Investment programme · Verified 26 Oct 2026

Tata Communications — ten lakh square feet, and no megawattsTata Communications · India · US$200 million+ · 10 lakh sq ft over three years · No MW disclosed · Zero megawatts counted

Record PRJ-235National — IndiaTier B — programme, not capacity4 public sources checkedAdditive: not applicable — 0 MW counted
A large commitment with no capacity unitImplied capacity spans 93 to 518 MW depending on densityCorrectly excluded from every total in this registryFloor area is the most quoted and least comparable metric in Indian data centres
US$200m
Committed
10lakh sq ft
Target floor area
3yr
Horizon
0MW
Disclosed
93–518MW
Implied range
₹1,200cr
INR equivalent

In June 2026 Tata Communications committed more than US$200 million, about ₹1,200 crore, to double its India data centre floor area to ten lakh square feet over three years. It did not state how many megawatts that is, and no subsequent disclosure has supplied the number. That omission is not unusual — floor area is the metric Indian data centre operators reach for when they want to announce growth without publishing capacity — and it is the reason this record is excluded from every total in this registry. Applied at ESDS density, ten lakh square feet is 93 MW. Applied at PDG Hyderabad density, it is 518 MW. The same commitment is a five-and-a-half-fold different fact depending on a number Tata Communications has not published.

1At a glance

Programme
Tata Communications India data centre capacity doubling
Announced
June 2026, three-year horizon
Commitment
More than US$200 million, about ₹1,200 crore
Target
Double India data centre floor area to 10 lakh sq ft
Megawatts disclosed
None
Rack count disclosed
None
Sites named
None — a national footprint, not a project
Record type
Investment programme
Additive flag
Not applicable
Counted in this registry
0 MW
Implied capacity at 93 W/sq ft
93 MW
Implied capacity at 367 W/sq ft
367 MW
Implied capacity at 518 W/sq ft
518 MW

2What was announced

Data centre doublingUS$200 million, Jun 2026US$200mIndia-Singapore subseaUS$152 million, Jul 2026US$152mThe first buys floor area and never states a megawatt. The second buys 98 Tbps and never will.
Figure 1 — the group's two 2026 commitments, side by side. Neither states a megawatt, and neither can be added to a capacity total.
The disclosure, in full
ItemPublishedMissing
InvestmentMore than US$200 million, ₹1,200 croreAllocation per site or per phase
Floor area target10 lakh sq ft after doublingCurrent floor area, and how much is data hall versus support space
HorizonThree years from June 2026Any annual or phase schedule
Capacity—Everything
Sites—Which cities, which campuses, new-build or fit-out
Customer—Any anchor tenant or pre-leasing

The record is honest and it is empty. A ₹1,200 crore commitment to double a national data centre footprint is a material fact about the Indian market, and it cannot be entered into a capacity total because it does not contain a capacity number.

The registry therefore files it as an investment programme with zero megawatts and a written reason. That is the correct handling, and it is also the reason the registry’s totals are lower than the market’s: a reader who counted every announcement as capacity would add a hundred to five hundred megawatts here on the strength of a square-footage target.

3Ten lakh square feet is between 93 and 518 MW

ESDSfive Tier-3 sites, 7 MW93Sify Hyderabad 01low density enterprise150Sify Hyderabad 01high density floor300NTT Bengaluru 4AI-ready, liquid cooled367PDG HY1 Hyderabaddesigned density518The same seven megawatts is 75,000 square feet at ESDS and 13,500 square feet at PDG density.
Figure 1 — measured density in this registry, from a Tier-3 services portfolio to an AI-ready hyperscale campus. The same floor area means five times the capacity at the top of that range.
The conversion, at every density the registry can evidence
Density sourceW/sq ft10 lakh sq ft impliesWhat that density is
ESDS, five Tier-3 sites9393 MWServices-heavy portfolio, low power density
Sify Hyderabad 01, low floor150150 MWEnterprise colocation, air-cooled
Colocation industry band, low200200 MWCommon design point for 2015 to 2020 builds
Sify Hyderabad 01, high floor300300 MWShared floor, high-density racks
NTT Bengaluru 4367367 MWAI-ready, liquid cooling capable
PDG HY1 Hyderabad518518 MWDesigned for high-density AI workloads

The range is 5.6-fold, and it is not a modelling nicety — it is the difference between Tata Communications becoming the fourth-largest operator in this registry and becoming the largest by a wide margin.

At 93 MW it would rank below NTT at 273.2 MW operating. At 518 MW it would be nearly twice NTT. One unpublished number separates those two outcomes.

This is the single most common error in Indian data centre market sizing

Floor area is published far more often than capacity because it is easier to announce and harder to audit. Every market report that converts square feet to megawatts at a fixed factor is guessing, and the factor they choose determines the answer.

A 4 W/sq ft error across ten lakh square feet is 40 MW. A density choice between the top and bottom of this table is 425 MW.

The registry does not make the conversion at all. Where an operator publishes only floor area, the record carries zero megawatts and a note, and the reader can see that the number is missing rather than inheriting someone else’s assumption.

4Why floor area is the wrong metric and the useful one

Floor area is the wrong metric for capacity and a good metric for three other things.

What floor area does tell you
QuestionFloor area answers itCapacity answers it better
How much land and shell is being committedYesNo
How much construction capex is comingYesPartly
How much can be sold as colocationPartly — data hall area onlyYes
How much power the local grid must supplyNoYes
How the operator will rank nationallyNoYes
Whether the commitment is realAs well as anything elseAs well as anything else

Ten lakh square feet is a real commitment to real construction. It is roughly 9.3 hectares of built space, or about the data centre floor of two NTT Bengaluru 4 campuses. The programme is material.

What it is not is a capacity claim, and the difference matters most in a diligence conversation. “We are doubling to ten lakh square feet” survives a follow-up. “We are adding 300 MW” would not, unless the number existed. Tata Communications has chosen the statement it can defend, which is more than most operators in this file have done.

5What would change this record

The facts that would give this record a megawatt figure
Fact neededWhat it would resolve
A megawatt or rack targetThe whole record; any figure is better than none for ranking purposes
Current floor area and current capacityAllows a density to be derived rather than assumed
Site or city splitMoves the record from national to state level, which is what buyers actually purchase
Data hall share of the ten lakh sq ftCuts the implied range by roughly half; support space is not sellable
Construction scheduleConverts a three-year programme into a capacity forecast

The record stays at zero until at least the first and third exist. Two of the 242 records in this registry are Tata Communications investment programmes, and neither carries capacity — this one and the subsea expansion on PRJ-236. Both are material to the group’s strategy and neither is a data centre.

6Sources

Sources: Economic Times, 1 June 2026, reporting Tata Communications’ plan to invest more than US$200 million, about ₹1,200 crore, to double its India data centre capacity to ten lakh square feet over three years; Gridvik records PRJ-236 for the companion subsea commitment; Gridvik records PRJ-237 for ESDS density and PRJ-233 and PRJ-240 for the NTT and PDG densities used in the conversion table. No megawatt, rack or per-site figure has been published for this programme. Record verified 26 October 2026.