L&T Vyoma Mahape — the 100 MW campus planLarsen & Toubro Vyoma · Mahape, Navi Mumbai, Maharashtra · 100 MW campus plan · 40 MW named · Basis not disclosed · Counts 0

Record PRJ-202Maharashtra — Navi MumbaiTier C — plan stage, not itemised5 public sources checkedAdditive: no — campus plan, counts 0
Plan stage only40 + 40 does not equal 10040 MW counted via PRJ-201No land area for the campusBasis IT or gross not stated
100MW
Campus plan
40MW
Named first phase
80MW
Two buildings at 40 each
20MW
Unexplained
2.45acres
Site of phase one
0MW
Counted at campus level

The Mahape data centre L&T Vyoma broke ground on in January 2026 is the first phase of a 100 MW campus planned in Navi Mumbai. That is the entire public description of the campus: 100 MW, planned, basis not stated. Six months later the company described the campus as two facilities of about 40 MW each, which totals 80 MW and leaves 20 MW unaccounted for. No campus land area is published. This registry counts the 40 MW of phase one through its own record and counts zero here, so a plan cannot inflate a state total.

1At a glance

Plan
100 MW data centre campus at Mahape, Navi Mumbai
Operator
Larsen & Toubro Vyoma, moving into Vyoma.AI Limited
Announced
21 January 2026, alongside the phase-one Bhoomi Pujan
Phase one
40 MW IT load on 2.45 acres, G+4 — record PRJ-201
Later description
Two facilities of about 40 MW each
Arithmetic
40 + 40 = 80, against a stated 100
Basis
IT or gross not stated for the campus figure
Campus land area
Not published
Phase schedule
Not published
Status
Plan stage; only phase one has a groundbreaking date
Counted in this registry
0 MW — non-additive; phase one is counted via PRJ-201

2Forty plus forty is eighty

What each source says about the campus
SourceCampus figureDetail
L&T Vyoma release, 21 Jan 2026100 MWPart of a 100 MW campus planned in the city
The Hindu, 21 Jan 2026100 MWFirst phase of a planned 100 MW campus
Inc42, Aug 2026two facilities, ~40 MW eachCampus potentially scaling up to 100 MW
Operator specification page40 MW ITPhase one only; no campus figure
This registry0 MWPlan not counted; phase one counted separately

The gap is 20 MW — one fifth of the plan — and it is not a rounding issue. Either there is a third building nobody has described, or the second building is larger than 40 MW, or the 100 MW is a site ceiling that includes capacity not yet designed.

Every one of those is a normal way for a developer to talk. None of them is a facility, and none can be counted. This is the fourth campus-scale plan in this registry where the headline exceeds the named components — the L&T 100 MW, the AirTrunk 601 MW against 600, the Iron Mountain 150 MW against 147.5, and the Raigad 3 GW against nothing.

The pattern worth naming

Indian campus announcements are consistently stated as a round number, named in smaller pieces. 100 MW becomes two 40s. 250 MW becomes 148 plus a Chennai allocation. 600 MW becomes five cards.

In most cases the round number is a genuine site ceiling and the pieces are what will actually be built. Both are useful; only one is capacity.

A data product that publishes the round number alone is a news feed. One that publishes the round number, the named pieces and the difference between them is a diligence tool.

3How much land a 100 MW campus needs

No campus land area is published, so it has to be inferred from the operator’s own phase-one density of 16.3 MW per acre.

Land implied at three densities
Density assumptionDensityLand neededBasis
L&T’s own phase-one density16.3 MW per acre6.1 acres40 MW on 2.45 acres
AirTrunk BOM2, same node9.0 MW per acre11.1 acres120 MW on 13.3 acres
CapitaLand Chennai, four acres gross13.3 MW per acre7.5 acres53 MW gross on 4 acres
Likely range—6 to 11 acresDensity dependent

Six to eleven acres in Mahape is not a small parcel. The MIDC industrial belt at Mahape and the neighbouring nodes are built up, and the 2.45 acres used for phase one is consistent with buying infill plots rather than assembling a greenfield campus.

Which is the most likely explanation for the missing 20 MW: a campus plan that depends on land not yet acquired. If the site exists, the plan is credible; if it does not, the 100 MW is a target.

4The Mahape node

Published capacity in Mahape
RecordMWStatus
AirTrunk BOM2 Mahape (PRJ-181)120Facility, at least; stage unverified
L&T Vyoma campus plan (this record)100Plan; 40 MW with a groundbreaking
Mahape published total220Mixed scopes and stages
Maharashtra counted total786.4IT load, additive rows only
Mahape as a share28%Of the state’s counted capacity

220 MW published in one node of Navi Mumbai — 28% of everything Maharashtra has counted — and none of the L&T figure exists yet.

This is the same finding the registry recorded on PRJ-181: the Mahape to Airoli belt publishes something close to 600 MW against roughly 30 MW live. Adding a 100 MW plan to a 120 MW claim does not change the ratio; it confirms it.

What does change is the competitive picture. AirTrunk at 120 MW and L&T at 100 MW in the same node means Mahape is no longer a secondary Navi Mumbai location. It is where the next phase of the market is being built, and both of them need the same substation capacity.

5Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
The campus plan and the 20 MW gap — the right question to ask any developer in this node
Where the capacity is
Mahape, Navi Mumbai. 40 MW in phase one; 100 MW planned
Who holds the answer
L&T Vyoma / Vyoma.AI Limited
The one question
Where is the land for the other 60 MW, and when is phase two dated
Why they will answer it
A listed parent must disclose material capital commitments
Gridvik estimate
Phase two will not be dated before phase one delivers. Labelled an estimate
What changes it
A campus land area, a phase two groundbreaking, or a second building specification
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

6Limits and open questions

  • Plan stage. No land area, no phase schedule, no capex and no basis for the 100 MW figure.
  • The named components total 80 MW against a stated 100 MW. Twenty megawatts unaccounted for.
  • Six to eleven acres is inferred from three density assumptions and is not a disclosed figure.
  • The campus figure may be a site ceiling rather than a build plan. Not stated.
  • Zero megawatts counted at campus level. The 40 MW phase one is counted once, through PRJ-201.
  • What would close it. A land area and a phase schedule. Either alone would resolve half the page.

7Sources

Sources: the Larsen & Toubro Vyoma press release of 21 January 2026; The Hindu and ETV Bharat coverage of the same date; Inc42 coverage of the Vyoma.AI restructuring and campus plan; and the L&T Vyoma Mumbai data centre specification page.