Programme record · Verified 26 Oct 2026

Colt DCS and RMZ — the India joint ventureColt Data Centre Services and RMZ · Mumbai and Chennai · US$1.7bn · 250 MW programme · 22 MW live · Mumbai 3 64 MW · Counts 0

Record PRJ-204National — Mumbai and ChennaiTier B — programme, itemised in part8 public sources checkedAdditive: no — programme, counts 0
Mumbai 3 fully pre-let before construction220 kV GIS and liquid cooling specified22 MW live against a 250 MW programmeNo completion date for Mumbai 3Customer not named
250MW
Programme target
US$1.7bn
Committed capital
US$6.8m
Per MW
22MW
Live today
64MW
Mumbai 3
148MW
Campus potential

The Colt DCS and RMZ joint venture committed US$1.7 billion in November 2024 to build 250 MW of data centre capacity across Mumbai and Chennai. That is US$6.8 million per megawatt — ₹60.1 crore — the highest disclosed programme rate in this registry. At the Navi Mumbai campus, Mumbai 1 and Mumbai 2 run 22 MW. Mumbai 3 adds 64 MW of AI-ready capacity with a 220 kV GIS substation on site, taking the campus to 86 MW against a potential 148 MW. Construction began on 15 October 2026, and the building was fully pre-let before it started — the first hyperscale customer signed and not named.

1At a glance

Joint venture
Colt Data Centre Services and RMZ — 50:50
RMZ vehicle
RMZ Digital Infrastructure Partners
Announced
November 2024
Commitment
US$1.7 billion — about ₹15,028 crore at ₹88.40
Capacity target
250 MW across Mumbai and Chennai
Rate per megawatt
US$6.8 million = ₹60.1 crore
Navi Mumbai campus
Mumbai 1 and Mumbai 2 live since September 2023; Mumbai 3 under construction
Live capacity
22 MW
Mumbai 3
64 MW AI-ready; 64 MW of secured contracted power; fully pre-let
Campus at Mumbai 3 completion
86 MW
Campus potential
148 MW at full development
Power
220 kV GIS substation located on campus
Cooling
Hybrid: air plus direct liquid-to-chip, closed loop, near-zero wastewater
Third site
Reportedly Vizag, undated and unquantified
Counted in this registry
0 MW — programme record, counts 0

2US$6.8 million per megawatt, the top of the market

The programme rate against every other disclosed rate in the file
ProgrammeRate per MW of IT₹ crore per MWBasis
Colt DCS–RMZUS$1.7bn for 250 MW₹60.1 croreTwo cities, multiple buildings
CapitaLand Chennai 01₹1,940 cr for 34 MW₹57.1 croreSingle building, four acres
AirTrunk IndiaUS$6.0m per MW₹53.0 croreFive sites, 601 MW
NTT NAV2 phase one₹5,500 cr for 107 MW₹51.4 croreFour data centres, 54 acres
NTT Bengaluru 4₹2,400 cr for 67.2 MW₹35.7 croreThree buildings, 8.5 acres
Market band—₹51.4 to ₹60.1 croreA 17% spread

Being at the top of a 17% band is not a red flag. It is a description of what this programme buys: urban infill land in Navi Mumbai and Ambattur, 220 kV power, and a fully pre-let building in an AI-ready configuration. All three of those cost more than a greenfield campus in Devanahalli.

The comparison that matters commercially is NTT Bengaluru 4 at ₹35.7 crore per megawatt — 41% cheaper. That is not an efficiency gain by NTT. It is the difference between three buildings on 8.5 acres of Devanahalli land and two buildings on constrained parcels in the two most contested data centre corridors in India.

What the top of the band tells you

A 41% spread between the cheapest and most expensive disclosed Indian build is a land and power spread, not a construction spread. Contractors charge similar rates in both cities.

That means the per-megawatt cost of Indian data centre capacity is a function of where far more than how. Which is why the land-efficiency ratio, megawatts per acre, is the single most predictive number in this registry.

A tenant paying rent in Navi Mumbai is paying for a substation and a fibre route that Devanahalli does not have. That is the whole premium.

3Twenty-two, then eighty-six, then one hundred and forty-eight

JV programmeUS$1.7bn across Mumbai and Chennai250 MWNavi Mumbai at full buildCampus potential148 MWNavi Mumbai, Mumbai 3 completeMumbai 1 and 2 plus Mumbai 386 MWLive todayMumbai 1 and Mumbai 222 MWTwo hundred and fifty megawatts committed, twenty-two running. The red bar is what happens when one building lands.
Figure 1 — the Colt DCS and RMZ programme from what runs today to what has been committed. The gap between the top bar and the bottom bar is 228 MW that does not exist.
The Navi Mumbai campus, stage by stage
StageMWEvidence
Mumbai 1 and Mumbai 222Live since September 2023
Mumbai 3 at completion64Construction began 15 October 2026; fully pre-let
Campus at Mumbai 3 completion86Company statement
Remaining campus potential62Undated, unbuilt, undesigned
Campus at full development148Company statement
JV programme across Mumbai and Chennai250US$1.7 billion commitment
Implied Chennai and third-site allocation102Derived: 250 − 148

Only 15% of the programme is running. One building — Mumbai 3 at 64 MW — takes the campus from 22 MW to 86 MW, a 2.9-fold increase, and it is the only facility in the programme with a construction date attached.

The remaining 62 MW of campus potential and the 102 MW implied for Chennai and a third site have no buildings, no dates and no designs. For a JV that has been running since November 2024, two years with one building under construction is a slow start — and it is a more useful fact than the US$1.7 billion headline.

4Fully pre-let before construction

This is the most commercially significant sentence in the announcement, and it is easy to read past: Mumbai 3 was fully pre-let before construction started.

What pre-letting 64 MW before construction means
ImplicationHoldsWhy it matters
Revenue is contracted before capital is spentYesThe JV is not building speculatively
The customer is a hyperscalerYesNamed by neither party
64 MW is described as secured contracted powerYesThe megawatts are sold, not available
The building is AI-configuredYesHybrid air plus direct liquid-to-chip cooling
Which means a specific rack densitynot disclosedLiquid cooling implies above 30 kW per rack
Commercial terms and term lengthnot disclosedThe number that would price this asset
Identity of the tenantnot disclosedConcentration risk cannot be assessed

A fully pre-let building is a different asset class from a speculative one. It is financeable at construction cost, it carries a named counterparty for the term, and its value is set by the lease rather than by the market.

The absence of the tenant name and the lease term is the whole gap. Sixty-four megawatts of AI-ready capacity in Navi Mumbai is pre-sold, and the market does not know to whom or for how long.

The engineering is also more specific than most. A 220 kV GIS substation on campus is the same voltage class as NTT’s Mumbai builds and AirTrunk’s Airoli and Mahape sites, and it is what 64 MW requires. The closed-loop cooling design with near-zero wastewater is a real differentiator in a city where water for cooling is contested.

5The Ambattur overlap

Ambattur, Chennai — published capacity by operator
RecordMWBasis
AirTrunk MAA1 (PRJ-183)128Facility, at least; stage not stated
Colt DCS–RMZ Chennai allocationup to 102Derived; not separately disclosed
CtrlS Chennai park72Published capacity
Iron Mountain Chennai42Announced, two buildings
NTT Chennai 2 (PRJ-167)34.8IT, live
CapitaLand Chennai 01 (PRJ-198)34IT, tenant-ready end-2026
Published in the corridor today310.8Excluding Colt DCS–RMZ
With this JV’s Chennai shareup to 412.8Upper bound
Tamil Nadu counted in this registry296.6IT load, additive rows

Up to 412.8 MW published in one industrial suburb, against 296.6 MW counted across the whole of Tamil Nadu. Ambattur is, on published numbers, larger than the state that contains it.

Six operators on one corridor is a different competitive dynamic from a market with one dominant park. It means the interconnection fabric and the local substations are shared infrastructure, and it means a tenant has real choice without leaving the district — which compresses rent.

It also means the corridor’s published figure is composed almost entirely of facility capacity and unverified stages. The only IT-load figures in the list are NTT's 34.8 MW and CapitaLand's 34 MW — 68.8 MW of the 310.8. Everyone else is quoting a bigger number on a looser basis.

The Ambattur lesson

When six operators stack into one corridor, the published number becomes a marketing equilibrium rather than a measurement. Each one has to be at least as large as the last announcement.

The two operators that publish IT load are the two that look smallest. They are not smaller; they are measured.

That single effect is worth more to a buyer than any individual capacity figure in this file.

6Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
A fully pre-let AI-ready building with 220 kV power in the most contested corridor in India
Where the capacity is
Navi Mumbai campus — 22 MW live, 64 MW building, 148 MW potential; Ambattur, Chennai for the balance
Who holds the answer
Colt DCS and RMZ Digital Infrastructure Partners, as a 50:50 joint venture
The one question
Who is the Mumbai 3 tenant, and what is the lease term
Why they will answer it
A pre-let of 64 MW is the JV’s principal asset and will surface in RMZ disclosures or refinancing
Gridvik estimate
Mumbai 3 capacity in 2028 on a normal 24-month build from October 2026. Labelled an estimate
What changes it
A completion date, a named tenant, or an RMZ capital raise against the asset
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

7Limits and open questions

  • US$1.7 billion is a programme commitment, not a facility cost. No capex is disclosed for Mumbai 3.
  • No completion date is given for Mumbai 3 by either party.
  • The tenant is not named, and no lease term is published, so concentration risk cannot be assessed.
  • 22 MW is derived by subtracting Mumbai 3’s 64 MW from the stated 86 MW campus figure. It is not separately disclosed.
  • The Chennai and third-site allocation of up to 102 MW is derived from 250 minus 148 and is not a disclosed figure.
  • Vizag is reported, not confirmed, and is not in the 250 MW programme as announced.
  • Appendix: the 250 MW is a target across all phases in two cities and is never additive to a state or national total in this registry.
  • What would close it. A tenant name, a lease term and a completion date.

8Sources

Sources: the Colt DCS and RMZ joint venture release of 19 November 2024; the Mumbai 3 construction announcement of 15 October 2026; PR Newswire, Yahoo Finance and ET Datacenters coverage of both; Datacenter Magazine on the pre-let; VCCircle on the joint venture structure; and the Colt DCS ownership and investment page.