice: smaller modules let a single-tenant, high-density AI deployment be isolated without stranding the rest of the building. NTT’s Bengaluru 4 runs 7 halls at 3.2 MW; CapitaLand runs 13 at 2.6 MW. Same total concept, twice the granularity.

Why hall count is a sales number, not an engineering one

A building with 13 halls can lease to 13 tenants of 2.6 MW, or to one tenant across all of them. A building with three halls of 11 MW can only do the second.

That flexibility is worth a premium in a market where the largest buyers are hyperscalers who want whole buildings and the fast-growing buyers are AI tenants who want two halls. Chennai 01 is built to serve both, which is why it costs ₹57 crore a megawatt rather than ₹35 crore.

4The Ambattur corridor

Published capacity in and around Ambattur
RecordMWScopeStatus
AirTrunk MAA1, Ambattur (PRJ-183)128Facility, at leastStage not stated
CtrlS Chennai park72PublishedOperating and expanding
Iron Mountain Chennai42AnnouncedTwo buildings, 23.2 and 19 MW
NTT Chennai 2 (PRJ-167)34.8IT, additive17.4 MW per building, live
CapitaLand Chennai 0134IT, additiveTenant-ready end-2026
Ambattur corridor published310.8Mixed scopes—
Tamil Nadu counted in this registry296.6IT, additive rowsThe corridor exceeds the state

310.8 MW published in one industrial suburb against 296.6 MW counted across all of Tamil Nadu. The corridor is the state, and the numbers are not on the same basis: the corridor figure includes facility capacity and unverified stages, the state figure is IT load from additive rows.

Chennai 01 is one of the few records in the corridor stating both scopes. Its 34 MW of IT is 11.5% of the state’s counted capacity — from a building that does not yet have a tenant.

The 110 kV substation is also worth marking. Every hyperscale site in this registry connects at 220 kV or above — AirTrunk MAA1 next door runs 230 kV, Hyderabad runs 440/220 kV. A 110 kV connection for 53 MW of gross power is a mid-size urban connection, and it is the physical reason this building is 34 MW and not 100.

5Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
New, itemised, liquid-cooling-ready Chennai capacity with 13 lettable modules and a disclosed cost
Where the capacity is
Ambattur, Chennai. 34 MW IT, 53 MW gross, 13 halls, tenant-ready end-2026
Who holds the answer
CapitaLand India Trust and CIDCF; the leasing team is in market now
The one question
What is available per hall, and at what rack density and term
Why they will answer it
A building targeting tenant-readiness in two months is actively selling
Gridvik estimate
First tenants announced within six months of tenant-readiness. Labelled an estimate
What changes it
A named tenant, a hall-level availability table, or a commissioning notice
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

6Limits and open questions

  • Nothing is commissioned. Unveiled October 2026; tenant-ready targeted end-2026.
  • ₹1,940 crore is a planned development investment stated by the CLINT chief executive, not an audited project cost, and may not cover this building alone.
  • The four-acre parcel is single-source from BusinessLine and is not in the operator release.
  • 600,000 sq ft is a built-up figure, not technical hall area, so 17,647 sq ft per MW overstates the floor per megawatt inside the halls.
  • 34 MW is IT capacity and is what the registry counts; 53 MW gross is never added to a total.
  • Liquid-cooling readiness is an operator statement with no published density ceiling per hall.
  • What would close it. A tenant announcement and a hall-level density specification.

7Sources

Sources: the CapitaLand Investment release of 15 October 2026; The Hindu BusinessLine coverage of 15 October 2026; the CapitaLand India Data Centre Fund release of 31 December 2025; CapitaLand data centre listing pages; and CLINT results disclosures.