Facility record · Verified 26 Oct 2026

Sify Chennai 02 — SiruseriSify Technologies · Siruseri, Chennai, Tamil Nadu · 25.92 MW built · 130+ MW designed · 230 kV substation · Cable landing station · ₹1,882 crore

Record PRJ-224Tamil Nadu — Siruseri, SIPCOT IT parkTier B — operating, built against installed7 public sources checkedAdditive: no — child of PRJ-028, counts 0
Tower B operational, Rated 3, IGBC PlatinumIntegrated cable landing station, 230 kV substation25.92 MW built against 4.32 MW installed₹72.6 cr per MW, above the 51.4 to 60.1 band
25.92MW
Built IT power
4.32MW
Installed, third party
130MW+
Design
₹1,882cr
Initial investment
72.6cr
Per MW IT
130kW
Per rack

Chennai 02 is the most complete data centre Sify has built: an AI-ready hyperscale campus at Siruseri with an integrated cable landing station rated to 2 PBps, four dedicated fibre paths, a dedicated on-premise 230 kV substation, Rated 3 and IGBC Platinum certification, and liquid cooling to 130 kW per rack. Tower B is operational. Sify publishes 25.92 MW of built IT power as of 30 June 2025. On the same date a third-party tracker records 4.32 MW installed — a sixfold difference on one building, from two sources that agree about the date and disagree about the meaning of built. At ₹1,882 crore of disclosed initial investment, the cost per megawatt depends entirely on which denominator you choose: ₹72.6 crore at 25.92 MW, ₹47.0 crore at the 40 MW of power infrastructure, and ₹436 crore at the 4.32 MW a tracker says is installed.

1At a glance

Campus
Sify Chennai 02, SIPCOT IT park, Siruseri, Chennai, Tamil Nadu
Parent
PRJ-028 Chennai campus aggregate; this is the Tower B phase
Operator
Sify Technologies, via Sify Infinit Spaces
Status
Tower B operational from 2025; towers A and C to follow
Built IT power
25.92 MW as of 30 June 2025
Portfolio card
30 MW, October 2026
Installed
4.32 MW, third-party tracker, 30 June 2025
Stated ready for service
26 MW on the Q4 FY24 earnings call
Design, full campus
130+ MW across three towers; 78 MW on an older page
Racks
13,000+
Density
Up to 130 kW per rack, liquid-cooled
Substation
230 kV dedicated on-premise; 40 MW of power infrastructure for this phase
Cable landing station
Integrated, up to 2 PBps, four dedicated fibre paths
Certification
Uptime Rated 3; IGBC Platinum
Investment
₹1,882 crore initial, disclosed by the state
Grid connection
130 MW from the state grid for the full campus
Counted in this registry
0 MW — included in the PRJ-028 campus aggregate

2Twenty-five point nine two and four point three two

Two figures, one date, two meanings of built
FigureSource and dateMWWhat it measures
Built IT powerSify Infinit Spaces, 30 Jun 202525.92The capacity the campus is built and designed to deliver
InstalledThird-party tracker, 30 Jun 20254.32Equipment actually energised inside Tower B
Ready for serviceSify, Q4 FY24 earnings call26Capacity made available to customers
Portfolio cardOct 202630Current published campus capacity

The two dated figures share a measurement date and describe different things. 25.92 MW is what the building was built to deliver. 4.32 MW is what was energised. Neither source is wrong, and the gap between them is the single most useful number on this page.

4.32 MW is one sixth of 25.92 MW — a tower that is 17% live against its own built specification. For a building that only opened in 2025 that is not surprising: halls are commissioned in blocks, and anchor tenants are signed against a delivery date rather than a certificate of occupancy.

The reconciliation this page will not perform

Sify says 25.92 MW built. A tracker says 4.32 MW installed. Sify says 26 MW ready for service on an earnings call, which is the number that matters commercially, and it is close to the built figure rather than the installed one.

That leaves three readings: the 4.32 MW figure is out of date or partial; the 26 MW figure is a contractable design capacity rather than energised plant; or the campus is genuinely six-sevenths unenergised.

Gridvik publishes all three and resolves none. Anybody paying for megawatts here should ask for energised plant, in writing, with a date — the same sentence that would settle Rabale Tower 5.

3Seven figures for one campus

Towers A and C to come, full campuscurrent campus page130+ MWThree towers, older page13,000+ racks78 MWThird-party planned buildArusGrid, September 202652 MWTower B, promotional video202543 MWPortfolio card, currentOctober 202630 MWBuilt IT power, Sify30 June 202525.92 MWInstalled, third-party tracker30 June 20254.32 MWSeven figures, one campus, one date in common. The bottom bar and the bar above it are both dated 30 June 2025.
Figure 1 — every published capacity for Siruseri on one scale. The red bar and the bar directly above it are both dated 30 June 2025.
Each figure, its scope and its date
FigureSource and dateMWScope and notes
Full campusCurrent page130+Three towers, towers A and C still to come
Three-tower planOlder page78With 13,000+ racks, later revised upward
Planned buildThird-party, Sep 202652Tracker’s own cumulative model
Tower B, promotional video202543Claimed capacity of the first operational part
Portfolio cardOct 202630Current published campus figure
Built IT power30 Jun 202525.92Operator, dated, precise to two decimals
Installed30 Jun 20254.32Third-party tracker, same date
This registry—0Inside the PRJ-028 campus aggregate

The 78 to 130+ revision is worth naming because it is the largest single upward change in this file outside Yotta. In 2024 Sify said a three-tower campus at Siruseri would add 78 MW and 13,000+ racks. By 2026 the same three towers are 130+ MW. The tower count and the rack count did not change. The megawatts rose by 67%.

One explanation fits and it is a commercial one: the racks were re-specified for AI density. A hall designed at 6 kW a rack and later fitted for 130 kW carries more than twenty times the power on the same floor plate, and 13,000 racks at an average of 10 kW is 130 MW. The 78 MW figure is what the same steel is worth at enterprise density.

That also resolves the 130 kW claim, which looks absurd next to a 130 MW campus until the arithmetic is done: 130 MW across 13,000 racks averages 10 kW. The 130 kW cabinets are the liquid-cooled pods, not the building.

4Pricing ₹1,882 crore three ways

One investment, three denominators
DenominatorMW₹ crore per MW
Power infrastructure, per the state announcement4047.0
Ready for service, per the earnings call2672.4
Built IT power, per the operator25.9272.6
Installed, per the tracker4.32435.6

₹47 crore or ₹436 crore per megawatt — a ninefold range from a single capital figure. That is the clearest illustration in this file of why a cost-per-megawatt number is meaningless without its denominator.

The 40 MW denominator is the one to avoid. It is the utility connection supporting the phase, and it is internally consistent with a 25.92 MW IT load at a power usage effectiveness of about 1.54 — 25.92 × 1.54 = 39.9 MW. Dividing capex by 40 prices utility power as if it were IT power and produces a figure that looks competitive with the cheapest build in the country. It is not.

The 4.32 MW denominator produces ₹436 crore per megawatt, which is a statement about how early in commissioning the campus is, not about its cost efficiency. Quoting either extreme is a way of misleading a reader without stating a falsehood.

₹72.6 crore per MW at the built figure is the one comparison that means something, because it is the only denominator the operator and the market both use for a completed phase.

5The cable station, the switchyard and the premium

Sify Kolkata 01hall build₹80.0 crSTT Kolkata 02hall build₹75.0 crSify Chennai 02Tower B, ₹1,882 cr at 25.92 MW₹72.6 crAirTrunk Raigad Penletter of intent only₹66.7 crColt DCS Navi Mumbaicampus build₹60.1 crCapitaLand Chennai 0153 acres gross, Ambattur₹57.1 crYotta D4120 MW facility₹55.3 crAirTrunk Mumbaifacility₹53.0 crNTT NAV2phase one₹51.4 crYotta NDC NERdesign basis, Assam₹41.0 crThe band of five independent operators sits at ₹51.4 to 60.1 crore per MW. Siruseri is above it, and the switchyard and cable station are why.
Figure 2 — every disclosed cost per MW of IT in the registry. Siruseri at ₹72.6 crore is the third most expensive build on the list, and the two above it are small hall conversions rather than campuses.

Against the replacement-cost band of ₹51.4 to 60.1 crore per MW established across five independent operators, Siruseri at ₹72.6 crore carries a premium of ₹12.5 to 21.2 crore per megawatt — or ₹324 to 549 crore across 25.92 MW. Both are arithmetic on published figures and both are labelled estimates.

Three things plausibly account for it, and all three are physically verifiable in the record:

What the premium buys
ItemDetailWhy it costs
Integrated cable landing stationUp to 2 PBps, four dedicated fibre pathsSubmarine capacity is the scarcest input in Indian data centres
230 kV dedicated substationOn-premise, against a 40 MW phase connectionA switchyard at this class is a fixed cost that a 25 MW phase carries alone
AI-ready liquid cooling130 kW per rack, NVIDIA DGX-Ready certified 2025Coolant distribution, manifolds and higher-density floor loading
CertificationUptime Rated 3, IGBC PlatinumDesign, commissioning and documentation overhead
Grid connection130 MW for the full campusSecured in advance for towers A and C

The cable landing station is the one that changes the commercial argument rather than the cost. India has a handful of landing points and almost no data centre can offer subsea capacity on the same campus. A tenant that needs to terminate international capacity — a cloud provider, an OTT, a content network, a financial exchange — has a very short list of buildings to choose from, and Siruseri is now on it.

That is the strategic reason to pay a 20 to 40% premium per megawatt: it is not a data centre with a cable station attached, it is a landing point with 130 MW of capacity behind it. The metro is the more valuable asset, and the megawatts are what make it sellable.

Where the Chennai 02 numbers leave a buyer

Built 25.92 MW, designed 130+ MW, installed 4.32 MW on the same date as the built figure, priced at ₹72.6 crore per megawatt.

The premium is defensible and the campus is real. The only number that cannot be relied on is the one an operator will lead with.

Ask for energised plant and a tower-level schedule. Everything else here is already public and already on this page.

6Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
An AI-ready hyperscale campus with subsea cable landing, a 230 kV dedicated substation and 130 kW rack capability, at Siruseri
Where it is
SIPCOT IT park, Siruseri, about 25 km south of central Chennai. Tower B operational
Who holds the answer
Sify Technologies hyperscale sales and the AI/neocloud team; Sify Infinit Spaces for the asset
The one question
How many megawatts of Tower B are energised today, and how much of that is uncontracted
Why they will answer it
An operator in an IPO process that needs audited, built, energised capacity to be credible
Gridvik estimate
Installed may sit between 4.32 MW and the 26 MW stated as ready for service. Labelled estimate
What changes it
An energisation disclosure, a cable landing customer announcement, or towers A and C going live
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

7Limits and open questions

  • Seven published capacities — 4.32, 25.92, 26, 30, 43, 52, 78 and 130+ MW. The registry counts zero here, because the megawatts sit inside the PRJ-028 campus aggregate.
  • 25.92 MW and 4.32 MW share a date but not a meaning. One is built, the other installed. The page does not choose between them.
  • The 78 to 130+ revision is unexplained in public. The re-specification for AI density is a plausible reading, not a stated cause.
  • ₹1,882 crore is described as an initial investment. What it covers — Tower B alone, or site-wide infrastructure including the cable station — is not itemised.
  • No PUE is published for Siruseri, so the 1.54 used to reconcile 40 MW against 25.92 MW is an inference, and is labelled as one.
  • Occupancy and realised rent are not disclosed for any Sify facility, so revenue from this campus cannot be derived from public data.
  • What would close it. One sentence: energised IT megawatts at Siruseri, by tower, with a date.

8Sources

Sources: the Sify Chennai 02 data centre page with the 25.92 MW, cable landing station, Rated 3 and IGBC Platinum specifications; the Sify Chennai data centre page; the Sify data centre portfolio page; Sify Infinit Spaces Chennai data centre page dated 30 June 2025; the Sify Infinit Spaces integrated report of 2025; DCD and The Print on the campus and its grid connection; ETV Bharat on the ₹1,882 crore investment and 40 MW of power infrastructure; the Q4 FY24 earnings call; and ArusGrid, which records 4.32 MW installed at 30 June 2025.