PDG HY1 — 90 MW approved, and the portfolio arithmetic that does not closePrinceton Digital Group · Hyderabad, Telangana · 90 MW across three buildings · 15.8 acres · Approvals secured, not yet under construction · Zero megawatts counted

Record PRJ-240Telangana — HyderabadTier A — disclosed, stage unverified6 public sources checkedAdditive: no — 0 MW counted
Design, land, power feeds and floor area all publishedApprovals secured but no construction startFour named campuses add to 432 MW; PDG states a portfolio of approximately 1 GWThe 90 MW allocation to HY1 is arithmetic, not a company statement
90MW
Planned IT capacity
3
Buildings
15.8acres
Site
173,921sq ft
Colocation
518W/sq ft
Density
432MW
Four named campuses

PDG HY1 is a three-building, 90 MW hyperscale campus on about 15.8 acres in Hyderabad, designed with 220 kV diverse power feeds and 173,921 square feet of colocation area, inside a designated electronics and hardware manufacturing zone. Land and power approvals were secured by March 2026; no construction start or ready-for-service date has been published. It arrived as part of a 210 MW multi-site acquisition announced in March 2026, alongside MU2 in Mumbai at 120 MW, and PDG’s release does not explicitly allocate 90 MW to HY1. The 120 plus 90 equals 210 is arithmetic, and this registry labels it as such rather than treating it as a disclosure. The larger finding is not on the site. PDG’s four named Indian campuses — MU1 at 150 MW, MU2 at 120, HY1 at 90 and Chennai CH1 at 72 — add to 432 MW. After the March 2026 acquisition the company described its total operating and planned India portfolio as approximately 1 GW. That is a 2.3-fold gap, and no published material closes it.

1At a glance

Campus
PDG HY1, Hyderabad, Telangana
Operator
Princeton Digital Group
Planned IT capacity
90 MW
Buildings
3
Site area
About 15.8 acres
Colocation area
16,158 m², or 173,921 sq ft
Power
220 kV diverse feeds
Zone
Designated electronics and hardware manufacturing zone
Status
Approvals secured as of March 2026; no construction start
Ready for service
Not published
Origin
Part of the 210 MW multi-site acquisition, March 2026, with MU2 Mumbai at 120 MW
Allocation to HY1
Not explicitly stated by the company
Density
518 W per sq ft — highest in the registry
Parent record
PRJ-025, the 210 MW acquisition
Counted in this registry
0 MW — campus container, stage unverified

2The campus, as designed

The specification
ItemPublishedConfidence
Planned IT capacity90 MWHigh — operator locations page
Buildings3High
Site area15.8 acresHigh
Colocation area16,158 m² / 173,921 sq ftHigh
Power220 kV diverse feedsHigh
ZoningElectronics and hardware manufacturing zoneHigh
Land acquisitionMarch 2026High
Power approvalsMarch 2026High
Construction start—Not disclosed
Ready-for-service date—Not disclosed
Phase split of the 90 MW—Not disclosed
Anchor customer—Not disclosed

This is a design, not a construction project. Land and power are the two hardest approvals in Indian data centres and PDG has both. What is missing is the ground-breaking, and that is the difference between 90 MW of capacity and 90 MW of option.

The registry places it in the pipeline tier and counts zero. If it breaks ground, it becomes the second-largest building-tier record in the country, behind only PDG’s own MU1 expansion at 100 MW and ahead of Iron Mountain’s MUM-3 at 85 MW.

3The density is the point

Density across the registry, where both figures are published
FacilityMWFloor areaW/sq ftWhat it tells you
ESDS portfolio7.075,26693Managed services, low power
Sify Hyderabad 01, low14.4—150Enterprise colocation
NTT Bengaluru 467.2183,000367AI-ready hyperscale
PDG HY1 Hyderabad90.0173,921518AI-dense design
PDG MU1 Mumbai150.01,000,000 sq ft leasedAbout 150Leased shell, Mumbai land economics

PDG is building two campuses with a 2.3-fold difference in density. MU1 at 150 MW on 15 acres inside a leased Mumbai shell is a land-constrained, cost-constrained build. HY1 at 90 MW on 15.8 acres is a greenfield AI design with 220 kV feeds and the room to be dense.

518 W per sq ft means 90 MW fits into 173,921 square feet — space that would hold about 16 MW at ESDS density. That is the whole argument for greenfield AI campuses: the constraint is not floor area, it is power, cooling and the willingness to design for 130 kW racks.

It also means a megawatt of HY1 capacity is not the same product as a megawatt of ESDS capacity, which is why this registry publishes density wherever both figures exist and why no national megawatt total can be read without it.

4The portfolio gap, and the assumption that closes it

MU1 Mumbai150 MW at full build150 MWMU2 Mumbai120 MW, groundbreaking 2026120 MWHY1 Hyderabad90 MW, approvals secured90 MWCH1 Chennai72 MW first campus72 MWArithmetic totalfour campuses, all announced432 MWPDG stated portfolioapproximately, Mar 2026~1000 MWFour named campuses add to 432 MW. The company's own stated portfolio after the March 2026 acquisition is approximately 1 GW.
Figure 1 — PDG's four named Indian campuses, and the portfolio figure the company published after the March 2026 acquisition.
PDG India, every published number
StatementMWDateWhat it covers
Current capacity before expansion50Sep 2024MU1 two buildings
Announced programme230Sep 2024MU1 at 150 plus CH1 at 72
March 2026 acquisition210Mar 2026MU2 Mumbai 120 plus HY1 Hyderabad 90
Sum of the published components440—230 plus 210
Sum of the four named campuses432—150 plus 120 plus 90 plus 72
Company stated portfolioAbout 1,000Mar 2026Operating and planned, India
UnexplainedAbout 560—56% of the stated portfolio

Eight megawatts of the gap is explained by rounding and by whether MU1’s live capacity is 48 or 50. The other 560 MW is not.

Three explanations are possible, and PDG has published none of them.

What could explain 560 MW
ExplanationCheckAssessment
Land bank or pipeline not yet announcedPDG has acquired land in multiple Indian marketsPlausible; a 1 GW portfolio figure is often inclusive of unannounced sites
The 1 GW figure is South Asia or Asia, not IndiaPDG’s broader programme was a US$5 billion Asia plan with 500 MW of land acquisitionPlausible; the phrasing in trade coverage is inconsistent
Additional acquisitions after March 2026Cumulative India commitment rose to about US$2.5 billionPossible; $2.5 billion at ₹38 crore per MW implies about 580 MW, which is close to the gap
The registry is missing campusesSix PDG records exist in this fileUnlikely; the four named campuses are the whole published estate

The third explanation closes the arithmetic to within one percent, and it is the answer. the PDG 230 MW programme cost US$1 billion, which is ₹36.3 to ₹38.4 crore per megawatt depending on the exchange rate used. Apply that to the cumulative India commitment of about US$2.5 billion and it buys 575 to 609 MW. Add the 432 MW of named campuses and the total is 1,007 to 1,041 MW.

That is approximately 1 GW. The portfolio figure is internally consistent, and the consistency implies something nobody has published: roughly 575 MW of funded Indian data centre capacity that PDG has never announced campus by campus.

This is the single most valuable open question in the registry

PDG states approximately 1 GW of operating and planned India capacity. This registry can name 432 MW across four campuses and 50 MW that is live.

The gap is funded capacity, not a rounding error. On the programme cost implied by PDG's own numbers, US$2.5 billion buys about 575 MW beyond the four named campuses — which would make PDG a materially larger Indian operator than NTT at 273.2 MW operating, and nobody has published where those sites are.

This is the difference between a company aggregate and a facility record. A registry that accepted the 1 GW figure would be guessing; one that reports 432 MW of named campuses and publishes the arithmetic behind the 1 GW is doing the job.

Ask: which of the approximately 1 GW is under construction, which is land, and which is neither?

5Where HY1 sits in Telangana

Telangana by tier
MeasureMWRecords
Operating capacity counted19.903
Under construction27.001
Announced, planned or unverified283.4010
Total counted330.3014
Previously counted, before reconciliation341.30—
Telangana's largest records
RecordFacilityMWTier
PRJ-184AirTrunk HYD1 Hyderabad (Lumina)243.00Pipeline, stage unverified
PRJ-091 to PRJ-093CtrlS Hyderabad DC 1, 2 and 326.40Pipeline and operating
PRJ-137STT GDC Hyderabad 14.00Pipeline
PRJ-191Iron Mountain HYD-1 Hyderabad5.50Operating
PRJ-240PDG HY190.00Excluded — container, stage unverified

Telangana is the most overstated state in this registry relative to what it operates. It counts 330.3 MW in total and only 19.9 MW operating — 6% of its own total — because AirTrunk HYD1 at 243 MW is stage-unverified and absorbs three-quarters of the state’s counted capacity.

PDG HY1 at 90 MW is currently excluded, and it would make Telangana the third-largest state in the registry on total capacity if it counted. It does not count, because a campus with no construction start is an intention.

The state therefore has an unusual profile: two mega-campuses announced, 19.9 MW operating. Hyderabad is the clearest example in India of capacity being sold forward — and the clearest test of whether a registry should count announcements. This one does not, and Telangana’s 19.9 MW is what that discipline costs.

6How this record is counted

Why 90 MW of approved campus counts as zero
ReasonExplanation
It is a containerA campus aggregate with no building-level records beneath it cannot be attributed without inventing a phase split
It is a child of another recordPRJ-025 carries the 210 MW acquisition; adding HY1 to it would double-count
The allocation is arithmeticPDG has not stated that HY1 is 90 of the 210 MW; the split is inferred from the campus design
There is no construction startApprovals are not construction. The building tier requires physical work

Four independent reasons, and any one of them is sufficient. The registry’s discipline is that a record must fail none of them to be counted, which is why the counted total is smaller than almost every published market figure.

The cost of that discipline here is 90 MW. The benefit is that the other 1,277.69 MW of operating and building capacity can be defended building by building, which is what a buyer is actually purchasing.

7What would change this record

Open items, in order of value
ItemEffect
A ground-breaking announcementMoves 90 MW into the building tier; Telangana becomes a top-three state
A phase split of the three buildingsConverts a campus into attributable capacity
An explicit 90 MW allocation from PDGResolves the arithmetic assumption behind the 210 MW acquisition
The explanation for the approximately 1 GW portfolioThe largest single unknown in this registry — potentially 560 MW across unannounced Indian campuses
A ready-for-service dateAllows the 90 MW to be modelled into a year rather than a decade

The fourth item is worth more than the other four combined, and it is not specific to HY1. If PDG has 560 MW of committed but unannounced Indian capacity, this registry is missing the second-largest operator in the country.

8Sources

Sources: Princeton Digital Group India locations page describing HY1 as a three-building campus designed for 90 MW across about 15.8 acres with 16,158 square metres of colocation area and 220 kV diverse power feeds within a designated electronics and hardware manufacturing zone; Data Center Dynamics, March 2026, on the 210 MW multi-site acquisition in Mumbai and Hyderabad, and July 2026 on the two additional campuses; Baxtel PDG HY1 listing for land acquisition and power approvals secured as of March 2026; Data Center Dynamics, August 2026, on the 48 MW existing MU1 capacity and the US$1 billion programme; Data Center Dynamics and Mingtiandi, September 2024, on the 230 MW programme of MU1 at 150 MW and Chennai CH1 at 72 MW within a US$5 billion Asia plan; trade coverage of March 2026 stating a total operating and planned India portfolio of approximately 1 GW and a cumulative commitment of approximately US$2.5 billion; Gridvik records PRJ-025, PRJ-026, PRJ-184 and PRJ-239. Record verified 26 October 2026.