Get Free Teaser
Campus record · Verified 26 Oct 2026

Sify Rabale — Mumbai 03 campusSify Technologies · Rabale, Navi Mumbai, Maharashtra · 100 MW headline · 96.94 MW built · 377+ MW design · 12 towers planned, 5 operational

Record PRJ-221Maharashtra — Rabale, Navi MumbaiTier B — operating, headline against built against design7 public sources checkedAdditive: no — campus aggregate, counts 0
Five towers operational, 96.94 MW built100 MW headline is the built figure rounded377+ MW design on 12 towersA 200 MW brochure figure has disappeared
100MW
Headline
96.94MW
Built
377MW+
Design
12
Towers planned
5
Towers live
99MW
Green power

Rabale, Sify’s Mumbai 03 campus, is the operator’s largest site: five operational towers holding 96.94 MW of built IT power as of 30 June 2025, seven more towers designed, and a full-build figure of 377+ MW. The current portfolio card headlines it at 100 MW — which is 96.94 rounded, not a new number. A September 2024 brochure put the campus at 200 MW with a ten-tower plan; both the number and the tower count have since changed. This record is a campus aggregate and counts zero megawatts: the towers are counted on their own records, and adding the headline to them would double-count the same steel.

1At a glance

Campus
Sify Mumbai 03, Rabale, Navi Mumbai, Maharashtra
Operator
Sify Technologies, via Sify Infinit Spaces
Site
Plot R-847, TTC Industrial Area, Rabale, Navi Mumbai 400 701
Status
Live and expanding
Portfolio card headline
100 MW IT power, October 2026
Built
96.94 MW across towers 1 to 5, as of 30 June 2025
Design, full build
377+ MW IT power
Towers
12 planned, 5 operational; towers 6, 7, 11 and 12 stated for 2026, towers 8 to 10 in planning
Withdrawn figure
200 MW on a September 2024 brochure describing a ten-tower plan
Substations
110 kV on-premise for towers 1 to 3; 220 kV GIS for towers 4 to 6
Green power
99 MW of contracted solar and wind; up to 70% renewable share
Build standard
G+8 towers, 6,300 mm floor to floor, 2,100 kg per sq m floor load
Security
K4-rated perimeter, 10 levels of access control
Counted in this registry
0 MW — campus aggregate, not additive

2One campus, five published figures

Design, full build of 12 towerscurrent operator pages377+ MWBrochure of September 202410-tower plan, since withdrawn200 MWPortfolio card headlineOctober 2026100 MWBuilt across five towersas of 30 June 202596.94 MWFactsheet of 2022, five towerssame five towers, four years earlier85 MWFrom 85 MW to 377 MW for one address. The two red bars are the same five towers measured eighteen months apart.
Figure 1 — every capacity Sify and its subsidiaries have published for the Rabale address. The 200 MW bar is the one that no longer appears anywhere.
Each figure, its scope and its date
FigureSource and dateMWScope and notes
Design, full buildCurrent pages377+Twelve towers. Superseded the 200 MW brochure without explanation
BrochureSep 2024200Ten-tower plan, 15,000+ racks, Tower 5 at 38.8 MW
Portfolio cardOct 2026100Current headline; equals 96.94 rounded
Built30 Jun 202596.94Five towers, per Sify Infinit Spaces
Factsheet202285Five towers, 10,000+ racks, plus 100 MW from three more
This registry—0Campus aggregate; towers counted individually

The headline is not a forward claim. 100 MW is 96.94 MW rounded up by 3.2%, and it describes five buildings that already exist. That makes Rabale unusual in this registry: most operators lead with a design number and bury the built one. Sify leads with the built one and buries the design number at 377 MW.

Which raises the more useful question. If 100 MW is the five-tower total, then 277 MW of the design figure sits in seven towers that do not yet exist — and Sify has been describing those towers since at least 2022, when a factsheet said three additional towers would add 100 MW of IT capacity.

The number that should worry a reader

In 2022 Sify said three more towers would add 100 MW. In 2026 the campus has five towers and the next four (6, 7, 11 and 12) are still described as becoming operational in 2026 — the same year, with no tower of that batch apparently live.

A 2022 brochure also said towers 6 and 7 would be operational in early 2025. They are still listed as upcoming.

Two schedule slips on the same two towers, four years apart. The design figure of 377 MW is credible as a site capability. It is not a schedule, and nothing in the public record supports treating it as one.

3The 200 MW that disappeared

The September 2024 Rabale brochure is the most detailed public document Sify has issued on this campus, and it contains a figure that appears nowhere in the 2026 record: 200 MW of IT capacity, on a ten-tower campus, with 15,000+ racks, 99 MW of solar and wind, and Tower 5 at 38.8 MW over 2,500+ racks. It also states that each tower is designed for up to 40 MW and 2,000+ racks.

The brochure against the current record
ItemSeptember 2024 brochureOctober 2026 pages
Campus IT capacity200 MW100 MW headline, 377+ MW design
Towers1012
Racks15,000+Not published on the campus card
Tower 5 IT power38.8 MW43.2 to 43.3 MW
Renewable shareUp to 79%Up to 70%
Towers 6 and 7Operational early 2025Operational by 2026

None of these are errors in themselves — a plan can be revised. What they establish is that no single public figure for Rabale has survived four years unchanged, including the tower count and the renewable share, which both moved down.

The renewable share is the least-noticed item and the one with the largest commercial consequence. 79% to 70% is a 9-point drop in a claim that hyperscale tenants audit. Sify’s contracted green portfolio is 300+ MW nationally, so the direction is right; the campus-level percentage simply no longer matches the brochure that was used to sell it.

How to read a campus headline in this market

Ask for three numbers, not one: built, designed, and site ceiling. Rabale answers all three — 96.94, 377 and 12 towers. Most Indian campus announcements answer only the second.

Then check whether the headline equals the built figure. At Rabale it does, and that is a good sign: 100 MW is a statement about steel on the ground, not about a permit.

The weakness is entirely in the schedule, where the record shows two slips on the same towers. Capacity claims here are conservative. Delivery claims are not.

4Towers, substations and the twelve-tower plan

The twelve-tower plan as published
TowersStatePower and substation
Towers 1 to 3Operational110 kV on-premise substation
Tower 4Operational220 kV GIS substation
Tower 5Operational, G+8220 kV GIS; designed for 43.3 MW
Towers 6, 7, 11, 12Stated operational by 2026220 kV GIS serves towers 4 to 6
Towers 8, 9, 10In planningEach tower designed for up to 40 MW and 2,000+ racks

The substation schedule is the most concrete evidence in the whole record and it deserves to be read closely. An operator does not build a 220 kV GIS switchyard for five towers. The 2022 factsheet described the 220 kV GIS as covering towers 4 to 10; the current page says towers 4 to 6. Either way, the switchyard was sized for a campus roughly three times the built capacity, and that is the strongest argument that the 377 MW design figure is a real engineering intent rather than a marketing ceiling.

It also sets the physical limit. At 40 MW a tower, ten towers is 400 MW and twelve is 480 MW — so 377 MW across twelve towers implies an average of 31.4 MW a tower, slightly below the stated per-tower design. The figures are coherent.

What 377 MW would require, and what exists
TestResultReading
Racks at 15 kW per rack25,133The 15,000+ rack brochure count covers built towers only
Racks at the 10 to 13 kW stated for towers 7 to 1029,000 to 37,700Consistent with a twelve-tower campus
Built-to-design ratio26%96.94 of 377 MW — roughly one tower in four
Towers delivered of plan5 of 1242%, over a plan that dates to at least 2022

Rabale is about a quarter built against its own design figure. That single ratio is the most useful thing on this page for anybody modelling Sify’s capacity: the campus can absorb roughly 280 MW of further investment, at the replacement band of ₹51.4 to 60.1 crore per MW, which is between ₹14,400 crore and ₹16,800 crore of future capex on one Navi Mumbai address. Both are arithmetic on published figures, not forecasts.

5Ninety-nine megawatts of green power

Rabale contracts 99 MW of solar and wind, described as delivering up to 70% renewable share. Against 96.94 MW of built IT power that is roughly 1.02 MW of green generation per MW of IT — a ratio worth understanding, because it is not what it looks like.

A data centre drawing 96.94 MW of IT load at a power usage effectiveness of 1.5 draws about 145 MW from the grid. Ninety-nine megawatts of contracted renewable energy covers roughly 68% of that total draw — which is almost exactly the 70% claim, and means the renewable percentage is measured against total facility draw, not IT load. The two numbers corroborate each other.

Energy arithmetic at Rabale
ItemValueBasis
IT power built96.94 MWSify Infinit Spaces, 30 June 2025
Estimated total draw at PUE 1.5145 MWEstimate; Sify does not publish a PUE for Rabale
Contracted solar and wind99 MWOperator, campus page
Renewable share implied68%99 of 145 MW — matches the stated up-to-70% claim
Stated shareUp to 70%Brochure said 79%, current page says 70%

This is the one place in the Rabale record where the numbers close. The renewable claim is arithmetically consistent with the built capacity and a standard PUE. Given how much of the rest of the record has moved, that consistency is worth recording.

It is also the number that will decide whether Rabale wins hyperscale tenants in the second half of this decade. India’s large buyers increasingly procure on renewable share and hourly matching, not on megawatts. A campus at 70% contracted renewable is competitive; a campus that must add 280 MW of future load against the same 99 MW of green supply will need a new power purchase agreement for every tower.

6Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
Navi Mumbai hyperscale capacity on a 12-tower campus with 220 kV GIS and 99 MW of contracted green power
Where the capacity is
Rabale, Navi Mumbai. 96.94 MW built across five towers; 377+ MW designed
Who holds the answer
Sify Infinit Spaces for the asset; Sify Technologies for the tenancy
The one question
Which of towers 6, 7, 11 and 12 is physically under construction today, and what is its committed handover date
Why they will answer it
A listed operator with an IPO process on file and a capex story it needs to substantiate
Gridvik estimate
Roughly 277 MW of unbuilt design capacity, implying ₹14,400 to 16,800 crore of future capex. Labelled arithmetic
What changes it
A tower-level construction update, or a slip on the 2026 delivery date for towers 6, 7, 11 and 12
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

7Limits and open questions

  • Five published capacities — 85, 96.94, 100, 200 and 377 MW. The registry counts zero because the towers are counted individually and this is an aggregate.
  • 96.94 MW is dated 30 June 2025 and is the only measured figure. The 100 MW headline is undated and equals it rounded.
  • The 200 MW figure is withdrawn without explanation. The tower count also moved from ten to twelve, and the renewable share from 79% to 70%.
  • Towers 6 and 7 have slipped at least once — promised for early 2025 in a 2024 brochure, still upcoming in 2026.
  • No PUE is published for Rabale. The 1.5 used in the energy arithmetic is an estimate and is labelled as one.
  • 96.94 MW may include Tower 5 at design rather than installed power. It is addressed on PRJ-222 and is the most consequential open item in the Sify family.
  • What would close it. A tower-by-tower schedule with megawatts, energisation dates and installed load.

8Sources

Sources: the Sify Rabale data centre page and its 96.94 MW, 43.2 MW and 377-plus MW specifications; the Sify data centre portfolio page; Sify Infinit Spaces Mumbai data centre page dated 30 June 2025; the Sify Europe data centre pages; the Rabale brochure of September 2024 and the MUM03 factsheet of 2022; the Tower 5 to Tower 10 factsheet; and third-party specifications from DataCenters.com, Baxtel and ArusGrid.