Facility record · Verified 26 Oct 2026

Sify Noida 02 — Greater Noida expressway corridorSify Technologies · Noida, Uttar Pradesh · 25.92 MW live · 130+ MW full build · 13,000+ racks · 220 kV substation · 130 kW per rack

Record PRJ-218Uttar Pradesh — NoidaTier B — operating, capacity scopes conflict8 public sources checkedAdditive: yes — 30 MW counted
13,000+ racks at 130 kW each220 kV on-premise substationNVIDIA DGX-Ready liquid coolingSix published capacities250 MW on 13,000 racks is 19 kW, not 130
25.92MW
Live power
133MW
Full build
13,000+
Racks
220kV
Substation
130kW
Per rack ceiling
3
Towers

Noida 02 is Sify’s second hyperscale campus in Delhi-NCR, about a kilometre from Noida 01, with three scalable towers, more than 13,000 racks, a dedicated on-premise 220 kV substation and NVIDIA DGX-Ready certification for liquid cooling at 130 to 200 kW per rack. It is the largest AI-ready campus in Northern India by its own description. Its capacity has been published at 25.92 MW of live IT power as of 30 June 2025, 30 MW on the current portfolio card, 78 MW planned, 130 to 133 MW at full build, and 180 MW scalable. Six figures for one campus. The registry counts 30 MW — the highest figure that describes a building rather than a plan — and this page explains why the other five matter.

1At a glance

Facility
Noida 02, Noida, Uttar Pradesh, Delhi-NCR
Operator
Sify Technologies, via Sify Infinit Spaces
Position
About 1 km from Noida 01, interlinked over four diverse fibre paths
Towers
Three, designed for horizontal and vertical expansion
Live IT power
25.92 MW as of 30 June 2025
Portfolio card figure
30+ MW
Planned
78 MW
Full build
130+ MW; 133 MW on a third-party specification
Scalable
180 MW per an August 2026 launch statement
Racks
13,000+
Substation
220 kV dedicated on-premise
AI certification
NVIDIA DGX-Ready for liquid cooling, certified 2025
Density
Up to 130 to 200 kW per rack; card states 130 kW
Inaugurated
March 2025, by the Chief Minister of Uttar Pradesh
Counted in this registry
30 MW — additive

2Six capacities for one campus

Scalable, per the AI lab launchAugust 2026180 MWFull build, DataCenterMap2026133 MWThree towers, Sify Europe site2026130+ MWPlanned, DataCenterMap202678 MWPortfolio cardOctober 202630+ MWLive power30 June 202525.92 MWSix figures for one campus, from 25.92 MW of live power to 180 MW of scalability. The two red bars are the only ones describing a building.
Figure 1 — every published figure for Noida 02 on one scale. Note the gap between 25.92 MW live and 133 MW full build: the campus is roughly one fifth built.
What each figure measures
FigureDateMWScope and source
Live IT power30 Jun 202525.92Sify Infinit Spaces, dated
Portfolio cardOct 202630+Largest AI campus in Northern India
Planned202678Third-party specification listing
Full build2026130 to 133Three towers, Sify and third-party
ScalableAug 2026180Sify operations head at an AI lab launch
Older blogMar 202678Three towers, total capacity 78 MW
This registry—30Highest figure describing a building

The 180 MW figure is the newest and the largest and it comes from the most operational source of all — the head of data centre operations, at an event. He described 130 MW of available power capacity that can be scaled up to 180 MW, which resolves most of the confusion in one sentence: 130 is the built-and-designed ceiling, 180 is the site ceiling.

Which leaves three genuine figures: 25.92 MW live, 130 MW designed, 180 MW site ceiling. The 30, 78 and 133 are intermediate readings of the same three.

Which number the registry counts, and why

The card says 30+ MW and the dated figure says 25.92 MW live. Counting 30 MW treats the operator’s current claim as capacity; counting 25.92 MW treats a fourteen-month-old measurement as the truth.

The registry counts 30 MW because it is the operator’s current published capacity for a named campus, and because understating is the more dangerous error in a market where the counted total is already a floor.

But the page publishes 25.92 MW as the last measured figure beside it, so a reader who wants the conservative number has it. Both disciplines at once is the only honest option.

3Thirteen thousand racks, and a contradiction

The rack count is where the disclosed numbers stop agreeing with each other in a way that can be tested with arithmetic.

What 13,000 racks implies at each published capacity
CapacityRackskW per rackReading
At 25.92 MW live13,000 racks2.0Enterprise cabinets, mostly unbuilt halls
At 30 MW on the card13,000 racks2.3Barely above the live figure
At 130 kW per rack, full build racks13,0001,690 MWSix times the campus ceiling
At 130 MW full build13,000 racks10.0Inconsistent with the 130 kW claim
At 130 MW and 130 kW per rack1,000 racks130.0The arithmetic that actually works
At 180 MW and 130 kW per rack1,385 racks130.0The site ceiling at AI density

Something has to give. 13,000 racks multiplied by 130 kW is 1,690 MW — six times the campus ceiling. So the density and the rack count cannot both be true for the same halls.

The resolution is almost certainly that 13,000 racks is the enterprise-hall count across three towers, and 130 kW per rack is the capability of the NVIDIA-certified liquid-cooled pods inside them. Different products, one campus. Sify has built for both markets simultaneously.

That is a sensible strategy and it is completely invisible in any single number. A campus quoting 13,000 racks and 130 kW per rack is describing two businesses, and every published capacity figure split the difference somewhere.

The test any buyer should run on a rack claim

Multiply the rack count by the advertised density. If the result exceeds the published megawatts by more than about 30%, the two numbers describe different products.

Applied across this registry, that test separates 7,000 racks at 15 kW (Yotta NM1: 105 MW implied against 52 MW published) from 13,000 racks at 130 kW (Noida 02: 1,690 MW implied against 130 MW published). Both are legitimate; neither is what a naive reading suggests.

It is a thirty-second calculation and it makes almost every Indian AI capacity claim auditable. Nothing else in this file does that as cheaply.

4Noida 01 and 02 as one resilience pair

The pair as a commercial product
ElementDetailWhy a tenant pays for it
DistanceAbout 1 kmClose enough for synchronous replication
FibreFour diverse pathsPhysical route diversity between the campuses
Power domainsSeparate substationsIndependent failure of one does not take the other
Combined capacity41 MW live and designedNoida 01 at 10.96 plus 30
CertificationNoida 02 is NVIDIA DGX-ReadyAI workloads land in the new tower
InterconnectDirect to hyperscalers, OTT and cloud connectThe reason enterprises choose Noida at all

A kilometre is a deliberately chosen distance: far enough that a single substation failure, fire or flood does not take both buildings, close enough that synchronous replication between them stays under a millisecond.

That is the product Delhi-NCR enterprises actually buy — two sites, one metro, one latency budget — and it is why the Noida cluster commands rents that a single greenfield campus outside the city cannot.

Combined, the two campuses are 41 MW of counted capacity. That would be 12.4% of Uttar Pradesh’s 331.1 MW from one operator in one city, before Yotta’s 180 MW of Greater Noida announcements are considered.

5The AI specification

Noida 02 is the most AI-specified building in Northern India and the detail is worth recording precisely.

The AI-ready specification
ItemDetailSignificance
NVIDIA certificationDGX-Ready, liquid coolingCertified 2025; Rabale was first in India, 2024
Density supported130 to 200 kW per rackAgainst 3 kW in an enterprise hall
CoolingLiquid cooling capableAir cooling stops being economic around 25 kW
Substation220 kV dedicatedThe connection a 130 MW campus requires
Commercial modelPay-per-use GPU colocationCompetes with GPU cloud, not with colocation
InaugurationMarch 2025By the Chief Minister of Uttar Pradesh
Green energyPart of Sify’s 300+ MW contracted portfolioA hyperscale procurement gate

The 220 kV substation is the physical fact that makes the rest credible. Every published mega-campus in this registry connects at 220 kV or above — AirTrunk in Mumbai and Hyderabad, CapitaLand in Chennai, NTT, Colt, and now Sify. A campus quoting 130 MW without a switchyard of that class is making a land claim.

Pay-per-use GPU colocation is the commercial restructure worth noting. A traditional landlord rents racks at a fixed rate for a decade. A GPU colocation provider rents compute by the hour and absorbs utilisation risk. That is a technology business with a data centre attached, and it is where Sify, Yotta and the AI neoclouds are all converging.

For this registry the distinction has one practical consequence: a megawatt in Noida 02 is not worth the same as a megawatt in Noida 01, even though both are Sify and both are in Noida. One is leased to enterprises, the other is sold by the GPU-hour.

6Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
The largest AI-ready campus in Northern India, with 220 kV power and NVIDIA liquid-cooling certification
Where the capacity is
Noida, Uttar Pradesh. 25.92 MW live, 130 MW designed, 13,000+ racks
Who holds the answer
Sify Technologies, Delhi-NCR sales and the AI/neocloud team
The one question
How much of the 25.92 MW is unsold, and what GPU density is available per hall
Why they will answer it
A listed company selling both enterprise colocation and GPU capacity
Gridvik estimate
The enterprise halls are largely let; the AI pods are the growth. Labelled an estimate
What changes it
A utilisation disclosure, or an anchor GPU tenant announcement
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

7Limits and open questions

  • Six published capacities — 25.92, 30, 78, 130, 133 and 180 MW. The registry counts 30 MW.
  • 25.92 MW is dated 30 June 2025 and is the last measured figure; the card figure is undated.
  • 13,000 racks and 130 kW per rack cannot both describe the same halls — the product implies 1,690 MW against a 130 to 180 MW campus.
  • 180 MW is a site ceiling stated verbally at an event, not in a filing.
  • No floor area or site area is published, so no land-efficiency figure exists.
  • 30 MW is counted, the highest figure describing a building, with 25.92 MW published beside it.
  • What would close it. A per-tower schedule with megawatts and dates.

8Sources

Sources: the Sify Noida 02 data centre page; the Sify data centre portfolio page; Sify Infinit Spaces data centre pages with the 30 June 2025 capacity date; the Sify Europe data centre pages; Sify’s Noida 02 factsheet of September 2024; the Sify blog on the Noida campus; VAR India on the August 2026 AI lab launch; DataCenterMap specifications; The Hindu and Indian Infrastructure on the March 2025 inauguration.