Campus aggregate · Verified 26 Oct 2026

CtrlS Navi Mumbai campus — 700 MW designCtrlS Datacenters · Mahape and Airoli, Navi Mumbai · 13 buildings, 3 million sq ft, 700 MW ultimate

Record PRJ-094Maharashtra — Navi MumbaiTier B — operator listed, dated12 public sources checkedAdditive: no — aggregate
Five buildings operationalCampus aggregateNon-additive by design700 MW is a ceiling
700MW
Ultimate IT load
116MW
Built
118.8MW
Card sum
30,000
Racks at design
300MW
Substation, scalable to 700
₹121cr
Per MW, at the 2026 valuation

CtrlS is building the largest private data centre campus in India at Navi Mumbai: 13 buildings, 3 million square feet, 30,000 racks at design, and 700 MW of ultimate IT load, behind a 300 MW gas-insulated substation scalable to 700 MW. Five buildings are operating at a combined 116 MW. The operator’s own building cards add to 118.8 MW, so even the built figure has two versions. This record adds zero megawatts to the registry, and this page is where that choice does the most damage.

1At a glance

Operator
CtrlS Datacenters Limited
Campus
Mahape and Airoli, Navi Mumbai. The operator calls the whole estate its Mumbai campus
Design
13 buildings, 3 million square feet, 30,000 racks, 700 MW of IT load at full build
Built
5 buildings operating at a combined 116 MW, per a July 2026 trade report. Six more are listed as upcoming
Next
DC 6 and DC 7 at 95 MW combined, dated 2026 on the operator’s site and unbuilt at the last update
Power infrastructure
A 300 MW gas-insulated substation, described by the company as the largest in Asia, scalable to 700 MW, fed by three sources
Renewables
A 125 MW captive solar farm at Nagpur, covering about 60% of the campus’s energy; more than 1 GW of solar committed by 2030
Status
Operational and expanding. Individual buildings carry their own records
Additivity
Not additive. This aggregate and the seven building records beneath it are all marked non-additive, which means the campus contributes nothing to the registry total — see the section below

2700 megawatts and 116

Two numbers describe this campus and the ratio between them is the whole story.

Five buildings operating116 MW, per a July 2026 trade report116 MWDC 6 and DC 7, upcoming95 MW, dated for 2026 on the operator’s site95 MWRemaining buildings to 13the balance of a 700 MW ultimate campus489 MWSeven hundred megawatts is the campus’s design ceiling across thirteen buildings. One hundred and sixteen is built. The figure in between has no schedule attached.
Figure 1The design ceiling, the pipeline and the built base. Six times the built capacity remains unbuilt and unscheduled.
The campus at three moments
MeasureTodayNextDesign
Buildings5+2 (DC 6, DC 7)13
IT capacity116 MW+95 MW700 MW
Racksnot published per buildingnot published30,000
Floor areanot publishednot published3 million sq ft
Power per square foot——233 W

116 of 700 is 17%. That is not a criticism — a thirteen-building campus takes a decade and this one started in 2015. It is the correct way to read any campus claim: the design number is what the substation is sized for, and the built number is what earns rent.

The two numbers are also regularly swapped. A press release that says the campus has 700 MW is describing land, grid sanction and ambition. A vendor who quotes 700 MW in a pipeline spreadsheet is quoting something that will not exist for years, and possibly not ever in the same form.

3Four cards, 118.8 megawatts

The operator publishes four facility cards for the buildings that exist. They add to 118.8 MW, which is 2.8 MW more than the 116 MW a trade report attributed to the same five buildings in July 2026.

The built campus, card by card
CardPowerRacksFloor area
DC 1 and DC 2 combined40 MW5,555394,177 sq ft
DC 310 MW1,045146,000 sq ft
DC 436.8 MW2,936265,000 sq ft
DC 532 MW2,750228,482 sq ft
Total of the four cards118.8 MW12,2861,033,659 sq ft

A 2.8 MW gap on a 116 MW base is 2.4% and it is not worth chasing. What is worth noting is the shape of the estate. DC 1 and DC 2 together are 40 MW across 5,555 racks — 7.2 kW a rack. DC 4 and DC 5 are 68.8 MW across 5,686 racks — 12.1 kW a rack. The campus is being rebuilt at twice the density in the same estate, which is exactly what the Indian market requires and exactly what the 2015 buildings cannot do.

A separate directory figure puts DC 1 and DC 2 at 36 MW, split as 20 MW and 16 MW. The operator’s own combined card says 40. Gridvik records 40 and notes that the pair has been described three ways: 36 MW combined, 40 MW combined, and 24 MW for DC 2 alone in a 2020 release.

423 kW a rack by design

The design numbers make a claim that no individual card does.

What a 700 MW campus implies
InputValueResult
Ultimate IT load700 MW—
Design rack count30,000—
Average density at full build700 MW ÷ 30,00023.3 kW a rack
Floor area3 million sq ft—
Power per square foot at full build700 MW ÷ 3 million233 W a sq ft
For comparison, the built cards7.2 to 12.1 kW a rackhalf to a fifth

A campus designed for 23 kW a rack is a campus designed for accelerated computing, and the company says so — its AI-ready material claims support for up to 250 kW a rack with liquid cooling, and racks up to 45 kW on air with high delta-T designs.

The gap between the 12 kW being built in DC 4 and DC 5 and the 23 kW implied by the design is the gap between what customers currently buy and what the operator is laying foundations for. That is a rational thing to build and a difficult thing to finance, which is why the pacing matters more than the total.

5The substation that explains the campus

Every Indian campus story is really a grid story, and CtrlS tells this one more explicitly than most.

The power behind the campus
ItemValueNote
Gas-insulated substation300 MWdescribed by the company as Asia’s largest; commissioned at 150 MW and doubled to 300 MW in 2024
Scalable to700 MWthe same number as the campus design, which is not a coincidence
Sourcesthreethe company claims 100% power availability from diversified paths
Captive solar125 MW at Nagpurcovering about 60% of campus energy; N-type panels on tabletop land along the Mumbai–Kolkata highway
Solar commitmentmore than 1 GW by 2030against a stated goal of 100% renewable operations

The substation is the tell. A campus that commissions 300 MW of gas-insulated switchgear before it has 120 MW of buildings is not guessing about demand; it is buying an option on it. That option is what makes 700 MW credible and what makes the intermediate years expensive.

The solar farm is the other half of the same logic. A 125 MW captive plant covering 60% of the campus’s energy is a hedge against tariff escalation, and it is the kind of asset that a buyer of this business would value separately from the buildings.

6₹121 crore a megawatt

The company, priced against its own capacity
ItemValueSource
CPP Investments commitment₹7,000 croreJune 2026, equity plus a joint venture
Pre-money valuation₹44,914 crorereported alongside that transaction
Operational capacityabout 370 MWcompany statement, June 2026
Implied value per operating megawattabout ₹121 croreGridvik arithmetic
Nxtra, for comparison₹91 to ₹110 crore a megawattfrom its March 2026 round at $3.1 billion on 250 to 300 MW
Project pipeline4.4 GWcompany target; a rating agency projects 950 to 1,000 MW by 2029

Two numbers matter here. The first is ₹121 crore per operating megawatt, which is 10 to 30% above what Nxtra’s March 2026 round implied for its own estate. CtrlS is being marked as the more valuable business per megawatt of capacity it runs, and the reasons are visible: a 300 MW substation, a captive solar farm, Rated-4 certification across the estate, and campuses in more cities.

The second is the pipeline gap. The company says 4.4 GW is at various stages. A rating agency projects 950 MW to 1 GW operational by 2029. If the analyst is right, roughly 3.4 GW of the stated pipeline is not going to be operational in any forecast anyone is underwriting — and if the company is right, the current valuation is a fraction of what the business is worth in five years. Both are published. Only one is bankable.

The single most useful number on this page

₹121 crore for every operating megawatt. It converts a capacity announcement into a price, and a price is what a buyer, a seller or a competitor can act on.

Apply it to the 700 MW campus and the finished asset is worth ₹84,700 crore on today’s mark. That is the size of the bet in Navi Mumbai.

7The record that counts nothing

This campus is marked non-additive, correctly, because the buildings inside it carry their own records. The problem is that those buildings are marked non-additive too.

How CtrlS Mumbai is counted in this registry
RecordMWIn the total
PRJ-094 — this campus700 ultimate, 116 builtno
PRJ-095 to PRJ-101 — the building cards40, 10, 36.8, 32 and othersno
Net effect0 MWnothing counted

Add the Kolkata case and the size of the understatement becomes clear. 118.8 MW of live Navi Mumbai capacity and 16 MW of live Kolkata capacity — 134.8 MW — appear in no total in this file. The registry’s counted figure is 2,420.4 MW, and it is a floor rather than a sum.

Twenty-eight records in this registry are both non-additive and described as operational, and they sum to 1,925.4 MW. Most of those are aggregates that contain other records and must not be added. The specific defect is narrower: where a live building has no additive sibling, its megawatts vanish.

The correction this page recommends

Count the facilities, hold the aggregates as ceilings — the rule the registry already applies to Nxtra, STT and NTT in most markets.

Under that rule the national count would rise by roughly 135 MW immediately. We would rather show the flaw and the fix than publish a number that cannot be defended.

8Timeline

  • The first buildings at Mahape enter service
  • DC 2 is launched, later described at 24 MW and 1,800 racks across 132,000 square feet
  • Grid capacity at the campus substation doubles from 150 MW to 300 MW, with headroom to 700 MW
  • Five buildings operate at about 116 MW; DC 6 and DC 7 at 95 MW are listed as upcoming; a 125 MW captive solar farm is completed
  • CPP Investments commits up to ₹7,000 crore at a reported pre-money valuation of ₹44,914 crore
  • No construction dates for the six remaining buildings, and no reconciled built capacity between 116 and 118.8 MW

9Limits and open questions

What this record is
The largest private data centre campus in India by design: 13 buildings, 3 million square feet, 700 MW of ultimate IT load, 116 MW operating behind a 300 MW substation
What it is not
Seven hundred megawatts. That is a ceiling written on a substation and a masterplan
What Gridvik will not do
We will not add this aggregate to its own buildings, and we will not present the design capacity as either capacity or pipeline without dates
First question
When do DC 6 and DC 7 start? Together they are 95 MW, which is more than four times the largest building on the campus and would move the built base by 82%
Second question
What is the occupancy of the five operating buildings? A 116 MW estate that is 60% let and one that is 95% let are entirely different businesses at the same capacity
Third question
How does the campus reach 700 MW when the substation is 300 MW? The answer is a second connection, and the location of that connection is the most valuable unpublished fact about this site
Why this record matters
It is the anchor for the largest operator campus in the country, it carries the best available valuation per megawatt, and its counting choice exposes a defect in this registry’s own totals
What changes the tier
A start date for DC 6 or DC 7, occupancy figures, or a single reconciled built capacity

10Sources

Sources: CtrlS Mumbai data centre page, CtrlS campus and visit pages, CtrlS AI-ready infrastructure page, Data Center Dynamics on the 125 MW solar farm and on the campus build, TelecomTalk on the 300 MW substation, The Hans India on the gas-insulated substation, Baxtel Navi Mumbai listings, datacenterlocations, dcmarketinsights, and Indian market commentary on the Mumbai data centre nodes.