Facility record · Verified 26 Oct 2026

Iron Mountain MUM-3 — Rabale, Navi MumbaiIron Mountain Data Centers · Rabale, MIDC, Navi Mumbai · 85 MW IT at full build · 1,398,000 sq ft · 120 MVA substation · Delivery 2027

Record PRJ-190Maharashtra — Navi MumbaiTier B — under construction, operator-published8 public sources checkedAdditive: no — child of the campus claim, counts 0
Substation matches the claimLargest IT load in the registryNothing built yet2027 or Q1 2028Capex not published
85MW
IT load, full build
1,398k sq ft
Floor area
130,000m²
Floor area
120MVA
Dedicated substation
1.41
Implied facility-to-IT ratio
2027
Targeted delivery

MUM-3 is the largest IT-load building in this registry: 85 MW at full build, across 130,000 square metres — 1,398,000 square feet — on the Navi Mumbai campus at Rabale, inside the MIDC industrial area. Ground was broken in January 2026 with Stirling & Wilson building it. Delivery is targeted for 2027, and Q1 2028 on two of the operator’s own pages. It is 3.5% of the entire 2,420.4 MW registry in one building, and 2.9 times the floor area of everything Iron Mountain operates in India today. The 120 MVA substation is what makes the number credible: 120 divided by 85 is 1.41, exactly a facility-to-IT ratio for a design PUE around 1.4 with no spare capacity.

1At a glance

Facility
MUM-3, Rabale, MIDC industrial area, Navi Mumbai, Maharashtra
Operator
Iron Mountain Data Centers India
IT capacity
85 MW at full build — the largest IT load in this registry
Floor area
130,000 m² / 1,398,000 sq ft
Density
16,447 sq ft per MW; about 60.8 W per sq ft
Substation
120 MVA dedicated; implied facility-to-IT ratio 1.41
Design
Tier III-designed, AI-ready, high-density, specialised cooling
Sustainability
100% renewable energy matching via Green Power Pass
Compliance
HIPAA, FISMA and ISO standards per the operator
Contractor
Stirling & Wilson
Ground broken
January 2026
Delivery
2027 on most pages; Q1 2028 on two operator pages
Original announcement
June 2023 at 32 MW, US$170 million, H2 2025 go-live
Counted in this registry
0 MW — non-additive, child of the campus claim

2Eighty-five megawatts, and what it is bigger than

AirTrunk HYD1Chandanvelly, facility, at least243 MWNTT NAV1Navi Mumbai, facility maximum plan150 MWIron Mountain MUM-3Rabale, IT load, substation-verified85 MWNTT Mumbai 9Chandivali, facility62 MWAirTrunk BOM1Airoli, facility, at least62 MWNTT Mumbai 8Chandivali, facility36 MWScopes are mixed on purpose. Only one bar on this chart has public power infrastructure sized to it, and that is the red one.
Figure 1 — the registry’s largest announced single buildings. NTT NAV1’s 150 MW is a facility maximum plan; AirTrunk’s figures are facility capacity described as at least; MUM-3 is the only one stated as IT load with power infrastructure published.
What 85 MW is bigger than
ComparisonMWMUM-3 isNote
AirTrunk HYD1, the largest site in the file2430.35× — smallerFacility capacity, at least
NTT Mumbai 9, the largest operating building621.37× largerFacility power, not IT
NTT’s eight Mumbai records combined16153% of themChandivali plus Andheri plus Vikhroli plus Fort
Iron Mountain’s six operating buildings20.34.2× largerOne building, four times the company
Maharashtra’s counted capacity786.410.8% of the stateWould take the state to 871.4 MW
The whole 2,420.4 MW registry2,420.43.5%One building, one thirty-fifth of India

Four point two times its own company is the number that matters commercially. Iron Mountain operates 20.3 MW in India after five years and one acquisition. MUM-3 alone is 85 MW. The platform is not growing in India; it is being replaced in India.

Why the substation is the whole story

Every other figure on this chart is a capacity statement with no power infrastructure attached to it. MUM-3 has a 120 MVA dedicated substation, which is a distribution utility commitment with a physical footprint and an energisation date.

Divide 120 MVA by 85 MW and you get 1.41. That is not a coincidence and it is not a marketing ratio — it is what an engineer sizes a connection to when the building will draw 85 MW of IT load plus cooling and losses.

That single division is why this registry treats 85 MW as a probable number and treats 3 GW in Raigad as a press release.

31.4 million square feet on five acres

MUM-3 is the clearest vertical build in the Indian market, and the arithmetic of floor area against site area proves it without needing a storey count.

Floor area against site area
MeasureValueReading
Floor area130,000 m² / 1,398,000 sq ftPublished ·
Site, if the five-acre MUM-3 parcel20,234 m²Acquired for the third building in 2023 ·
Floor area ratio6.4Six storeys of full-site coverage ·
Site, if the whole 5.5-acre campus22,257 m²5.8 · Five to six storeys with setbacks
Existing MUM-1 and MUM-2 combined14,923 m² / 160,631 sq ftWhat 8.8 MW occupies ·
MUM-3 relative to that8.7×The same campus, eight times the floorspace ·
MUM-3 relative to the 44,700 m² platform2.9×One building, three platforms ·

A floor area ratio of 5.8 to 6.4 on a parcel in the MIDC industrial belt means the building is five or six storeys of near-full-site coverage. There is no greenfield alternative on a five-acre site: 85 MW at ground level would need roughly 18 acres at typical low-rise data hall coverage.

The registry does not claim a storey count. It claims the ratio, which is arithmetic from two published numbers, and the ratio only admits one kind of building.

What a vertical build costs you in engineering

Multi-storey data halls mean vertical chilled-water distribution, heavy floor loadings, and chilled water plant either on the roof or in a basement. They also mean a single point of failure stack — one riser serving five floors is a different risk profile from five independent halls.

That is why the market pays a premium for land: the alternative to five storeys in Rabale is 18 acres somewhere a tenant does not want to be.

4What 85 MW costs

Iron Mountain has not published a capital cost for the 85 MW configuration. The 2023 announcement carried US$170 million for a 32 MW building. Everything below the first row is a Gridvik estimate at a stated rate, and is labelled as one.

Published and estimated capex
BasisRate85 MW impliesStatus
2023 announcement, 32 MWUS$170m = US$5.31m per MWUS$451m / ₹3,987 croreRate is published; the multiplication is ours
AirTrunk programme rateUS$6.0m per MWUS$510m / ₹4,508 croreGridvik estimate
Per square foot, at the 2023 rateUS$121 per sq ftUS$170m at 32 MWCoincidence of scale, not a rule
Disclosed capex for 85 MWnone—The only row that is a fact

At ₹3,987 to ₹4,508 crore, MUM-3 is a ₹4,000 crore plus single building — which would make it one of the largest single private data centre investments recorded in this registry, alongside NTT’s NAV2 at ₹5,500 crore for 107 MW and NTT Kolkata at ₹2,000 crore for a 40 MW campus.

The reason this matters for a data buyer is different. Do not use the 2023 rate to forecast anything. A 32 MW enterprise colocation building and an 85 MW AI-ready building do not have the same cost curve: the AI building carries liquid cooling readiness, far higher power density per hall, and a much larger substation relative to load.

5What 85 MW does to the registry

MUM-3 in the national and state counts
MeasureMWShareNote
Maharashtra counted today786.4—88 records
Maharashtra with MUM-3 at delivery871.4+10.8%One building moves a state by an eighth
Registry counted today2,420.4—241 additive records
Registry with MUM-3 at delivery2,505.43.5%Largest single addition possible in the file
Iron Mountain India counted today11.50.48%Three records carry no value
Iron Mountain with MUM-396.54.0%The company becomes a top-five platform in one building

Iron Mountain goes from 0.48% to 4.0% of the national counted total on the delivery of one building. That is not a normal growth step and it is why this record is the hinge of the whole Iron Mountain family in this file.

It also means the registry has a genuine sensitivity: if MUM-3 slips from 2027 to 2030, 85 MW of nationally counted capacity moves with it, and no other single record in the 242 can absorb that swing.

6Procurement

Procurement window and scope
Gridvik assessment · 22 Oct 2026
What to buy here
The largest IT-load building in the registry, with a substation and a contractor named — the best-evidenced large build in India
Where the capacity is
Rabale, MIDC industrial area, Navi Mumbai. 85 MW IT, unbuilt
Who holds the answer
Iron Mountain Data Centers India; Stirling & Wilson; the Maharashtra distribution utility for energisation
The one question
What is the phase schedule — how many megawatts, in which year
Why they will answer it
Hyperscale tenants need phase dates to plan their own racks, and sales teams are already in market
Gridvik estimate
First capacity no earlier than H2 2028; full 85 MW not before 2030. Labelled an estimate
What changes it
A substation energisation notice, a phase-one handover, a named anchor tenant, or a disclosed capex
All estimates are labelled as estimates. No tender dates claimed, no private contact data published.
Unlock GridFeed →

7Limits and open questions

  • Nothing is built. Ground was broken in January 2026; no capacity, no phase schedule and no tenant is published.
  • Delivery is 2027 or Q1 2028 depending on which operator page is read. Both are live simultaneously.
  • The site is ambiguous. The 2023 announcement describes a five-acre parcel acquired for the third building; the campus is separately described as 5.5 acres. The floor area ratio is 6.4 on the five acres and 5.8 on the campus.
  • No capex is disclosed for 85 MW. Every rupee figure beyond the US$170 million for 32 MW is a Gridvik estimate at a stated rate.
  • 85 MW is IT load as stated by the operator, which is unusual in this registry and rests on the 120 MVA substation inference.
  • The 1.41 ratio assumes a power factor of 1.0. At 0.95 the implied ratio is 1.34, which is conservative rather than exact.
  • A floor area ratio is not a storey count. Five to six storeys is the only design that fits, but the count itself is inferred.
  • What would close it. A phase schedule with megawatts attached to years. Nothing else in this record is missing.

8Sources

Sources: the Iron Mountain MUM-3 and Mumbai location pages; the Iron Mountain Data Centers India platform page; the January 2026 MUM-3 groundbreaking release; Data Center Dynamics on the groundbreaking; W.media; ETTelecom; Communications Today; Structure Research; the Baxtel MUM-3 entry; and the June 2023 Web Werks and Iron Mountain announcement.